
Shares Issued: 151,402,324
THUNDER BAY, ON, Jan. 28, 2014 /CNW/ - PREMIER GOLD MINES LIMITED ("Premier" or "the Company") (TSX:PG) is pleased to announce the results of independent Preliminary Economic
Assessment Studies ("PEA") on the Company's 100%-owned Hardrock and
Brookbank Deposits in Northwestern Ontario. The PEA Studies were
prepared by Stantec Mining with contributions from BBA Inc., InnovExplo
Inc. and Micon International Limited, and completed in accordance with
National Instrument 43-101 ("NI 43-101"). The technical report with
respect to both PEA's will be filed on the Company's website and on
SEDAR within 45 days. The Company has also scheduled a conference call and webcast for
investors and analysts at 1:30 p.m. (Eastern Time) Tuesday, January 28,
2014. Details for the call can be found at the bottom of this press
release.
The Hardrock PEA Study was prepared as an open-pit only mining project
related solely to the mineral resources reported on October 29th, 2013 by the Company (press release "Premier Gold Releases Updated
Mineral Resource Estimate On Hardrock Deposit"), for the Hardrock
Project (a part of the Trans-Canada Property) some 260 kilometres by
highway northeast of Thunder Bay, Ontario just south of Geraldton.
The Brookbank PEA Study was prepared as a combined open-pit and
underground mining project related solely to the mineral resources
reported on December 19th, 2012 by the Company (press release "Premier Gold Releases Trans-Canada
Property Resource Estimates On Four Deposits") for the Brookbank
Deposit. Brookbank is located some 77 kilometres by road and highway
west of the Hardrock Deposit.
Highlights of the 2014 PEA Studies (all currency amounts in Canadian
dollars unless otherwise stated) include:
Hardrock Project Estimates
- Average annual gold production during the first 8 years of 253,100
ounces with life of mine "LOM" (15 years) annual production of 202,700 ounces
(including low-grade stockpiles).
- Average grade over the first 8 years of 1.50 grams per tonne gold "g/t
Au" with a LOM average grade of 1.18 g/t Au (including low-grade
stockpiles).
- Initial processing of 10,000 tonnes per day "tpd", expanding to 18,000 tpd in Year 3.
- Pre-production capital costs of $410.6 million including $83 million for contingency.
- Pre-tax net present value "NPV" (at a 5% discount rate) of $519 million
at US$1250 gold.
- Pre-tax internal rate of return "IRR" of 23.0% and a 3.5 year payback at
US$1250 gold.
Brookbank Project Estimates
- Pre-tax NPV (at 5% discount rate) of $76 million and IRR of 30.7% at
US$1250 gold when rock is trucked to Hardrock versus stand alone processing option.
- Average annual gold production during LOM (7 years) of 48,700 ounces.
Ewan Downie, President and CEO of Premier Gold Mines stated, "The
completion of these PEA's represent a significant milestone for our
technical teams and a very high quality and achievable opportunity for
our shareholders. Economics compare favourably to peer projects and
Premier is well-financed to move the projects aggressively through to
feasibility."
Hardrock Project
Mineral Resources Used In PEA
The Hardrock PEA study assumes that open pit mining only will be used
for resource extraction.This was judged to be the quickest and least risky proposition of
converting resource to reserves and execution. The mineral resource
estimate, as reported on October 29, 2013, excluded the impact of mining dilution, which is the incidence of
waste rock extracted together with mineralized material.
For the PEA, open pit mining dilution is calculated as 5% at 0 g/t gold.
Open pit resources have been calculated assuming a material loss of 5%.
With an open pit cut-off grade of 0.35 g/t gold, the resulting tonnages
and grades for the open pit conceptual mine plan, including planned
low-grade stockpiles, is shown in Table 1.
