16:05:46 EDT Thu 25 Apr 2024
Enter Symbol
or Name
USA
CA



Eldorado Gold Corp
Symbol ELD
Shares Issued 794,010,680
Close 2018-04-26 C$ 1.21
Market Cap C$ 960,752,923
Recent Sedar Documents

Eldorado earns $8.71-million (U.S.) in Q1 2018

2018-04-26 17:39 ET - News Release

Mr. George Burns reports

ELDORADO GOLD REPORTS 2018 FIRST QUARTER FINANCIAL AND OPERATING RESULTS

Eldorado Gold Corp. has released its financial and operational results for the first quarter ended March 31, 2018.

Highlights from the Quarter and Subsequent Period 1

  • Hellas Gold S.A., Eldorado's Greek subsidiary, received a positive ruling in the arbitration proceedings with the Greek Government, and will continue to seek a collaborative dialogue with the Greek government.
  • Completed and filed technical reports for the Lamaque, Kisladag and Skouries projects. These technical reports were prepared pursuant to Canadian Securities Administrators' National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI-43-101").
  • Installation of the additional filter press and paste plant completed at Olympias Phase II bringing the plant up to its run rate production of 1,250 tonnes per day.
  • The Company held $459.7 million in cash, cash equivalents and term deposits, and $250.0 million in undrawn lines of credit at the end of the quarter.
  • Profit attributable to shareholders of $8.7 million ($0.01 per share), compared to profit attributable to shareholders of $6.8 million ($0.01 per share) in the first quarter 2017.
  • Gold production of 89,374 ounces, (including 2,740 ounces from Lamaque pre-commercial production) (first quarter 2017: 75,172 ounces).
  • Gold revenues of $115.4 million (first quarter 2017: $90.5 million) on sales of 86,587 ounces at an average realized gold price of $1,333 per ounce (first quarter 2017: 74,068 ounces at $1,222 per ounce).
  • All-in sustaining cash costs averaged $878 per ounce (first quarter 2017: $791 per ounce).
  • Cash operating costs averaged $571 per ounce (first quarter 2017: $466 per ounce).
  • Cash generated from operating activities before changes in non-cash working capital was $37.9 million (first quarter 2017: $28.2 million).

1 Throughout this press release we use cash operating cost per ounce, all-in sustaining cash cost per ounce, and cash flow from operating activities before changes in non-cash working capital as additional measures of Company performance. These are non-IFRS measures. Please see our MD&A for an explanation and discussion of these non-IFRS measures. All dollar amounts in US$, unless stated otherwise.

"We had a very successful first quarter maintaining operational momentum and laying a clear path forward for long-term growth," said George Burns, Eldorado's President and Chief Executive Officer. "The filing of the technical reports was a crucial first step towards delivering on our prioritized development projects, Lamaque and the Kisladag mill. Given our current liquidity and anticipated capital deployment for 2018 and 2019, we have time to evaluate and implement an appropriate long-term financing plan to deliver these investments."

"Operationally, production was in-line with plans. We removed the tailings bottleneck at Olympias with the installation of a second tailings filter press. We also made good progress at our Lamaque project, including advancing refurbishment of the Sigma mill and continuing underground development at the Triangle deposit. At Kisladag, we are transitioning to right size the workforce to support leaching of the pad inventory and mine pre-stripping as we advance permitting and complete a feasibility study to position this asset for the next phase of growth."

"We are now in the delivery phase of our new business plan. By focusing on the disciplined build of Lamaque and the Kisladag Mill while maintaining a strong base of operations at Efemcukuru and Olympias Phase II, I am confident we will re-establish annual low cost production of 600,000 ounces by 2021. Skouries remains a compelling project, providing additional long-term growth, but requires collaborative government dialogue and a clear line of sight to cash flow in order for us to allocate further capital for development. We remain focused on driving forward our industry-leading growth projects under a disciplined capital allocation framework to create long-term value for all stakeholders."

