14:49:22 EDT Fri 25 Jul 2025
Enter Symbol
or Name
USA
CA



Copper Fox Metals Inc
Symbol CUU
Shares Issued 397,647,993
Close 2012-12-21 C$ 1.06
Market Cap C$ 421,506,873
Recent Sedar Documents

Copper Fox estimates Schaft Creek NPV at $513-million

2012-12-21 15:30 ET - News Release

Mr. Elmer Stewart reports

COPPER FOX ANNOUNCES A POSITIVE FEASIBILITY STUDY ON THE SCHAFT CREEK DEPOSIT

Copper Fox Metals Inc. has released the results of a positive feasibility study on the Schaft Creek project located in northwestern British Columbia, Canada. The feasibility study was prepared under the direction of Tetra Tech, an industry-leading international engineering firm, with a high-level review of capital cost completed by Merit Consultants International Inc. and an internal review conducted by Matt Bender, MBA, PE. The feasibility study, with capital costs defined to within plus/minus 15 per cent, builds upon the previous preliminary economic assessment and preliminary feasibility study prepared by Samuel Engineering Inc. in January and September of 2008, and metallurgical and geotechnical work completed in 2009, 2010, 2011 and 2012.

Elmer Stewart, president and chief executive officer, said: "I am extremely proud of the work put into this feasibility study by the Copper Fox team and its capable consultants. Like all large-scale projects located in alpine-type terrain, this project did come with its own unique technical challenges. At an 8-per-cent discount rate as required in the teck option agreement, the feasibility study confirms the technical and financial viability of a nominal 130,000-tonne-per-day copper mining and processing operation at Schaft Creek. The company will host a webcast conference call in mid-January, details will follow by way of a separate news release."

The feasibility study recommends diamond drilling to determine the extent to which the 171.16 million tonnes of inferred resource that lie within the proposed open pit, now treated as waste, can be upgraded to either a measured or indicated mineral resource. If successful, this would categorize this rock as a revenue generator.

The project has a nominal 130,000 tpd milling capacity over a 21-year mine life representing a 30-per-cent increase from that proposed in the preliminary feasibility study prepared in September, 2008, with only a 20-per-cent increase in the estimated capital expenditures, no easy achievement.

The feasibility study provides for expansion of the project based on the current mineral resource and exploration potential of the Schaft Creek mineral trend. The potential to significantly expand the tailings storage facility, the current concentrate storage and shipping agreement with Stewart Bulk Terminals, and most importantly access to electrical power are positive features that support possible future expansion of the Schaft Creek project. Opportunity to lower operating and capital costs, and increase operating revenue could be identified during the detailed engineering phase of project development.

The project has the advantage of being located in the province of British Columbia, Canada, a safe geopolitical jurisdiction that strongly supports resource development.

Highlights of the feasibility study:

  • Nominal 130,000 tpd open-pit mine feeding a concentrator with two semi-autogenous grinding (SAG) mills;
  • Initial capital cost (capex) totals $3,256-million, which includes contingencies of $374-million;
  • Sustaining capex totals $1.24-billion over the proposed mine life, including $200-million for BC Hydro tariff;
  • Life-of-mine (LOM) metal production contained in concentrates totals 4.88 billion pounds of copper, 4.21 million ounces of gold, 214.92 million pounds of molybdenum and 25.1 million ounces silver;
  • Five years preproduction period followed with a productive mine life of 21 years;
  • Proven and probable mineral reserves total 940.8 million tonnes containing 5.6 billion pounds copper, 5.7 million ounces gold, 363.5 million pounds molybdenum and 51.7 million ounces silver on the basis of drill data up to May 23, 2012;
  • Within the pit shell there is a total of 171.16 million tonnes of inferred resource grading 0.25 per cent copper, 0.018 per cent molybdenum, 0.164 gram per tonne gold and 1.58 g/t silver, which for purposes of this study must be treated as waste rock;
  • LOM average mill feed grades of 0.271 per cent copper, 0.191 g/t gold, 1.716 g/t silver, 0.018 per cent molybdenum and a copper-equivalent (CuEq) of 0.441 per cent. The CuEq is back calculated based on how much in situ copper is required to provide the same after-recovery value to equal the combined metals value after recovery.