Table 1 Diluted Open Pit Mineral Resources Used in Hardrock PEA Study
| Cut-off Category | Resource Category | Tonnes (Mt) | Gold (Au) Grade (g/t) | Au Ounces (Moz) |
Open Pit (O/P)
| Indicated
Inferred | 64.663
24.669 | 1.18
1.18 | 2.454
0.938 |
The Hardrock PEA is preliminary in nature and it includes inferred
mineral resources that are considered too speculative geologically to
have the economic considerations applied to them that would enable them
to be categorized as mineral reserves, and there is no certainty that
the Hardrock PEA will be realized.
Mineral resources are not mineral reserves and do not have demonstrated
economic viability. All figures are rounded to reflect the relative
accuracy of the estimate. All assays have been capped where
appropriate.
Mining
The Hardrock PEA assumes the processing of an average 10,000 tonnes per
day of material during the first two (2) years of production, followed
by an expansion to 18,000 tonnes per day in Year 3 for the remainder of
the mine life (13 years), from a combination of direct process open pit
material and stockpile reclaiming operations.
The open pit mine and stockpiling reclaim plan is a 15-year plan that
utilizes a stockpile strategy to maximize grade to the mill and mines
to an ultimate depth of 460 metres below surface.
The Hardrock open pit is designed as a conventional surface mining
operation blasting 30 million tonnes of material per year in the first
two years of operations and 45 million tonnes per year thereafter. The
primary equipment fleet would consist of up to two 27 m3 hydraulic shovels, one 15 m3 hydraulic shovel, one 18 m3 wheel loader, 150 and 250 tonne-class haul trucks, and a fleet of
support equipment. Production drilling will be carried out by up to
five diesel-powered track-mounted units on 203 mm holes. Operating
bench heights of 10 metres have been assumed for mining operations.
Over the life of the open pit, a total of 391 million tonnes of waste
rock and overburden material would be moved. During the pre-production
period, 1.6 million tonnes of overburden and waste rock would be
removed as part of development work. Waste rock-to-mill-feed operating
strip ratio are expected to average 5.37 during mining operations and
4.38 over the life of the mine (including low grade stockpiles and
overburden).
Open pit mining operating costs include mine supervision, drilling,
blasting, loading, hauling, services, dumps, roads and maintenance
costs. These costs were evaluated using data from other similar
projects and from budget quotes provided by suppliers. An extra 38% was
added to the salaries to account for benefits, and depending on the
job, bonuses were also included. Table 2 presents a summary of the
estimated operating costs. A maximum of 207 direct positions have been
estimated for mining requirements based on past experience and industry
averages.
Table 2 Summary by Total, Per Tonne Mined & Per Tonne Milled of
Estimated Hardrock Operating Costs
| Cost Centre | Total Pre-Production Cost | Total Production | Total Project Cost | Unit Cost Per Tonne Mined | Unit Cost Per Tonne Milled |
|
|
| Technical services |
|
|
|
|
|
|
Engineering
|
$440,000.00
|
$17,113,000.00
|
$17,553,000.00
|
$0.04
|
$0.20
|
|
Geology
|
$477,000.00
|
$30,161,000.00
|
$30,638,000.00
|
$0.07
|
$0.34
|
| Mining cost |
|
|
|
|
|
|
Mine supervision
|
$460,000.00
|
$21,279,000.00
|
$21,739,000.00
|
$0.05
|
$0.24
|
|
Drilling
|
$433,000.00
|
$76,744,000.00
|
$77,177,000.00
|
$0.16
|
$0.86
|
|
Blasting
|
$865,000.00
|
$151,550,000.00
|
$152,415,000.00
|
$0.32
|
$1.71
|
|
Loading
|
$230,000.00
|
$44,939,000.00
|
$45,169,000.00
|
$0.10
|
$0.51
|
|
Hauling
|
$551,000.00
|
$247,663,000.00
|
$248,214,000.00
|
$0.52
|
$2.77
|
|
Services
|
$630,000.00
|
$81,360,000.00
|
$81,990,000.00
|
$0.18
|
$0.92
|
|
Dumps & Roads
|
$266,000.00
|
$59,178,000.00
|
$59,444,000.00
|
$0.13
|
$0.67
|
|
Maintenance
|
$1,081,000.00
|
$216,002,000.00
|
$217,083,000.00
|
$0.47
|
$2.43
|
|
Total | $5,433,000.00 | $945,989,000.00 | $951,422,000.00 | $2.04 | $10.65 |
Metallurgy & Processing
Recent metallurgical testing conducted during 2013 on open-pit resource
material served as a basis for the milling flowsheet developed by BBA.
