19:20:19 EDT Wed 23 Sep 2026
Enter Symbol
or Name
USA
CA



Electric Metals (USA) Ltd
Symbol EML
Shares Issued 201,883,424
Close 2026-09-23 C$ 0.18
Market Cap C$ 36,339,016
Recent Sedar+ Documents

Electric Metals finds North Star's FEL-1 cost at $452M

2026-09-23 16:40 ET - News Release

Mr. Brian Savage reports

ENGINEERING COST STUDY VALIDATES COMMERCIAL-SCALE U.S. HPMSM CAPITAL COST AND ESTABLISHES EMM CAPITAL COST FOR ELECTRIC METALS' NORTH STAR MANGANESE PROJECT

Electric Metals (USA) Ltd. has released the positive results of a front-end loading 1, Class 5, costing study for the planned Gulf coast processing facility of the company's North Star manganese project. Hargrove Engineers and Constructors of Mobile, Ala., completed the study.

The chemical facility is designed to process manganese ore concentrate shipped by rail from the company's Emily, Minn., project and produce high-purity manganese sulphate monohydrate through a leaching, purification and crystallization circuit.

FEL-1 study highlights:

  • The FEL-1 study was designed to provide a higher level of engineering analysis and costing than the preliminary economic assessment. While comparable with the 2025 PEA, it did not reassess the economics of the NSMP -- that will be conducted as additional project improvements are incorporated into a new National Instrument 43-101 technical report.
  • The FEL-1 total installed cost of $452-million for a full-production HPMSM facility producing 200,000 tonnes per year of HPMSM compares favourably with $464-million in the company's 2025 preliminary economic assessment, representing a cost saving of approximately 3 per cent.
  • Estimate developed using Aspen capital cost estimator software from a conceptual plant layout, preliminary equipment list and preliminary plot plan with the facility occupying fewer than 40 acres.
  • The estimate incorporates a 20-per-cent contingency and a 5-per-cent escalation allowance in accordance with AACE Class 5 estimating guidelines, providing additional conservatism at this stage of engineering. The PEA used a 25-per-cent contingency.
  • The estimated 32-month schedule from the start of detailed design to mechanical completion and start-up positions the company to reach start-up readiness within just over 2-1/2 years of a final investment decision. The PEA estimated 36 months to reach full production.
  • The proposed location on the U.S. Gulf coast will provide access to river and port logistics, rail infrastructure, and processing chemical feedstocks from petrochemical plants, a specific site has not yet been selected.

Comparison with the 2025 PEA

The FEL-1 study announced today reflects a more detailed level of engineering definition than the PEA. The PEA and FEL-1 study were prepared about a year apart by different engineering firms, and both have a cost-estimated accuracy of plus or minus 50 per cent.

"Hargrove's FEL-1 capital estimate for the full-scale commercial 200,000-tonne-per-year HPMSM facility is approximately 3 per cent below the PEA estimate, validating the earlier capital estimate and further supporting the PEA economics," said Brian Savage, chief executive officer of Electric Metals.

"For more than five decades, the United States has relied entirely on imported manganese in all forms, including ores, concentrates, advanced chemicals, and metals and metal alloy additives. The country has no primary manganese production and only limited intermediate processing capacity. Because manganese has few viable substitutes in most uses and global recycling averages just 9 per cent, this dependence creates a major strategic vulnerability across defence, aerospace, power generation, batteries, electronics, infrastructure, transportation, and other industrial and consumer sectors."

"With the United States designating manganese a critical mineral and relying on imports for all of its manganese sulphate, the engineering study reinforces the strategic urgency of building dedicated domestic capacity to secure our supply chains. We're moving directly into the next phase of engineering, with continued updates on the North Star manganese project's path to production."

