Recent Sedar Documents

E3 Lithium completes DLE tech testing at pilot plant

2023-11-07 12:44 ET - News Release

Mr. Chris Doornbos reports

E3 LITHIUM OUTLINES THE PERFORMANCE OF ITS DLE PILOT AGAINST KPIS

E3 Lithium Ltd. has completed field testing of its proprietary direct lithium extraction (DLE) technology at its pilot plant. E3 Lithium provides an overview of the results below, which have met and exceeded its Key Performance Indicators (KPIs).

E3 Lithium's DLE Test Results

The table below outlines a summary of E3 Lithium's DLE full results.

Results Discussion

E3 Lithium's DLE system has demonstrated to achieve a high lithium recovery at much higher flow rate ratios. A higher flow rate ratio can have a significant positive economic impact on the design of a commercial facility for a given recovery. The concentration of lithium and that of the impurities varied throughout the testing based on what the system was testing for, represented here with some indicative results from the testing. However, the relative impurities generally have a smaller impact on the potential costs. The information gathered enables E3 Lithium to continue to optimize to refine the quality of E3 Lithium's DLE concentrate, and it is anticipated the team will improve the purity of the concentrate.

"In addition to the third-party results we've outlined previously, E3 Lithium's proprietary DLE's performance surpassed our expectations," said Chris Doornbos, President & CEO of E3 Lithium. "The field pilot plant has operated exactly as intended since its commissioning in August. Total testing has consumed more than 500 m3 of brine produced from the well at the pilot location, providing us with the data needed for the commercial design and a deep understanding of the performance of various DLE technologies on our brine resource."

Next Steps

The Company plans to continue testing an additional third-party technology through the remainder of 2023 and likely into early 2024. E3 Lithium is reviewing the results from the two DLE systems already tested and will compare them with the results of the third system once complete to determine the cost implications of integrating them into the full process flow sheet.

With the positive results from these two systems now complete, the Company has paused site operations and will continue testing the third system off-site to realize the cost savings associated with avoiding winter operations. Given the learnings and success from the field pilot plant thus far, the Company can execute an off-site pilot with similar operating conditions and quality of data with the additional benefit of cost savings.

Based on the results of testing, commercial readiness of the systems and a fulsome understanding of the associated economics, the Company will decide which technology to pursue for its first commercial facility. The Company continues to work through the full process design for its Pre-Feasibility Study (PFS). The fulsome project economics will be outlined within the PFS, taking into account the DLE results and other process factors to produce a final battery quality lithium hydroxide.

ON BEHALF OF THE BOARD OF DIRECTORS

Chris Doornbos, President & CEO

E3 Lithium Ltd.

About E3 Lithium

E3 Lithium is a development company with a total of 16.0 million tonnes of lithium carbonate equivalent (LCE) Measured and Indicated and 0.9 million tonnes LCE Inferred mineral resources1 in Alberta. As outlined in E3's Preliminary Economic Assessment, the Clearwater Lithium Project has an NPV8% of USD 1.1 Billion with a 32% IRR pre-tax and USD 820 Million with a 27% IRR after-tax1. E3 Lithium's goal is to produce high purity, battery grade lithium products to power the growing electrical revolution. With a significant lithium resource and innovative technology solutions, E3 Lithium has the potential to deliver lithium to market from one of the best jurisdictions in the world.

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.