The highlights of the process flowsheet include:
-
Primary crushing and two-stage grinding;
-
Gravity recovery;
-
Whole-rock carbon-in-leach circuit;
-
Cyanide destruction;
- Carbon stripping, electro-winning, and smelting to produce gold doré.
Major equipment for the initial process facility includes a gyratory
crusher sized for 18,000 tpd, a 32' x 14' semi-autogenous ("SAG") mill
and a 20' x 30.5' ball mill. Mill feed would be ground to a P80 of 75 µm before entering a gold leaching circuit. Major requirement
related to the 3rd year expansion to 18,000 tonnes per day include additional crushing,
ball milling, solid-liquid separation units and leach capacity.
Metallurgical recoveries for gold over the life of the mine are
expected to average 89.6%. No by-product credits are anticipated.
Table 3 Estimated Mill Operating Expenses per Tonne Milled
| Cost Centre | 10,000 TPD | 18,000 TPD |
Reagents
|
$ 3.11
|
$ 3.03
|
Consumables
|
$ 3.73
|
$ 3.24
|
Personnel
|
$ 1.68
|
$ 1.06
|
Utilities
|
$ 4.07
|
$ 3.76
|
|
TOTAL
|
$ 12.59
|
$ 11.09
|
The estimated mill operating expenses were based on available reagent
consumptions and additions from testwork, local manpower costs, and
industry standards where applicable. A breakdown of the mill operating
expenses is shown in Table 3. A roster total of 62 workers (increasing
to 71 with the 18,000 tpd expansion) is established for the milling and
assay lab requirements based on past experience and industry averages.
An electrical power cost of $0.08/kWh is assumed for this study.
Infrastructure
The Hardrock Project benefits from world-class infrastructure, services
and available labour within several communities in the immediate area.
The project site is located only 260 km from Thunder Bay, Ontario
(population 108,000), a few kilometres south of Geraldton, Ontario
(population 1,893) and at 32 kilometres west of Longlac (population
1,388) all within the Municipality of Greenstone, and the Long Lac
#58/Ginoogaming (population 600) First Nation Reserves. It resides
along the Trans-Canada Highway and is accessible year-round. The
Trans-Canada natural gas pipeline passes close to the site. Finally,
some infrastructure will need to be relocated to accommodate the
project.
Infrastructure is anticipated to include:
-
Plant site and haul roads, gate house, parking, bus station and weigh
station;
-
Administration building, including all services; engineering, geology,
administration, environment, health and safety, mine supervision, fire
fighting, emergency office (ERT) and human resources;
-
9 door open pit garage and warehouse;
-
Assay lab;
-
Electrical surface infrastructure;
-
Emulsion plant;
-
Fuel storage facilities;
-
Fresh water supply and fire protection;
-
Dewatering and water contact treatment plant;
-
Sewage treatment;
-
One tailings pond;
-
Power to the project supplied by an existing 115-kV transmission line
connected to the provincial grid;
A total of 65 workers have been estimated for the general and
administrative expense (G&A) requirements based on past experience and
industry averages. The G&A costs include, for the operation,
administrative personnel, general office supplies, safety and training
supplies, contracted consultant services, insurance, permits property
taxes, security, camp, building maintenance, environment management,
geology, engineering and all indirect cost. Estimated annual G&A costs
are summarized in Table 4.