Summary of economic results

Base case pretax net present value for the Schaft Creek deposit using long-term metal prices and exchange rates, and an 8-per-cent discount rate is $513-million. Internal rate of return is 10.13 per cent and a payback period of 6.5 years. In addition to the base case, three alternative cases were presented. Alternative cases one and two are using three-year trailing average and spot metal prices (as of Oct. 15, 2012), respectively, and are presented for comparative purposes. Of particular significance is the third alternative case using the sophisticated economic science referred to as real option valuation (ROV). NPV at an 8-per-cent discount rate for the alternative cases one, two and three are $967-million, $1,024-million and $1,382-million, respectively.

ROV is a discounted cash flow technique that incorporates the uncertainty of future metal prices and exchange rates, as well as the management flexibility to adjust the operating status of the mining operations in the future based on the market conditions. ROV applies a dynamic optimization process that compares the values of the alternative plans at each point of time and makes decisions that maximize the present value of the whole project. Market variables are modelled using stochastic processes such as geometric Brownian motion and mean-reverting process. Numerical techniques such as finite difference, binomial lattice and Monte Carlo simulations are applied to the ROV. In this project, the Monte Carlo method was applied using 100,000 simulations.

Project enhancements

The feasibility study makes recommendations for further development of the project that could enhance the economics of Schaft Creek including:

  • Copper Fox undertakes a diamond drilling program at Schaft Creek with a goal to determine the extent to which the 171.16 million tonnes of inferred resource, that lie within the pit shell, can be upgraded to a measured or indicated resource. To the degree such a program is successful it will remove the affected material from being categorized as a rock-removal expense to an ore-bearing material and as such, a revenue generator;
  • Additional metallurgical testwork to pursue opportunities to increase metal recoveries and reduce processing costs;
  • Shorten the project development execution timeline.

Permits

Copper Fox is currently preparing the British Columbia environmental assessment (EA) application and a federal environmental impact statement (EIS), both required to obtain a B.C. EA certificate and federal approval. Copper Fox anticipates submitting the EA application and EIS as early as third quarter 2013. Copper Fox is also developing the permit applications required to construct the access road to the mine site. Access road permits have been prioritized based on the construction schedule presented in the feasibility study. Other permit applications required for mine site construction will follow completion of the EA application and EIS.

Development schedule

  • Project development will take place over a five-year period after initial permitting and engineering;
  • Permitting completed June 30, 2014;
  • Engineering completed February, 2016;
  • Access road construction completed March, 2016;
  • Construction phase one completed July, 2019, and phase two March, 2020;
  • Commercial production phase one start December, 2019, and phase two August, 2020.

Mineral resources

The project mineral resource was prepared by Tetra Tech with an effective date of May 23, 2012, as previously disclosed in a news release on May 31, 2012, and filed on SEDAR on June 25, 2012.

                                                                                                                         
                                    SCHAFT CREEK MINERAL RESOURCE ESTIMATE
                                        (Using a 0.15 g/t CuEq cut-off)
                                                                                        Contained metal

Resource           Tonnes  Copper  Molybdenum   Gold   Silver              Cu            Mo         Au          Ag
category                       (%)         (%)  (g/t)    (g/t)            (lb)          (lb)       (oz)        (oz)

Measured      146,615,300    0.31       0.017   0.24     1.78   1,001,824,600    55,624,000  1,149,100   8,402,700
Indicated   1,081,939,500    0.26       0.017   0.18     1.68   6,104,400,000   399,718,500  6,218,000  58,335,500
M+I         1,228,554,800    0.26       0.017   0.19     1.69   7,106,224,600   455,342,500  7,368,000  66,738,200
Inferred      597,191,300    0.22       0.016   0.17     1.65   2,872,034,300   206,252,100  3,359,600  31,601,400

