First Quantum produces 427,655 t Cu in 2014

2015-01-26 22:46 ET - News Release

Mr. G. Clive Newall reports

FIRST QUANTUM MINERALS ANNOUNCES ITS 2014 PRODUCTION AND SALES AND 2015 PRODUCTION AND CAPITAL EXPENDITURE OUTLOOK

First Quantum Minerals Ltd. has released its production and sales results for the three months and year ended Dec. 31, 2014, and its production and capital expenditure outlook for the full-year 2015.

Chief executive officer's comments

"Over all, our operations performed well in 2014, recording the highest annual copper production in the company's history. Limited local smelter capacity in Zambia persisted and affected Kansanshi's performance and sales, and a structural failure in an atmospheric leach tank at Ravensthorpe suspended operations there in mid-December. The spill from the failure was contained within the plant's protective area, there were no environmental effects or injuries, and we anticipate the mine will be back in production shortly.

"Two thousand fifteen is an important year for First Quantum. Our smelter in Zambia is being commissioned with first anodes poured during December, 2014. First concentrate was also successfully produced at Sentinel during the fourth quarter 2014. The smelter's ramp-up will influence the rate of production buildup of our new Sentinel mine. This will also influence, as more acid becomes available, the level and mix of operations and unit cost of production at Kansanshi.

"The financial and commodity markets have started 2015 with high volatility on concerns about the global economy, demand for natural resources and companies' liquidity positions. As a result, our share price, along with others in the sector, has been materially affected. While we have high confidence in the mid to long-term outlook for copper, we are mindful of the current concerns. As always, we pay close attention to the company's financial position to make sure there is sufficient flexibility despite having an active project development pipeline. At Cobre Panama, we have substantially reduced the planned capital expenditure for 2015 to $600-million without compromising the project's progress. We also maintain strong and supportive relationships with our principal banks that have worked with us throughout the development of the company and through several economic and commodity cycles," noted Philip Pascall, First Quantum's chief executive officer and chairman.

Full-year 2014 highlights:

  • Production for copper, nickel, gold and zinc was all within the company's previously announced market guidance range while platinum and palladium were above:
    • Copper increased 4 per cent to 427,655 tonnes.
    • Nickel decreased 3 per cent to 45,879 tonnes.
    • Gold decreased 7 per cent to 229,813 ounces.
    • Zinc increased 12 per cent to 55,980 tonnes.
    • Platinum increased 12 per cent to 34,090 ounces.
    • Palladium increased 5 per cent to 25,990 ounces.
  • Sales of copper and zinc were higher while nickel and gold were lower compared with 2013:
    • Copper increased 7 per cent to 411,203 tonnes.
    • Nickel decreased 3 per cent to 47,749 tonnes.
    • Gold decreased 6 per cent to 214,104 ounces.
    • Zinc increased 8 per cent to 56,268 tonnes.

                  FOURTH QUARTER AND YEAR PRODUCTION SUMMARY

                                         Q4        Q4         Year      Year
                                       2014      2013         2014      2013

Copper (tonnes)                     105,176   114,791      427,655   412,281
Nickel (contained tonnes)             9,934    12,634       45,879    47,066
Gold (ounces)                        57,480    63,199      229,813   248,078
Zinc (tonnes)                        12,557    15,393       55,980    49,933
Platinum (ounces)                     9,311     7,993       34,090    30,403
Palladium (ounces)                    7,234     6,600       25,990    24,639

                    FOURTH QUARTER AND YEAR SALES SUMMARY

                                         Q4        Q4         Year      Year
                                       2014      2013         2014      2013

Copper (tonnes)                      94,836    95,598      411,203   386,057
Nickel (contained tonnes)            12,189    13,795       47,749    49,105
Gold (ounces)                        48,608    50,399      214,104   228,962
Zinc (tonnes)                        12,663    17,866       56,268    51,925
Platinum (ounces)                     8,330    11,375       33,898    28,930
Palladium (ounces)                    6,256     8,167       25,846    23,420