Table 4 Annual G&A Cost Estimate for the Hardrock Mine
|
|
Total
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
11
|
12
|
13
|
14
|
15
|
|
Open Pit G&A (M$)
|
48.8
|
4.0
|
4.0
|
4.0
|
4.0
|
4.0
|
3.9
|
3.9
|
3.9
|
3.9
|
3.9
|
3.9
|
3.9
|
1.5
|
0.0
|
0.0
|
|
General G&A (M$)
|
129.5
|
9.2
|
9.7
|
9.8
|
9.8
|
9.8
|
9.8
|
9.8
|
9.8
|
9.8
|
9.8
|
9.8
|
9.8
|
5.7
|
3.5
|
3.4
|
|
Owner Indirects (M$)
|
9.0
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
0.6
|
The base price for the fuel used in calculations is $1.00/ litre.
Capital & Operating Costs
Open pit pre-production capital costs require a minimal overburden and
waste stripping component as the bedrock material to be mined is
already exposed on surface. The breakdown of open pit pre-production,
sustaining capital costs and mill expansion are summarized in Tables 5
and 6 respectively.
Table 5 Hardrock Pre-Production Capital Costs Estimate
| Capital Cost | Pre-Production ($ millions) |
|
Processing Plant (phase 1)
|
$193.2
|
|
Infrastructure and Earthwork
|
$52.7
|
|
Pre-Stripping and Owner's cost
|
$15.4
|
|
Tailings and Water Pipeline
|
$23.7
|
|
Indirects
|
$42.4
|
|
Contingency
|
$83.2
|
| Total Pre-Production Cost | $410.6 |
Table 6 Hardrock Sustaining and Mill Expansion Capital Costs
Estimate
| Capital Cost | LOM Sustaining ($ millions) | Mill Expansion ($ millions) |
|
Processing Plant (phase 2)
|
-
|
$105.1
|
|
Infrastructure and Earthwork
|
$38.5
|
-
|
|
Open Pit Equipment
|
$120.1
|
-
|
|
Tailings and Water Pipeline
|
$42.0
|
$9.0
|
|
Indirects
|
-
|
$18.9
|
|
Contingency
|
-
|
$33.2
|
| Total Cost | $200.6 | $166.2 |
The cash cost profiles on a per ounce and per tonne basis for the
Hardrock Project are summarized in Table 7 and Table 8 respectively.
Table 7 Hardrock Cash Cost Per Ounce Summary
| Cash Cost Summary (oz) | Years 1-8 ($/oz) | LOM (Years 1-12) Without stockpile ($/oz) | LOM (Years 1-15) ($/oz) |
|
Mining
|
291.06
|
320.80
|
302.77
|
|
Processing
|
261.26
|
294.51
|
329.38
|
|
G&A
|
56.17
|
61.40
|
61.60
|
|
Refining
|
4.00
|
4.00
|
4.00
|
| Cash Cost | 612.48 | 680.71 | 697.75 |
|
Royalties
|
39.35
|
39.35
|
39.35
|
| Total Cash Costs | 651.84 | 720.06 | 737.11 |
|
Sustaining Costs
|
85.78
|
69.35
|
66.03
|
| All-in Sustaining Costs | 737.62 | 789.41 | 803.14 |
Table 8 Hardrock Cash Cost Per Tonne Summary
| Cash Cost Summary (t) | Years 1-8 ($/t) | LOM (Years 1-12) Without stockpile ($/t) | LOM (Years 1-15) ($/t) |
|
Mining
|
12.62
|
12.24
|
10.30
|
|
Processing
|
11.32
|
11.24
|
11.21
|
|
G&A
|
2.43
|
2.34
|
2.10
|
|
Refining
|
0.18
|
0.16
|
0.14
|
| Cash Cost | 26.55 | 25.98 | 23.75 |
|
Royalties
|
1.70
|
1.50
|
1.34
|
| Total Cash Costs | 28.25 | 27.48 | 25.09 |
|
Sustaining Costs
|
3.72
|
2.65
|
2.25
|
| All-in Sustaining Costs | 31.97 | 30.13 | 27.34 |
Community
Premier is a proud member of the local Greenstone communities,
participating in a number of local events, initiatives and boards. The
company's community relations office provides members of the public
with the opportunity to engage with the company directly, outside of
regular communications, mailings, and open houses. Additionally,
Premier also has a site office, multiple staff residence properties and
extensive local staff.
