First Quantum warns Cobre power plant low on juice

2023-11-20 10:36 ET - News Release

An anonymous director reports

FIRST QUANTUM PROVIDES UPDATE ON COBRE PANAMA OPERATIONS

First Quantum Minerals Ltd.'s subsidiary, Minera Panama SA (MPSA), has further ramped down operations at Cobre Panama to one remaining ore-processing train. Without shipments arriving at the mine's Punta Rincon port, it expects to run out of supplies for the on-site power plant during the week commencing Nov. 20, 2023.

The continuing presence of an illegal blockade of small boats at the Punta Rincon port continues to prevent the delivery of supplies that are necessary to operate the power plant. Local law enforcement authorities are present and continue to monitor and assess the situation in order to achieve a return to normal maritime operations. If the illegal actions continue to prevent the delivery of supplies necessary to operate the power plant, MPSA will ramp down the remaining processing train this week and temporarily halt production. The safety and well-being of the Cobre Panama work force, of which approximately 90 per cent are Panamanian and have been trained and developed by First Quantum, are the company's priority.

With respect to the lawsuits admitted by the Supreme Court of Panama alleging the unconstitutionality of the recently enacted Law 406, which approved MPSA's revised concession contract, the Secretary General of the Supreme Court has stated that plenary sessions of the court will sit from Nov. 24, 2023, and remain in session until a ruling is delivered in the shortest possible time frame.

The company also reports that MPSA, in accordance with its contractual obligations to Panama, made a tax and royalty payment on Nov. 16, 2023, of $567-million (U.S.) in respect of the period from December, 2021, to October, 2023. This payment is one of the largest-ever tax and royalty payments in the history of the global copper mining sector and is the largest fiscal payment ever made in Panama.

Further to these significant tax and royalty payments, the mine accounts for over 2 per cent of Panama's total working population and makes payments to Panamanian suppliers of almost $20-million (U.S.) a week. The overall economic contribution of the mine to the state of Panama is estimated at more than $50-million (U.S.) per week, equivalent to around 5 per cent of annual GDP (gross domestic product), if the mine is able to continue operations.

First Quantum wishes to reiterate its willingness to open new forums of dialogue to address the concerns of diverse sectors of society, in order to create lasting relationships based on respect, cordiality, understanding and mutual benefit. The company continues to reserve all its local and international legal rights in regard to developments in Panama.

Further information about Cobre Panama

For the past 25 years, MPSA has developed and operated the Cobre Panama mine. The development of the mine has been governed by a concession agreement contract first signed by Panama and MPSA in February, 1996, and approved by Law 9 by the National Assembly in February, 1997. On the basis of that contract, Cobre Panama has invested $10-billion (U.S.) in the mine and associated infrastructure, including a power plant, cross-country transmission lines, roads and a port.

Cobre Panama has also developed substantial community outreach and environmental mitigation programs, both during the construction phase of the mine and since commercial operations commenced in September, 2019. The mine is governed by an environmental and social impact assessment approval which stipulates 371 obligations in regard to stewardship of the mine, communities and the environment; for example, the requirement to provide continuing reforestation of 11,175 hectares of forest in Panama. To date, the mine has impacted around 3,000 hectares for mining activities whilst it has completed reforestation of approximately 4,200 hectares throughout Panama, and provides support programs for more than 200,000 hectares of protected areas, almost 20 per cent of Panama's total protected areas.

Following a Supreme Court decision in late 2017 and at the request of Panama, MPSA engaged in an extensive process to renegotiate the terms of the concession agreement, which took more than two years. The company and Panama agreed to a new concession agreement contract in March, 2023, which, following due public consultation and regulatory sign-off, was approved by Law 406 by the National Assembly on Oct. 20, 2023.

We seek Safe Harbor.