     FOURTH QUARTER AND YEAR PRODUCTION AND SALES SUMMARIES BY MINE

                                          Q4        Q4         Year      Year
Kansanshi                               2014      2013         2014      2013
Production
Copper (tonnes)                       61,924    72,602      262,287   270,724
Gold (ounces)                         36,705    43,508      154,431   167,395
Sales
Copper (tonnes)                       52,721    57,692      247,312   248,746
Gold (ounces)                         27,731    36,844      142,609   152,632

                                          Q4        Q4         Year      Year
Las Cruces                              2014      2013         2014      2013
Production
Copper (tonnes)                       17,525    18,346       71,090    69,304
Sales
Copper (tonnes)                       15,594    16,883       71,120    66,806

                                          Q4        Q4         Year      Year
Guelb Moghrein                          2014      2013         2014      2013
Production
Copper (tonnes)                        9,768     8,866       33,079    37,970
Gold (ounces)                         13,901    13,336       48,948    58,191
Sales
Copper (tonnes)                        8,519     6,327       30,095    36,585
Gold (ounces)                         13,421     8,281       45,901    56,040

                                          Q4        Q4         Year      Year
Ravensthorpe                            2014      2013         2014      2013
Production
Nickel (contained tonnes)              7,736    10,244       36,445    38,103
Sales
Nickel (contained tonnes)              9,912    10,142       37,981    40,612

                                          Q4        Q4         Year      Year
Kevitsa                                 2014      2013         2014      2013
Production
Nickel (contained tonnes)              2,197     2,390        9,433     8,963
Copper (tonnes)                        4,101     4,015       17,535    14,775
Gold (ounces)                          3,093     3,008       12,844    11,723
Platinum (ounces)                      9,311     7,993       34,090    30,403
Palladium (ounces)                     7,234     6,600       25,990    24,639
Sales
Nickel (contained tonnes)              2,277     3,652        9,768     8,493
Copper (tonnes)                        5,545     2,938       19,542    12,652
Gold (ounces)                          3,229     1,182       10,876     7,358
Platinum (ounces)                      8,330    11,375       33,898    28,930
Palladium (ounces)                     6,256     8,167       25,846    23,420

                                          Q4        Q4         Year      Year
Cayeli                                  2014      2013         2014      2013
Production
Copper (tonnes)                        7,820     7,538       29,360    31,510
Zinc (tonnes)                          8,513     9,837       36,218    43,097
Sales
Copper (tonnes)                        8,419     7,940       29,241    31,370
Zinc (tonnes)                          9,362    12,179       37,298    43,354

                                          Q4        Q4         Year      Year
Pyhasalmi                               2014      2013         2014      2013
Production
Copper (tonnes)                        4,038     3,422       14,304    14,854
Zinc (tonnes)                          4,043     5,556       19,762    21,679
Sales
Copper (tonnes)                        4,038     3,819       13,894    15,221
Zinc (tonnes)                          3,300     5,687       18,970    22,339

Production and sales numbers are preliminary and subject to final adjustment.
Production and sales numbers for Las Cruces, Cayeli and Pyhasalmi for year 
2013 are on a pro forma full-year basis.

                          FULL-YEAR 2015 OUTLOOK

                    Copper   Nickel     Gold     Zinc  Platinum  Palladium
                     (000s    (000s    (000s    (000s     (000s      (000s
                    tonnes)  tonnes)  ounces)  tonnes)   ounces)    ounces)

Total              410-440    32-40  218-247    40-45     25-35      26-29
Kansanshi          250-265       --  150-170       --        --         --
Las Cruces           69-72       --       --       --        --         --
Guelb Moghrein       40-45       --    52-57       --        --         --
Ravensthorpe            --    24-30       --       --        --         --
Kevitsa              16-18     8-10    11-13       --     25-35      26-29
Cayeli               24-27       --       --    22-25        --         --
Pyhasalmi            11-13       --      5-7    18-20        --         --

Full-year 2015 outlook highlights:

  • In addition to the attached full-year 2015 outlook, total physical production at Sentinel in 2015 is expected to be between 150,000 and 200,000 tonnes of copper. Sentinel is performing well in the commissioning phase and ramping up as planned toward commercial operation midway through 2015.
  • Total capital expenditure, excluding capitalization of any precommercial production costs and capitalized interest, is estimated to be between $1.2-billion to $1.4-billion.