Premier regularly engages with local Aboriginal communities, and is
proud of the relationship that has and continues to develop. Premier
utilizes personnel from local Aboriginal communities on the Hardrock
Project, such as representatives from each community as part of the
environmental monitoring team.
Environment
A formal environmental baseline work program has been ongoing since
2011. Since 2013, Premier began more extensive regional monitoring and
assessment work that was undertaken to gain a thorough understanding of
the current environmental conditions in the region, including the
impacts of the Trans-Canada Highway on this former industrial site.
Project Economics
Key economic performance metrics are summarized in Table 9 on both a
pre-tax and after-tax basis. A range of gold prices (US$) are shown
for sensitivity purposes only. At US$1250 gold price, the Hardrock
open pit project has a pre-tax Internal Rate of Return (IRR) of 23.0%
(19.% after-tax), a pre-tax NPV (discounted at 5%) of some $519 million
($359 million after-tax) and a payback of 3.5 years on a pre-tax basis
(3.9 years on an after-tax basis).
Table 10 is a spider graph representing the sensitivity of the change of
any one variable over a range of percentage difference versus the base
case. Of the five variables measured, changes in grade and gold price
have the greatest impact on the NPV (pre-tax) of the project.
Table 9 Pre-tax and After-tax IRR, NPV & Payback Summary
| Pre-tax | US$1050 | US$1250 | US$1450 |
| IRR (%) | 10.3% | 23.0% | 33.6% |
| NPV5% (CA$M) | 128 | 519 | 909 |
| Payback (Years) | 6.2 | 3.5 | 2.8 |
|
|
|
|
|
| After-tax | US$1050 | US$1250 | US$1450 |
| IRR (%) | 8.2% | 19.0% | 27.7% |
| NPV5% (CA$M) | 72 | 359 | 633 |
| Payback (Years) | 7.2 | 3.9 | 2.9 |
Exchange Rate CAN$1.00 = US$ 0.95
Opportunities & Risks
Opportunities to improve Hardrock Project economics include the
following:
-
The Hardrock PEA is based on the August 9, 2013 mineral resource cut-off
date and does not include subsequent infill drilling of some 45,000
metres completed to the end of 2013.
-
The next resource update is planned for Q2/2014 and will include a more
refined underground voids model which could potentially contribute
resource tonnes and ounces previously included at zero grade.
-
Infill assays of previously unsampled drill core will improve the
confidence of the grade estimate in some areas.
-
Refining the litho-structural model by incorporating information gleaned
from historic drilling (not assay data) will improve confidence in the
model constraints.
-
Follow-up drilling in the North Wall area could bring additional mineral
resources into the optimized pit.
-
Completing an underground study to further enhance project economics.
-
Potential improvement in metallurgical recovery
Risks requiring mitigation strategies include:
-
Management of construction/engineering and procurement schedules, costs,
and cost containment.
-
Operating risks related to recruitment and training of open-pit
workforce.
-
Currency risk relating to equipment purchases denominated in US
currency.
-
Permitting risk
Next Steps
Technical
-
Complete infill drill program for revised mineral resource estimate in
2014.
-
Proceed with baseline environmental work for completion by summer 2014
(ongoing monitoring work forecasted for life of mine.
-
Optimization work (testing and engineering) for minimizing capital and
operating costs.
-
Detailed engineering work for final feasibility.
Exploration
-
Renewed focus on regional targets and new deposit discovery.
Community and Environment
-
Complete the baseline environmental and optimization work (testing and
engineering) necessary to ensure a successful environmental assessment
process.
-
Submission of a project description is anticipated in spring 2014 to
federal and provincial governments to begin the formal environmental
assessment processes. This will comprise baseline environmental
information collected over past years, comprises formal public and
aboriginal consultation periods and helps ensure a mine design that
avoids and mitigates environmental impacts.