FEL-1 study scope

The study's scope for the processing plant included a preliminary basis of design, heat and material balance, process flow diagrams, a process equipment list with major equipment pricing, a plot plan, and a site sketch. Using this conceptual layout of the plant's footprint and major equipment, Hargrove derived quantity-based estimates for materials such as concrete, cable and piping, producing plus-or-minus-50-per-cent total installed cost estimates, including contingency, for both a 100,000-tonne-per-year HPMSM and a 200,000-tonne-per-year HPMSM facility. Site size, raw material and product storage capacity, and utility capacity were sized from the outset to accommodate the higher production rate, such that scaling to the expansion case is expected to require minimal incremental capital investment and time.

Mine site development and transload infrastructure associated with the company's proposed Minnesota and Gulf coast operations were outside of the scope of this study and will continue to be evaluated separately. The Gulf coast site selection and associated permitting will advance in parallel with subsequent engineering phases.

The FEL-1 study was designed to provide a higher level of engineering analysis and costing than the PEA, and, while comparable with the 2025 PEA, it did not reassess the economics of the North Star manganese project that will be conducted as additional project improvements are incorporated into a future National Instrument 43-101 technical reports.

Preliminary EMM capital cost estimate

In addition to preparing an FEL-1 engineering costing study for both a 100,000-tonne-per-year HPMSM and a 200,000-tonne-per-year HPMSM chemical plant, Hargrove separately evaluated the capital cost of integrating a 10,000-tonne-per-year EMM circuit at the same facility.

The FEL's study's scope for the EMM circuit included a preliminary design, heat and material balance, process flow diagrams, a process equipment list and pricing, a plot plan, and a site sketch, for a 10,000-tonne-per-year EMM line within the full chemical facility complex. The EMM circuit was designed as an add-on facility to the HPMSM chemical plant. The FEL-1 installed cost estimates for the EMM plant, siting, storage, utility infrastructure and plant buildout were estimated at $98.6-million (U.S.), and the EMM line construction was assumed to be in association with the development of an HPMSM plant, saving costs on infrastructure development, including concrete, steel, cable and piping.

The FEL-1 work on the EMM plant did not assess its economic impact on the North Star manganese project -- it was solely prepared to generate initial installed cost information for an integrated EMM plant to be used in future studies that will be conducted as additional project improvements are generated and incorporated into future NI 43-101 technical reports.

Manganese -- critical to U.S. defence and national security

Manganese is a critical mineral essential to U.S. defence, aerospace, steel, battery, energy and industrial supply chains. The U.S. relies 100 per cent on imports for manganese while China controls about 96 per cent of global high-purity manganese sulphate processing and 98 per cent of electrolytic manganese metal processing.

Manganese is essential to steel and specialty alloys used throughout the defence industrial base, including in armour and military vehicles, aircraft and aerospace components, naval applications, munitions, and other high-strength military applications. HPMSM is also an important input for manganese-bearing lithium-ion-battery chemistries used in electrification, energy storage and increasingly in defence systems requiring advanced battery technologies.

This dependence on foreign supply has elevated manganese to a U.S. national security priority. The federal government has identified manganese as an essential material for defence and civilian battery applications, and has prioritized developing secure domestic critical mineral supply chains to reduce reliance on foreign sources. More broadly, federal policy identifies secure supplies of critical minerals and materials as essential to military applications, including aircraft, munitions, armour plating and naval ships, reinforcing the strategic importance of establishing secure domestic sources of manganese and other critical materials.

Qualified person

The scientific and technical information in this news release has been reviewed and approved by Donald Hulse, SME-RM, of Frenchman Creek Consultants LLC, who is a qualified person under NI 43-101.

About Electric Metals (USA) Ltd.

Electric Metals is a United States-domiciled critical mineral and advanced material company advancing the North Star manganese project in Minnesota, host to the Emily manganese deposit, the highest-grade manganese deposit in North America. The company's strategy is to build an integrated, domestic manganese supply chain, from mine to battery grade, high-purity manganese sulphate monohydrate and electrolytic manganese metal, serving U.S. battery, defence, aerospace, drone, steel and industrial customers. Electric Metals trades on the TSX Venture Exchange under the symbol EML and on the OTCQB under the symbol EMUS.

We seek Safe Harbor.

© 2026 Canjex Publishing Ltd. All rights reserved.