                Summarized Quarterly Financial Results
  
  
   ($ millions unless otherwise noted)               3 months ended March 31
                                                          2018       2017

Revenues                                                 131.9      111.9
Gold revenues 1                                          115.4       90.5
Gold sold (ounces)                                      86,587     74,068
Average realized gold price ($/ounce)                    1,333      1,222
Cash operating costs -- gold mines ($/ounce)                571        466
Total cash costs -- gold mines ($/ounce)                    598        483
All-in sustaining cash cost -- gold mines ($/ounce)         878        791
Gross profit from gold mining operations                  34.7       37.0
Cash flow from operating activities 2                     37.9       28.2
Adjusted net earnings                                     14.0        8.0
Net profit 3, 4                                            8.7        6.8
Earnings per share -- basic ($/share) 3                    0.01       0.01
Earnings per share -- diluted ($/share) 3                  0.01       0.01

(1)Including market to market price adjustments on provisional sales.
(2)Before changes in non-cash working capital.                       
(3)Attributable to shareholders of the Company.                      
(4)2017 net profit is from continued operations.                     

Review of Quarterly Financial Results

Profit attributable to shareholders of the Company was $8.7 million compared to $6.8 million from continued operations for the first quarter of 2017. Gross profit from gold mining operations was $34.7 million compared to $37.0 million for the first quarter of 2017. Higher sales volumes and prices were offset by higher operating costs and depreciation, depletion and amortization ("DD&A") expense. Higher sales volumes were driven by sales from the newly commissioned Olympias mine as well as higher sales at Efemcukuru and Kisladag as compared to 2017.

Total cash costs per ounce increased year over year at both Efemcukuru and Kisladag with the increase at Kisladag being driven by the decrease in leach pad ounces as a result of an adjustment made in October 2017 as well as higher cyanide and lime costs. Olympias total cash costs were $734 per ounce and trending down over the quarter as issues encountered during commissioning in 2017 were resolved. DD&A expense was higher due to the start of commercial production at Olympias as well as an increase at Kisladag related to the leach pad adjustment. Stratoni gross profit fell $4.2 million year over year as a result of lower ore throughput.

General and administrative expenses were $3.4 million lower year over year mainly due to lower employee payroll costs. Share based compensation expense was $3.6 million lower due to a postponement of the grant of options to employees as the Company was in blackout. Interest expense was $2.5 million higher as the Company is no longer capitalizing bond interest related to Olympias now that it is in commercial production.

Stratoni and Certej were impaired in previous years. Under IFRS any expenditures on these projects are capitalized and subsequently written-off in the same period. The Company recorded $4.0 million in asset write-downs related to these two projects.

Operations Review

TURKEY

Kisladag

Production at Kisladag in the first quarter was 53,814 ounces of gold which was within guidance. This was higher than the previous year (52,644 ounces in the first quarter 2017) as adjusted cyanide concentrations coupled with increased irrigation volumes resulted in increased amounts of gold extracted from the pad. Kisladag reported a reduction in ore tonnes to the leach pad in the quarter (2.8 million tonnes in the first quarter 2018 versus 3.2 million tonnes in the first quarter 2017), due to the elimination of run of mine ("ROM") ore. The average ore grade in the quarter was 1.14 grams per tonne versus 1.13 grams per tonne in the first quarter 2017. Moving forward we expect gold production to decrease as no new material will be placed on the pad over the remainder of 2018 while the Company continues to evaluate feasibility of mill construction. Including the production reported in this quarter, the Company expects to recover 160,000-180,000 ounces for 2018-2019 from continued leaching of previously stacked ore.

Cash operating costs were within guidance at $576 per ounce ($446 per ounce in the first quarter 2017), but were higher year over year, due to increased lime and cyanide costs as well as the impact on average inventory unit carrying costs of a 40,000 ounce negative adjustment to estimated recoverable ounces remaining in the leach pad, which was recognized in October 2017.

Sustaining capital spending during the quarter of $7.5 million was related to waste stripping and site construction projects.