Notes to mineral resources tables

  • Mineral resources are inclusive of mineral reserves.
  • While the terms measured (mineral) resource, indicated (mineral) resource and inferred (mineral) resource are recognized and required by National Instrument 43-101, investors are cautioned that except for that portion of mineral resources classified as mineral reserves, mineral resources do not have demonstrated economic viability. Investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be upgraded into mineral reserves. Additionally, investors are cautioned that inferred mineral resources have a high degree of uncertainty as to their existence, as to whether they can be economically or legally mined, or will ever be upgraded to a higher category.
  • A 0.15-per-cent CuEq cut-off was selected for the base case resource estimate. A 0.15-per-cent CuEq cut-off was the minimum grade of CuEq estimated by Tetra Tech required (using the estimated copper recovery rate, the milling and sales cost) to break even on an operating-cost-per-tonne basis.
  • CuEq grade cut-offs were used to report the mineral resource estimation as a function of copper, molybdenum, gold and silver. The CuEq is based on Tetra Tech's long-range metal prices of $2.97 (U.S.)/pound for copper, $16.80 (U.S.)/pound molybdenum, $1,256 (U.S.)/ounce gold and $20.38 (U.S.)/ounce for silver, and metal recoveries of 60.90 per cent for molybdenum, 70.6 per cent for gold and 43.4 per cent for silver. No copper recoveries were applied to the copper-equivalent grade.
  • Rounding as required by reporting guidelines may result in apparent summations differences between tonnes, grade and contained metal content.
  • Tonnage and grade measurements are in metric units. Contained copper and molybdenum are reported as pounds, and contained gold and silver are reported as troy ounces.

Mineral reserve

Proven and probable mineral reserves are the economically minable portions of the measured and indicated mineral resources set out in the table, respectively, as demonstrated by the feasibility study. The proven and probable reserves at Schaft Creek are summarized in the table.

                                                                      
                  SCHAFT CREEK MINERAL RESERVE ESTIMATE   
                      
Reserve category   Run of mine      Copper  Molybdenum     Gold   Silver  
                           (Mt)         (%)         (%)    (g/t)    (g/t)

Proven                   135.4        0.31      0.0175     0.25     1.81   
Probable                 805.4        0.26      0.0176     0.18     1.70   
Proven and probable      940.8        0.27      0.0176     0.19     1.72

Notes to mineral reserves table

  • Mineral reserves are contained within measured and indicated pit designs.
  • Appropriate mining costs, processing costs metal recoveries and interramp pit slope angles varying from 27 degrees in overburden to 45 degrees in bedrock were utilized to generate the pit phase design.
  • Mineral reserves have been calculated using a net-smelter-return cut-off. The NSR was calculated as follows: NSR equals recoverable revenue minus TCRC (on per-tonne basis), where TCRC equals transportation and refining costs; recoverable revenue equals revenue for recoverable copper, molybdenum, gold and silver, respectively, using metal prices of $3.52 (U.S.)/pound, $15.30 (U.S.)/pound, $1,366 (U.S.)/ounce and $25.96 (U.S.)/ounce for copper, molybdenum, gold and silver, respectively; at an exchange rate of 96 cents to to $1 (U.S.); metal recoveries used are based on recovery curves if critical average recoveries could be calculated.
  • The LOM average strip ratio (waste to ore) is 2 to 1, excluding rehandle.
  • Significant digits on run of mine are rounded to one decimal point.
  • Rounding as required by reporting guidelines may result in apparent summations differences between tonnes, grade and contained metal content.
  • Tonnage and grade measurements are in metric units. Contained copper and molybdenum are reported as pounds, and contained gold and silver are reported as troy ounces.
  • The proven and probable mineral reserves are included within the measured and indicated mineral resources as estimated by Tetra Tech on May 23, 2012.

Project description

The Schaft Creek deposit is located approximately 60 kilometres south of Telegraph Creek, 375 kilometres northwest of Smithers and 340 kilometres northwest of Terrace on the east side of the Coast Mountain range, where annual precipitation is approximately 900 millimetres per year in the form of rain and snow.

