Mr. Hugues Jacquemin reports
NORTHERN GRAPHITE PROVIDES UPDATE ON LAC DES ILES RESTART PLANS
While Northern Graphite Corp. has received authorization to begin mining activities associated with a planned pit expansion at its cornerstone Lac des Iles mine in Quebec, the timing of the restart has been affected by issues relating to its mining lease, financial constraints and current market conditions.
Mining lease
On Aug. 10, 2026, Northern received a notice from the Ministere des Ressources naturelles et des Forets advising of the suspension of the LDI mining lease in connection with an outstanding payment related to an increase in the amount of the financial guarantee sought by the MRNF from the company for the restoration of the site upon completion of its mining activities. The company disagrees with the MRNF's interpretation for calculating the financial guarantee and the applicable deadline for the payment under the Mining Act (Quebec) and its regulations.
Northern has 30 days to contest the MRNF's decision, with a deadline of Sept. 9, 2026. The company intends to contest the decision within the applicable period, and the suspension of the mining lease will be stayed until a final determination is made by the Quebec court. Accordingly, the mining lease will remain in effect until a final judgment is rendered on the issue.
The requirement for additional security arose following approval of the company's updated restoration plan for LDI in November, 2025. Under the updated plan, the total financial guarantee was increased by about $1.8-million, from about $8.2-million to about $10.1-million. The company was requested to pay 50 per cent of the additional security in the form of a $900,000 cash deposit by Feb. 28, 2026, with a further $450,000 due in each of November, 2026, and November, 2027.
Northern does not agree with the MRNF's interpretation for calculating the financial guarantee and the applicable deadline for the payment under the Mining Act (Quebec) and its regulations. It also believes the decision to suspend the mining lease is a disproportionate response by the MRNF.
The MRNF already holds a surety bond of $8,232,941, or more than 80 per cent of the required guarantee, which the company believes covers the first two prescribed instalments. Northern also believes it has until Nov. 28, 2027, to pay the final portion of the guarantee in the amount of $1,829,635 under Section 113 of the regulations under the Mining Act (Quebec). Northern therefore maintains that it is not in default.
"We recognize and take seriously our responsibility to provide financial security for the future restoration of Lac des Iles, and Northern already has provided $8.2-million in security toward those obligations," said Northern chief executive officer Hugues Jacquemin. "However, we do not agree with the interpretation the MRNF has provided in this matter and consider, on the basis of our legal adviser's analysis, that we are not in default, because the final portion of the guarantee should not be payable until Nov. 28, 2027. We intend to contest this decision while continuing to pursue a practical arrangement that protects the environment and preserves the future of the operation."
Authorization and planned restart
Through a separate regulatory process, Northern received authorization from the Ministere de l'Environnement, de la Lutte contre les changements climatiques, de la Faune et des Parcs on July 9, 2026, to begin mining activities associated with a staged pit expansion that has the potential to add up to eight years to the mine life of North America's only graphite mine.
The amended certificate of authorization allows Northern to expand the current pit to the west by 48,000 square metres, to mine down to the 209-metre elevation and excavate up to 2.2 million tonnes of waste rock from the expansion area through April 9, 2027. The company is in the process of doing additional kinetic studies for the MELCCFP to support authorization to mine beyond April 9, 2027, to produce up to 44,000 tonnes of graphite flake over its three-year, phase 1 mining plan.
Northern placed the LDI mine and mill into temporary care and maintenance in November, 2025, to accelerate critical maintenance and development work ahead of the pit expansion and to complete plant upgrades designed to support 24-seven plant operations and help achieve nameplate capacity of 25,000 tonnes per year.
Restart plans follow the receipt of federal and provincial financing to support the staged pit expansion. Work had previously been expected to begin in the third quarter with extraction activities, followed by plant operations once sufficient ore-bearing material had been stockpiled to ensure continuous feed and support stable operating conditions during ramp-up.
Although the mining lease will remain in effect pending a decision of the Quebec court of the company's appeal of the MRNF's decision to suspend the mining lease, and Northern has received the MELCCFP authorization to begin mining associated with its pit expansion, the company is now unlikely to meet its target of restarting mining at LDI during the third quarter of 2026.
Financial constraints and market conditions
Timing of the restart will depend on the company securing sufficient working capital or other financing after a longer-than-anticipated shutdown of LDI placed further pressure on Northern's financial resources. Maintenance and upgrade work on the LDI plant is well advanced, and it, along with a permitted tailings facility, remains important and valuable assets.
As it seeks to control costs and establish a viable path to restarting operations, the company plans to temporarily reduce its LDI work force. The extent and timing of the reduction remain subject to applicable consultation and notification processes.
Additionally, since Northern began preparing for the pit expansion in November, 2025, demand for natural graphite has not developed at the pace expected despite growing geopolitical and supply chain concerns and forecasts of a global graphite deficit by the end of the decade. Accordingly, a restart will also be contingent on the company having adequate visibility into product demand.
The pit expansion is intended to support production approaching LDI's nameplate capacity of 25,000 tonnes per year. Given the higher strip ratio associated with the new mining area, operating at materially lower production levels would not currently be economically viable.
"Receiving the authorization to expand the pit is an important milestone for LDI, but regulatory authorization alone is not sufficient to support a successful restart," said Mr. Jacquemin. "The extended shutdown has depleted financial resources, and we will need to secure sufficient working capital or financing while also having confidence that the market can absorb the level of production required to operate the new pit economically. In the interim, we must make difficult decisions to reduce costs as we work to preserve the operation and establish a sustainable path forward."
Northern will continue to pursue a timely resolution of the mining lease matter while assessing the financing and market conditions required to support a restart. The company will provide further updates as material developments occur.
About Northern Graphite Corp.
Northern is a Canadian, TSX Venture Exchange-listed company that is the only flake graphite miner in North America. Northern is focused on becoming a world leader in producing natural graphite and upgrading it into high-value products critical to the green economy, including anode material for lithium-ion batteries/electric vehicles, fuel cells and graphene, as well as advanced industrial technologies. The company's mine-to-battery strategy is spearheaded by its Battery Materials Group, which has a fully equipped, state-of-the-art laboratory in Frankfurt.
Northern's graphite assets include the Lac des Iles mine in Quebec, where the company plans to boost output to meet growing demand from industrial customers and coming demand from North American battery makers. The company also owns the large-scale, advanced-stage Bissett Creek graphite project in Ontario and the fully permitted Okanjande graphite mine in Namibia, which is currently on care and maintenance, and represents an opportunity to substantially increase graphite production at a lower cost and with a shorter time to market than most competing projects. All projects have battery-quality graphite and are located close to infrastructure in politically stable jurisdictions.
Qualified person
Gregory Bowes, BSc, MBA, PGeo, the chairman of Northern, is a qualified person as defined under National Instrument 43-101, and has reviewed and approved the content of this news release.