During the quarter, the Company filed a pre-feasibility study on the mill project at Kisladag. The report outlined Proven and Probable reserves of 3.1 million contained ounces at 0.82 grams per tonne of gold to support a nine year mine life with average annual production of 270,000 ounces of gold at an all-in sustaining cost ("AISC") of $778 per ounce. At an assumed gold price of $1,300 per ounce the project is expected to generate an estimated after-tax project net present value of $434 million at a 5% discount rate, an internal rate of return of 22.1%, and a payback period of 3.7 years.

Efemcukuru

During the quarter, gold production at Efemcukuru of 22,855 ounces of gold (22,528 ounces in the first quarter 2017) was higher year on year with slightly higher processed tonnage (124,300 tonnes in the first quarter 2018 versus 115,800 tonnes in the first quarter 2017). Gold ounces sold were higher due to some carry over of 2017 gold production sold in 2018. The average ore grade in the quarter was 6.47 grams per tonne versus 6.77 grams per tonne in the first quarter 2017. Cash operating costs of $532 per ounce increased slightly ($515 per ounce in the first quarter 2017).

Sustaining capital spending in the quarter of $3.7 million included underground development, mine equipment overhauls, an upgrade to the water treatment plant and construction projects.

GREECE

On September 14, 2017, Hellas Gold received formal notice from the Greek Ministry of Finance and the Ministry of the Environment and Energy initiating Greek domestic arbitration proceedings. The arbitration proceedings concluded on April 4, 2018 with a positive ruling for the Company. The Panel's ruling rejected the Greek State's motion that the technical study for the Madem Lakkos metallurgy plant for treating Olympias and Skouries concentrates, as submitted by the Company's Greek subsidiary Hellas Gold S.A. in December 2014, was in breach of the provisions of the Transfer Contract. The Company and Hellas Gold are continuing to engage with the Greek government in order to find a mutually-agreeable path forward with respect to its Kassandra investments.

Olympias

In the first quarter 2018, Olympias produced 9,965 ounces of gold at cash operating costs of $699 per ounce of gold, costs were higher than guidance. Olympias began plant commissioning during the second quarter of 2017 and declared commercial production at the end of 2017. The plant was restricted to two-thirds of design throughput due to tailings filtration capacity constraints. This resulted in lower tonnage processed for much of the first quarter and higher per ounce costs.

During the quarter, the second filter press was successfully installed and commissioned, which will allow the plant to reach its design throughput of 1,250 tonnes per day. Due to timing of concentrate shipments, gold sales for the quarter totaled 5,748 ounces of commercial production (versus 9,965 produced) and cash operating costs are calculated based on these ounces only. We expect costs to come down as mill throughput increases.

Capital expenditures of $11.7 million included $2.6 million of sustaining capital on underground development, mine equipment overhauls and waste rock/tailings facilities construction projects. The remaining $9.1 million was related to mine construction costs including the completion of the paste plant and installation of the new tailings filter press as well as capitalized operating costs related to the concentrate attributable to the pre-commercial period of production.

Stratoni

Concentrate production at Stratoni was lower year on year (8,565 tonnes in 2018 vs 11,599 tonnes in 2017). This was due to decreased mill throughput (38,000 thousand tonnes in the first quarter 2018 vs 44,600 thousand tonnes in the first quarter 2017), lower zinc grades (8.8% in the first quarter 2018 versus 10.5% in the first quarter 2017) and lower lead grades (5.4% in the first quarter 2018 versus 5.6% in the first quarter 2017). The expected reduced grade and tonnage reflects the continued depletion of the current mineable ore reserves remaining at the Mavres Petres ore body. Development during the quarter provided access to the lower sections of the mine for exploration drilling which continues to identify additional resources. These have the potential to extend the mine's life while allowing production rates to return to the historic levels of approximately 225,000 tonnes per annum.

Average realized price2 for concentrate increased year on year ($1,423 per tonne in the first quarter 2018 versus $1,197 per tonne in the first quarter 2017) due to an increase in both lead and zinc prices. Total cash operating costs increased over the comparative quarter ($1,277 per tonne in the first quarter 2018 vs $811 per tonne in the first quarter 2017) due to reduced tonnes sold.