Qualified Persons
Each of the following individuals is a "qualified person" for the
purposes of NI 43-101. All scientific and technical information in
this press release in respect of the Hardrock Project or the Hardrock
PEA is based upon information prepared by or under the supervision of
such individuals.
Stantec
Michel St. Laurent, P. Eng., (Mining & Environment)
Fiona Christianson, M.Sc. (Environment)
BBA Inc.
Julie Fournier, ing. (Metallurgy & Processing)
InnovExplo Inc.
Carl Pelletier, B.Sc., P.Geo. and Karine Brousseau, P.Eng. (Resource
Estimate)
Sylvie Poirier, ing. (Mining)
Brookbank Project
Mineral Resources Used In PEA
The Brookbank PEA study assumes that open pit and underground mining
will be used for resource extraction. The mineral resource estimate as
reported on December 19, 2012 excludes the impact of mining dilution,
which is the incidence of waste rock extracted together with
mineralized material. For the PEA, open pit mining dilution is
calculated as 25% at 0.22 g/t gold. Open pit resources have been
calculated assuming a material loss of 10%.
Underground excess mining dilution is calculated as 15% at 0.00 g/t gold
after a 27.6% planned internal dilution at 2.5g/t gold. Underground
mining also assumes a material loss of 10%. With open pit and
underground cut-off grades of 1.52 g/t gold (before dilution and mill
recovery) and 4.50 g/t gold respectively, the resulting tonnages and
grades for the open pit and underground conceptual mine plan is shown
in Table 11.For the purpose of this study, it has been assumed that the ore would be
processed at a future Hardrock mill.
Table 11 Diluted Open Pit & Underground Mineral Resources Used for
Brookbank PEA Study
| Deposit | Cut-off Category | Resource Category | Tonnes (Mt) | Gold (Au) Grade (g/t) | Au Ounces (Moz) |
Brookbank |
Open Pit
|
Indicated (I)
|
0.503
|
2.31
|
0.037
|
|
Underground
|
Indicated (I)
|
1.659
|
6.25
|
0.333
|
Mineral resources are not mineral reserves and do not have demonstrated
economic viability. All figures are rounded to reflect the relative
accuracy of the estimate. All assays have been capped where
appropriate.
Mining
The Brookbank PEA assumes the processing of an average 900 tonnes per
day of material from open pit and underground sources during the life
of the mine. Open pit mining (average grade of 2.31 g/t gold) would be
conducted for a period of 2.5 years at 600 tonnes per day in the
beginning of the mine life followed by underground mining operations
(average grade of 6.25 g/t gold) at up to 900 tonnes per day for a
period of 6 years. The waste rock-to-mill-feed operating strip ratio
averages 5 to 1 over the life of the open pit.
Underground mining operations would be accessed via a single portal and
main ramp from surface. The operation would utilize longitudinal
longhole stoping (25-metre sub-levels), with consolidated and
unconsolidated rockfill as a mining method and require up to 4,000
metres of pre-preproduction and sustaining capital development and
some 7,000 metres of operating lateral development (waste and silling)
over the life of the mine.
Metallurgy & Processing
Based on available historical information and test work at Brookbank,
the proposed process flowsheet determined by BBA remains similar to the
historical flowsheet. It includes primary and secondary crushing,
single-stage grinding, CIL, cyanide destruction, carbon stripping,
electrowinning, and refining. As such, Brookbank material would also
be amenable to the proposed Hardrock flowsheet.
A trade-off study was conducted which determined that transporting
Brookbank material to Hardrock for processing and gold recovery
significantly enhances the Brookbank PEA economics when compared to a
stand-alone milling complex for Brookbank rock. No additional
processing facilities are anticipated at Hardrock to facilitate the
Brookbank rock milling.
Infrastructure
The Brookbank Project benefits from world-class infrastructure, services
and available labour within several communities in the immediate area.