Copper Fox holds title and a 100-per-cent working interest in the Schaft Creek project located within Tahltan traditional territory consisting of 55,779.56 hectares (137,834 acres) in northwestern British Columbia. Included in this total are the Schedule A mineral tenures originally conveyed to Copper Fox pursuant to the option agreement dated Jan. 1, 2002, between Teck Resources Ltd. and Copper Fox, which consist of 8,334.34 hectares (20,594 acres). The Schedule A mineral tenures are subject to a 3.5-per-cent net-profits interest held by Royal Gold Inc., a 30-per-cent carried net-proceeds interest held by Liard Copper Mines Ltd. and, together with the additional mineral tenures obtained by Copper Fox within the area of interest provided for in the Teck option agreement, an earn-back option held by Teck. On completion of the feasibility study, Copper Fox earns Teck's 78-per-cent interest in Liard. Teck's earn-back option to acquire either 20 per cent, 40 per cent or 75 per cent of Copper Fox's interest in the Schaft Creek project is triggered upon delivery of a positive bankable feasibility study (as defined) to Teck after which it has 120 days to make a decision. Should Teck elect to exercise its earn-back option for 75 per cent, Teck is required to finance subsequent property expenditures up to a total of 400 per cent of those incurred by Copper Fox ($84.9-million to July 31, 2012) and use best efforts to arrange for project financing, including the Copper Fox portion. For full details of the Teck earn-back option please refer to the company's website.

Mining of the Schaft Creek deposit is planned as a conventional truck-shovel open-pit mining operation with a nominal 130,000 tpd throughput over the LOM. The current 940.8-million-tonne mineral reserve should support a mine life of approximately 21 years (47.4 million tonnes per year). There is potential to extend the mine life with additional infill drilling to upgrade the approximately 171.16 million tonnes of current inferred resource located within the proposed open pit. Additional exploration of the Schaft Creek deposit to the east and the north of the Paramount zone, and north of the Liard zone, as well as the recently discovered Discovery zone could extend the mine life of the Schaft Creek project.

Processing of the ore would utilize a conventional copper ore-grinding and flotation circuit to produce a high-quality copper concentrate with significant gold and silver credits, and a separate molybdenum concentrate. Mining and waste rock facilities would be located in the Schaft Creek Valley and Mess Creek Valley, with the plant, infrastructure, airport and tailings facilities being located adjacent to Mess Creek Valley, Skeeter and Start Lakes.

Annual mine production of ore and waste is projected to average approximately 147 million tonnes per year with an in situ LOM waste/ore stripping ratio of 2 to 1. Run-of-mine ore would be fed into two gyratory crushers located at the edge of the open pit in the Schaft Creek Valley and transported via conveyor from the Schaft Creek Valley to a coarse ore stockpile near the proposed mill site in the Start Lake Valley.

The proposed process plant would be a conventional double-line grinding-flotation concentrator. The plant site has sufficient mill pad area to install a third processing line to increase daily throughput to 180,000 tpd should expansion of the mine be required to optimize the economics of the project. Tailings would be transported to the tailing storage facility (TSF) through pipelines. Concentrates would be transported by trucks to port facility in the town of Stewart, B.C., and the molybdenum concentrate to the Fairview Terminals in Prince Rupert, B.C., for shipment to various international destinations.

The closest provincial road to the mine site is Highway 37. The access road to the Schaft Creek project would be used to transport material and consumables to and from the mine site, and to deliver mine capital equipment. Personnel would be transported to and from the Schaft Creek site via aircraft. The road would have controlled access to ensure the health and safety of company personnel and the public, as well as to protect the environment. Copper Fox is in the process of preparing its environmental assessment application which is required before application can be made for permits to construct the access road and power line to the Schaft Creek site. Copper Fox's plan would be to reach agreement with Galore Creek Mining Corp. regarding joint use of the access road from Highway 37 (kilometre zero) to approximately kilometre 65, including construction of the More Creek Canyon Bridge and completion of an additional 25.2 kilometres of the Galore Creek road for a total distance of 65.2 kilometres. The balance of the access road would be single lane, with occasional pullouts. Power for the project would be provided from the Northwest transmission line (NTL) currently being constructed by the provincial electrical authority, BC Hydro. An 81-kilometre-long, 287-kilovolt power line would run to the processing site substation.