Sustaining capital spending in the quarter of $1.6 million related to underground development.

2 Average realized price includes mark to market adjustments.

Development Projects and Exploration

GREECE

Skouries

Works completed during the quarter included ongoing bank stabilization, essential water ditches and storage ponds, primary drainage network, finalization of all site-built tanks, in addition to equipment erection (mills -- liners, lube oil system, power) steelwork modifications and reinforced concrete works which are required for the ongoing maintenance regime and the long term storage of equipment.

Total capital expenditure for the quarter was $8.0 million, in line with current guidance. The Company announced its intention to move the project into care and maintenance in November 2017 until which time it receives approval of all permits required to complete construction. The transition to care and maintenance has been delayed by bad weather at site and is expected to be complete by the end of Q2. Ongoing care and maintenance costs are estimated to be $3-5 million per year for 2019 and beyond.

During the quarter, the Company filed an updated technical report on the Skouries project. The report included Proven and Probable reserves of 3.8 million ounces of gold at 0.74 grams per tonne Au and 1.7 billion pounds of copper at 0.49% Cu, supporting a 23 year mine life at an average annual production rate of 140,000 ounces of gold and 67 million pounds of copper with production from both the open-pit and underground mines. At an assumed gold price of $1,300 per ounce the project is expected to generate an estimated after-tax project NPV $925 million at a 5% discount rate, an IRR of 21.2%, and a payback period of 3.4 years.

Perama Hill

Perama Hill remains on care and maintenance pending receipt of the necessary permits.

CANADA

Lamaque

The mining lease for the Triangle deposit was approved during the quarter. This represents a major project milestone and enables Lamaque to enter the production phase. A total of 1,643 metres of underground development were completed at Triangle during the quarter. The ramp up of refurbishment work on the Sigma mill continued with the mobilization of key contractors to site. Key activities at the Sigma mill focused on the inspection and refurbishment of electrical equipment and motors.

During the quarter, test mining extracted approximately 20,000 tonnes of ore with an average head grade of 6.3 grams per tonne gold, with approximately 6,000 tonnes processed at a nearby custom milling facility. Results from the custom milling have confirmed our metallurgical assumptions for future mill performance. A total of 2,740 ounces of gold were produced during the quarter, primarily from material mined during the fourth quarter of 2017.

Capital spending in the quarter totaled $18.9 million.

During the quarter, Eldorado released the results of the Lamaque pre-feasibility study, which focused on the development of the Triangle deposit (one of three currently identified deposits at Lamaque) and the refurbishment of the previously producing Sigma mill. The study also included the release of maiden reserves at Triangle of approximately 893,000 contained ounces of gold at an average grade of 7.3 grams per tonne. This supports an initial seven year mine plan with an average annual production rate of 117,000 ounces of gold at AISC of $717 per ounce. At an assumed gold price of $1,300 per ounce the project is expected to generate an estimated after-tax project NPV of $205 million at a 5% discount rate, an IRR of 34.3%, and a payback period of 3.7 years. The Company is carrying out an aggressive program of infill and extension drilling with the goal of converting resource to Proven and Probable reserves as well as locating additional resources at Triangle and other known mineralized zones and new targets.

BRAZIL

Tocantinzinho

The mining concession application is under review by the federal branch of the Mines Ministry and approval is expected this year. Work completed in the first quarter included a review of capital costs, detailed engineering of the tailings ponds and a consolidated geotechnical study.

Spending in the quarter totaled $1.7 million.

ROMANIA

Certej

During the quarter work at Certej continued to focus on tailings impoundment and waste rock storage engineering and studies required for the permitting process. Work also continued on the evaluation of the limestone quarry and facilities required for the pressure oxidation process as well as providing engineering support for the permitting effort. Offsite infrastructure construction work continued including water tank installation, water supply pipeline installation and power line construction.

Spending in the quarter totaled $2.2 million.

Exploration

A total of $6.9 million was spent on exploration programs during the quarter. Exploration drilling totaled 21,240 meters and was conducted at projects in Quebec, Greece and Turkey.