The project site is located only 232 kilometres from Thunder Bay,
Ontario (population 108,000) and 28 kilometres northeast of Beardmore,
Ontario (population 400) within the Municipality of Greenstone. It
resides 12 kilometres from the Trans-Canada Highway and is accessible
by road year-round.
Infrastructure at the Brookbank Project is anticipated to include, among
other things, the following facilities:
-
Plant site and haul roads, gate house, parking, bus station and weigh
station;
-
Separate administration building, compressor building;
-
Assay lab, core shack, surface shop;
-
Mine maintenance garage, warehouse;
-
Fuel storage facilities; power distribution;
-
Fresh water supply and fire protection;
-
Sewage treatment;
-
Coarse and fine material storage pads;
-
Non-acid generating waste storage;
Power to the project supplied by electric transmission line connected to
the provincial grid.
Capital & Operating Costs
Total pre-production and sustaining capital cost estimates for both the
open pit and underground portions of the Brookbank Project are
summarized in Table 12.
Table 12 Pre-production and Sustaining Estimated Capital Costs for
Brookbank Open-pit & Underground Mines
| Capital Cost | All LOM ($ millions) |
|
Surface Infrastructure
|
20.3
|
|
Vertical and Horizontal Development
|
33.6
|
|
Underground Infrastructure
|
3.9
|
|
Mobile Equipment
|
21.5
|
|
Indirects
|
6.7
|
|
Contingency
|
20.6
|
| Total Capital Cost | 106.6 |
The estimated cash cost profile for the Brookbank Project is summarized
in Table 13. Operating expenses shown below reflect a blend of
Brookbank and Hardrock operation at a nominal 18,000 tpd.
Table 13 Cash Cost Summary for Brookbank Open-pit & Underground
Mines
| Cash Cost Summary | LOM ($/t) | LOM ($/oz) |
|
Mining
|
32.46
|
205.71
|
|
Processing
|
11.24
|
71.23
|
|
Surface Haulage
|
14.76
|
93.54
|
|
G&A
|
38.68
|
245.09
|
|
Refining
|
0.63
|
4.00
|
| Total Cash Costs | 97.77 | 619.57 |
Community
Premier continues to operate a local office in Beardmore, and has
conducted community meetings as well as outreach efforts to local
Aboriginal communities. While these have been preliminary in nature,
Premier is anticipating continued engagement throughout the development
of this project.
Environment
Environmental information to support a Project Definition and Closure
Plan for the Brookbank site has been collected since 2011. Existing
data consists of quarterly surface water quality and terrestrial and
aquatic wildlife studies.
Project Economics
As alluded to in the Metallurgy and Processing sub-section of this
document, trade-off studies were performed which confirmed that
transporting Brookbank rock material some 77 kilometres to an existing
processing facility at Hardrock realized the greatest economic benefit
for the Brookbank Project.
Key economic performance metrics are summarized in Table 14 on both a
Pre-tax and After-tax basis. A range of gold prices (US$) are shown
for sensitivity purposes only. At US$1250 gold price, the Brookbank
open pit and underground mining project has a pre-tax Internal Rate of
Return (IRR) of 30.7% (24.7% after-tax), a pre-tax NPV (discounted at
5%) of some $76 million ($52 million after-tax) and a payback of 4.3
years on a pre-tax basis (4.4 years on an after-tax basis).
Table 14 Pre-tax and After-tax IRR, NPV & Payback for the Brookbank
Project
Pre-tax | US$1050 | US$1250 | US$1450 |
IRR (%) | 14.0% | 30.7% | 43.6% |
NPV5% (CA$M) | $29 | $76 | $139 |
Payback (Years) | 5.3 | 4.3 | 3.7 |
|
|
|
|
After-tax | US$1050 | US$1250 | US$1450 |
IRR (%) | 9.4% | 24.7% | 38.1% |
NPV5% (CA$M) | $11 | $52 | $87 |
Payback (Years) | 5.6 | 4.4 | 3.8 |
Exchange Rate CAN$1.00 = US$ 0.95
Opportunities & Risks
Opportunities to improve Brookbank Project economics include the
following:
-
Infill assays of previously unsampled drill core will improve the
confidence of the grade estimate in some areas
-
Refining the litho-structural to improve confidence in the model
constraints.
