Lithium South completes 400 m pumping well at Alba

2024-03-14 11:47 ET - News Release

Mr. Adrian Hobkirk reports

LITHIUM SOUTH COMPLETES 400 METER PUMPING WELL AT ALBA SABRINA

Lithium South Development Corp. has completed the first pumping well at the 2,089-hectare Alba Sabrina claim block located in Salta province, Argentina. The Alba Sabrina claim is the largest of the five, salar-located claim blocks which total 3,287 hectares of the 5,687-hectare Hombre Muerto North lithium project (HMN lithium project) package. Pumping well PW23-AS-02 has been completed to 400 metres of depth and has encountered sand layers as the dominant texture throughout. PW23 AS-02 has been piped and gravelled in preparation for long-term pumping tests, with a screen length of 207 metres.

State-of-the-art down-the-hole geophysics has been completed by Zelandez (Salta, Argentina), a provider of specialized lithium brine technology. A profile of the well was completed and provides valuable insight into the hole potential. Test work completed by Zelandez includes the measurement of conductivity and temperature of well fluid, well calibre measurement, resistivity measurement, radioactivity measurement, ultrasonic wave measurement, and nuclear magnetic resonance of sediment rock/fluid.

Based on this test work, total porosity averaged 21 per cent ranging from 1 per cent to 45 per cent. The specific yield throughout the profile averaged 7 per cent, with maximum values of up to 33 per cent. Based on this information, the technical team plans to install a high-capacity pump capable of extracting brine at a rate of between 40 and 50 litres per second. Hole PW23-AS02 is in a key location and could provide substantial brine for production throughput.

"We are excited to announce the successful drill completion of pumping well PW23-AS-02 to 400 metres of depth," states Adrian Hobkirk, chief executive officer at Lithium South Development. "The geophysical profile conducted by Zelandez confirms the exceptional qualities of this hole location. Once the high-capacity pump test is complete, the company is poised to capitalize on the potential of this claim block."

The technical and scientific information in this press release was reviewed and approved by William Feyerabend, CPG, a consulting geologist and a qualified person under National Instrument 43-101, who also participated in its production.

About Lithium South Development South

Lithium South owns 100 per cent of the HMN lithium project located in Salta and Catamarca provinces, Argentina, in the heart of the lithium triangle. The Salar del Hombre Muerto has a history of lithium production, with Arcadium Lithium (Alkema and Livent merger) in operation for over 25 years, in an area just south of the HMN lithium project. The HMN lithium project is surrounded by a $4-billion (U.S.) lithium development under construction by POSCO (Korea) and the Sal de Vida project under development by Arcadium. Exploration work to date has delineated a National Instrument 43-101 compliant 1,583,200-tonne lithium carbonate equivalent (LCE) resource on the Alba Sabrina, Natalia Maria and Tramo claim blocks, three of five non-contiguous blocks that make up the HMN lithium project. A recent preliminary economic assessment announced on March 4, 2024, delineates the exciting potential of the 15,600-tonne-per-year lithium carbonate project. With pumping well installation under way, Lithium South is transitioning from being a lithium explorer to becoming a lithium developer.