At the Lamaque project in Quebec, five drill rigs were active at the Triangle deposit and several nearby target areas, completing 17,700 metres of drilling. Drilling at Triangle tested the continuity and extent of high-grade mineralization at levels beneath the C4 and C5 zones. Results were positive, with numerous intersections of shear-hosted mineralization similar to those at upper levels of the deposit, as well as secondary splay zones and associated extension vein systems. The current program at Triangle is designed to include at least 19,000 metres of drilling and testing the deposit to depths of approximately 2,000 metres. Drilling during the quarter also tested targets at the Gabbro, Southwest, Sigma East and Triangle East areas.

In Greece, underground development continued at the Stratoni mine on the hangingwall exploration crosscut. A total of 2,350 metres of resource expansion drilling were completed with three drill rigs active during the quarter targeting the western and downdip extensions of the Mavres Petres orebody. At Olympias, exploration drilling commenced late in the quarter testing previously unexplored areas immediately east of the East Zone orebody.

In central Turkey, the initial drilling program at the 60% owned Bambal Tepe exploration joint venture began in March. This 2,000 metre program will test the downdip extent of outcropping gold-mineralized zones focused along schist-marble contacts, as well as a strong chargeability anomaly in the same region.

2018 Outlook and First Quarter Results

In 2018, Eldorado expects to produce 290,000-330,000 ounces of gold, including pre-commercial ounces from Lamaque. Cash operating costs are forecasted to be $580-630 per ounce.

  
                ($ millions unless otherwise noted)

                                   Q1 2018 Actuals  2018 Outlook (full year)
Operations                                                                
Total                                                                     
Ounces produced                             86,634       290,000 -- 330,000
Cash operating costs ($/ounce)                 571               580 - 630
Sustaining capex                             15.41                    62.0
Kisladag                                                                  
Ounces produced                             53,814       120,000 -- 130,000
Cash operating costs ($/ounce)                 576               600 -- 700
Sustaining capex                               7.5                    22.0
Efemcukuru                                                                
Ounces produced                             22,855        90,000 -- 100,000
Cash operating costs ($/ounce)                 532               530 -- 570
Sustaining capex                               3.7                    20.0
Olympias                                                                  
Ounces produced                              9,965         55,000 -- 65,000
Cash operating costs ($/ounce)                 699               550 -- 650
Sustaining capex                               2.6                    20.0
Lamaque                                                                   
Ounces produced                             2,7402        25,000 -- 35,0002
Cash operating costs ($/ounce)                 n/a                     n/a
Sustaining capex                               n/a                     n/a
Corporate                                                                 
General and administrative                     8.2                      45
Development capex                                                         
           Kisladag                            0.0                    31.0
           Olympias                           9.13                    28.0
           Lamaque                            18.9                   100.0
           Skouries                            8.0                    20.0
           Stratoni                            0.0                     8.0
           Tocantinzinho                       1.7                     8.0
           Certej                              2.2                     7.0
Exploration expenditure                       6.94                      25

(1)Including $1.6 million in sustaining capital at Stratoni.       
(2)Pre-commercial production.                                      
(3)Includes capitalized selling expenses.                          
(4)Includes 2.4 million of expensed exploration and land purchases.

Corporate

Board and Senior Management Changes

Robert Gilmore has announced his intention to not stand for re-election to the Company's board at the June Annual and Special Meeting. The Company thanks Robert for his long service to the Company.

Charles Parker, currently Corporate Controller will be interim Chief Financial Officer from May 1, 2018 until a permanent replacement is found.

Previously announced management changes that occurred during the quarter included:

  • Andor Lips, joined the Company as VP Government Relations, Europe on February 19, 2018
  • Timothy Garvin, EVP and General Counsel, joined the Company on February 20, 2018
  • Fabiana Chubbs, Chief Financial Officer, will depart at the end of April 2018
  • Dawn Moss, EVP Administration, retired on February 28, 2018
  • Eduardo Moura, VP and Special Advisor to the CEO, departed the Company as of February 28, 2018

New York Stock Exchange Minimum Share Price Requirement

New York Stock Exchange ("NYSE") regulations stipulate that listed issuers must maintain a minimum average closing share price of US$1.00 per share calculated over a period of 30 consecutive trading days. On April 18, 2018, Eldorado received notice from the NYSE that it no longer met this requirement.