-
Follow-up drilling in at Cherbourg and Foxear to delineate mineral
resources
Risks requiring mitigation strategies include:
-
Management of construction/engineering and procurement schedules, costs,
and cost containment.
-
Operating risks related to recruitment and training of open-pit and
underground workforces.
-
Currency risk relating to equipment purchases denominated in US
currency.
-
Permitting risk
Next Steps
Technical
-
Optimization work (testing and engineering) for minimizing capital and
operating costs
Exploration
-
Renewed focus on regional targets and new deposit discovery
Community and Environment
-
Premier intends to continue to engage with the local Beardmore and
Aboriginal communities on its plans for the Brookbank project. These
will include open houses, direct communications and bilateral
engagements.
Qualified Persons
Each of the following individuals is a "qualified person" for the
purposes of NI 43-101. All scientific and technical information in
this press release in respect of the Brookbank Project or the Brookbank
PEA is based upon information prepared by or under the supervision of
such individuals.
Stantec
Michel St. Laurent, P. Eng., (Mining & Environment)
Helga Sonnenberg (Environment)
BBA Inc.
Julie Fournier, ing. (Metallurgy & Processing)
Micon International Limited
Messrs Alan J. San Martin, MAusIMM(CP) and Charley Murahwi, P.Geo,
FAusIMM. (Resource Estimation)
Live Conference Call and Webcast Access Information
North American callers please dial: 1-888-231-8191
Local and international callers please dial: 647-427-7450
TAPED REPLAY: 416-849-0833 or 1-855-859-2056
Reference number: 49097250
Available until February 28, 2014 at midnight
WEBCAST URL: A live audio webcast will be available at: www.premiergoldmines.com
Premier Gold Mines Limited is one of North America's leading exploration and development companies
with a high-quality pipeline of gold projects focused in proven, safe
and accessible mining jurisdictions in Canada and the United States.
The Company is well financed with a portfolio of advanced-stage assets
in world class gold mining districts such as Red Lake and Geraldton in
Ontario and the most prolific gold trends in Nevada.
This Press Release contains certain information that may constitute
"forward-looking information" under applicable Canadian securities
legislation. Forward-looking information includes, but is not limited
to, statements about strategic plans, including future operations,
future work programs, capital expenditures, discovery and production of
minerals, price of gold and currency exchange rates, timing of
geological reports and corporate and technical objectives.
Forward-looking information is necessarily based upon a number of
assumptions that, while considered reasonable, are subject to known and
unknown risks, uncertainties, and other factors which may cause the
actual results and future events to differ materially from those
expressed or implied by such forward-looking information, including the
risks inherent to the mining industry, adverse economic and market
developments and the risks identified in Premier Gold's annual
information form under the heading "Risk Factors". There can be no
assurance that such information will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such information. Accordingly, readers should not place
undue reliance on forward-looking information. All forward-looking
information contained in this press release is given as of the date
hereof and is based upon the opinions and estimates of management and
information available to management as at the date hereof. Premier Gold
disclaims any intention or obligation to update or revise any
forward-looking information, whether as a result of new information,
future events or otherwise, except as required by law.
SOURCE Premier Gold Mines Limited
Image with caption: "Table 10 - Hardrock Sensitivity Analysis of Significant Parameters (CNW Group/Premier Gold Mines Limited)". Image available at: http://photos.newswire.ca/images/download/20140128_C5557_PHOTO_EN_35946.jpg

<p> Ewan Downie, President & CEO<br/> Phone: 807-346-1390<br/> Fax: 807-346-1381<br/> e-mail: <a href="mailto:Info@premiergoldmines.com">Info@premiergoldmines.com</a> <br/> Web Site: <a href="http://www.premiergoldmines.com">www.premiergoldmines.com</a> </p>