The time period estimated from completion of the feasibility study to allow for permitting, detailed engineering, equipment procurement, construction, and start-up to production is approximately seven years. This time period may be significantly shortened during the detailed engineering phase and by running concurrent activities.

Mining

The Schaft Creek pit design for the feasibility study includes seven phases. The initial phase is the excavation of the material required for the construction of the conveyor to transport ore to the mill. The second phase, labelled 1N, is a starter pit in the Paramount zone at the north toe of the east face of Mount LaCasse, to provide construction waste and stockpile high-grade ore to be processed in year one. The third and fourth phases mined are 1S and 2S, which are the low-strip-ratio phases at the south end of the Liard zone. The fifth and sixth phases mined are 2N and 3N, the north phase pushbacks. The final phase is 4N, which extends to the ultimate pit bottom, which, based on the resource block model, would end in mineralization. Access to each phase and bench is continuously provided by ramps built into the highwall or cut into the rehandle face.

The total waste mined is estimated to be 1.89 billion tonnes. A portion of the waste mined will be used for road, TSF and infrastructure construction. The balance of the waste is planned to be stored in three separate areas located at varying distances from the proposed open pit, designated the east, west and south dumps.

Process plant

Initial planned mill throughput is 65,000 tpd, which will be increased to 130,000 tpd after approximately one year of operation. The ore from the pit will be conveyed to the process plant located approximately eight kilometres northeast of the pit. The process for metal recovery from the ore is conventional flotation, consisting of two process trains. Each of the process trains consists of SAG mill/ball mills/pebble crushers (SABC) primary grinding, bulk rougher/scavenger flotation, bulk concentrate regrinding and cleaner flotation circuits. The bulk concentrate produced will be separated to produce market-grade copper-gold-silver concentrate and molybdenum concentrate. Metal recoveries to the copper concentrate containing at least 28 per cent copper are expected to be 86.6 per cent for copper, 73.0 per cent for gold and 48.3 per cent for silver. The molybdenum recovery to the molybdenum concentrate (plus-50 per cent Mo) is estimated to be 58.8 per cent.

Estimated metal production

Over the 21-year mine life, the parameters of the mining operation, and metals production to the copper concentrate and molybdenum concentrate are summarized in the table.

                                   
 SCHAFT CREEK MINE PRODUCTION SUMMARY

Parameter                 Life of mine 

Tonnes ore milled (000)        940,800   
Strip ratio                        2.0     
Grade                             
Copper (%)                        0.27     
Gold (g/t)                        0.19     
Molybdenum (%)                   0.018    
Silver (g/t)                      1.72

                                                                                                                         
                                 SCHAFT CREEK CONCENTRATE METAL PRODUCTION

Description                  Year 1-5 annual avg.  Year 1-10 annual avg      LOM annual avg        LOM total

Copper concentrate (kt)                      445                    420                 376            7,897
Copper in concentrate (Mlb)                  274                    259                 232            4,875
Copper in concentrate (kt)                   124                    118                 105            2,211
Gold in concentrate (koz)                    237                    237                 201            4,213
Silver in concentrate (koz)                1,229                  1,280               1,195           25,100
Molybdenum concentrate (t)                 8,420                  8,957               9,284          194,967
Molybdenum in concentrate (klb)            9,281                  9,873              10,234          214,914

The LOM average metal content of copper concentrate is estimated to contain 28 per cent copper and 16.6 g/t gold, 98.9 g/t silver, and the molybdenum concentrate at 50 per cent molybdenum. The average impurity element levels in the final concentrates would be lower than the penalty limits based on the test results. The moisture content is estimated to be 9.0 per cent for the copper concentrate and 5.0 per cent for the molybdenum concentrate.