Eldorado anticipates that it will request shareholder approval at its 2018 Annual and Special Meeting, to be held on June 21, 2018, to effect a share consolidation with a ratio of 5-for-1 in order to regain compliance with the NYSE's continued listing requirements. The proposed share consolidation will be subject to receipt of shareholder approval and all necessary regulatory approvals, including from the NYSE and the Toronto Stock Exchange.

Dividend

As previously announced, the Company suspended cash payment of its semi-annual dividend payment effective the first quarter of 2018.

Conference Call and Webcast with Slides

A conference call to discuss the details of the Company's 2018 First Quarter Results will be held by senior management on April 27, 2018 at 8:30 AM PT (11:30 AM ET). The call will be webcast and will have an accompanying slide deck. The webcast and slides can be accessed at this link and from Eldorado's website.

  Conference Call Details               Replay (available until May 18, 2018)
Date:         Friday, April 27, 2018   Toronto:         416 849 0833        
Time:         8:30 am PT (11:30 am ET) Toll Free:       1 855 859 2056      
Dial in:      647 427 7450             Pass code:       1564 377            
Toll free:    1 888 231 8191                                               

About Eldorado Gold

Eldorado is a gold and base metals producer with mining, development and exploration operations in Turkey, Greece, Romania, Serbia, Canada and Brazil. The Company has a highly skilled and dedicated workforce, safe and responsible operations, a portfolio of high-quality assets, and long-term partnerships with local communities. Eldorado's common shares trade on the Toronto Stock Exchange (TSX: ELD) and the New York Stock Exchange (NYSE: EGO).

Unaudited Condensed Consolidated Income Statements

    (Expressed in thousands of U.S. dollars except per share amounts) 
  
  
   For the quarter ended March 31                                 Note   2018   2017
                                                                         $      $
Revenue                                                                          
Metal sales                                                        131,905 111,880
                                                                                 
Cost of sales                                                                    
Production costs                                                    67,235 50,688
Depreciation and amortization                                       29,188 18,064
                                                                    96,423 68,752
Gross profit                                                        35,482 43,128
                                                                                 
Exploration expenses                                                 4,148  5,247
Mine standby costs                                                   2,706  1,031
Other operating items                                                    -  2,133
General and administrative expenses                                  8,225 11,614
Defined benefit pension plan expense                                 1,083    831
Share based payments                                              8  1,318  5,128
Write-down of assets                                                 4,024  1,054
Foreign exchange loss                                                1,142     88
Operating profit                                                    12,836 16,002
                                                                                 
Gain (loss) on disposal of assets                                       86  (307)
Gain on derivatives and other investments                              788     34
Other income                                                         3,097  2,349
Asset retirement obligation accretion                                (510)  (523)
Interest and financing costs                                       (3,564) (1,110)
                                                                                 
Profit from continuing operations before income tax                 12,733 16,445
Income tax expense                                                   7,084 10,776
Profit from continuing operations                                    5,649  5,669
Loss from discontinued operations                                        - (3,000)
Profit for the period                                                5,649  2,669
                                                                                 
Attributable to:                                                                 
Shareholders of the Company                                          8,718  3,834
Non-controlling interests                                          (3,069)(1,165)
Profit for the period                                                5,649  2,669
                                                                                 
Profit (loss) attributable to shareholders of the Company                        
Continuing operations                                                8,718  6,834
Discontinued operations                                                  -(3,000)
                                                                     8,718  3,834
Profit per share attributable to shareholders                                    
of the Company:                                                                  
Basic profit per share                                                0.01   0.01
Diluted profit per share                                              0.01   0.01
                                                                                 
Profit per share attributable to shareholders                                    
of the Company - continuing operations:                                          
Basic profit per share                                                0.01   0.01
Diluted profit per share                                              0.01   0.01

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.