The copper concentrates will be trucked via Highway 37 to Stewart for storage and loading. In 2011, Copper Fox executed an agreement with Stewart Bulk Terminals for the storage and shipment of up to 600,000 tonnes of concentrate per year to provide for export of the copper concentrates to foreign markets (see news release dated Oct. 12, 2011).

Tailings storage facility

The project requires the design of a TSF with the flexibility to manage tailings from either one or both of the processing trains. The south end of the TSF is located approximately 1.8 kilometres north of the milling facilities in Skeeter Valley and the facility is designed to accommodate approximately 941 million tonnes of tailings during the 21-year mine life. Total capacity of the TSF could be significantly expanded by increasing the height of the retaining embankments.

Infrastructure

The project will require the development/construction of a number of infrastructure items. The locations of the facilities and other infrastructure items were selected to take advantage of local topography, accommodate environmental considerations, and ensure efficient and convenient operation of the mine haul fleet.

Project infrastructure will include:

  • A secure single-lane access road with double-lane sections to support the construction and operation of the project. This road will include, and extend from, the partially constructed (approximately 40 kilometres), existing Galore Creek access road. The road will follow the Galore Creek access road/route for the first 65.2 km from Highway 37. At kilometre 65.2 it turns north from the Galore Creek access route. Approximately 40 km of new road will be constructed north through the Mess Creek Valley to the mine site;
  • A 287-kilovolt power line from Bob Quinn to the site covering a total distance of approximately 81 km;
  • 105.26-kilometre fuel pipeline from Tahltan depot/Highway 37 to site, including diesel fuel supply and distribution;
  • TSF complete with diversion channels including a reclaim water system;
  • Site haul roads;
  • New on-site airport capable of receiving aircraft with a capacity of up to 78 passengers;
  • A depot located at the juncture of Highway 37;
  • Water supply and distribution system;
  • Sewage disposal plant;
  • Lay-down area;
  • Process and ancillary facilities;
  • Power distribution network;
  • Communications infrastructure.

Social and environment

Copper Fox is committed to maximizing benefits and economic opportunities for local communities and local first nations, including employment and training.

Environmental baseline work on the project started in 2006 and has continued through 2012. The project is currently in the first of the province's two-staged EA process. The preapplication stage focuses on identification of the issues and concerns to be addressed in the application and reflected in the AIR. The preapplication stage is considered completed on acceptance of the application for review by the EAO, initiating the application review stage of the EA process. The application must comply with the project-specific AIR that is formally approved and issued by the EAO.

Closure and reclamation plans will be considered and updated throughout design, construction and operation of the project to help ensure that the objectives can be successfully achieved. Reclamation plans have been prepared for the TSF, open pit and waste rock.

Capital cost estimates

The project initial capital costs are estimated at $3,256-million (approximately $22,200/operating tonne, excluding contingency) with an accuracy of plus/minus 15 per cent as of third quarter 2012, including a contingency of $373.8-million (11.5 per cent of initial direct and indirect capital cost estimate). The estimates are consistent with a Class 3 estimate. Major items of the capital costs estimate are set out in the table.

                                               
             INITIAL CAPITAL COSTS
Item                                          $M

Direct costs
Overall site                              251.06
Mining                                    483.47
Primary crushing                          179.62
Grinding, flotation and regrind           594.68
Tailing management facility               212.23
Site services and site utilities           23.86
Ancillary buildings                       202.15
Plant mobile fleet                          8.88
Temporary services                          5.20
Off-site infrastructure and facilities    202.34
Total direct costs                     $2,163.49
Indirect costs
Project indirects                         601.24
Owner's costs                             118.04
Total indirect costs                      719.28
Total direct and indirect costs        $2,882.77
Contingency at 11.5%                      373.80
Total initial capital                  $3,256.57

This estimate includes direct field costs, and indirect costs associated with design, construction and commissioning. This estimate is based on pricing as of third quarter 2012, with no allowances for inflation or escalation.

LOM sustaining capital is estimated to total $1.24-billion over the projected 21-year mine life, and includes development of the open-pit deposit, BC Hydro tariff ($200-million) for the power line from Bob Quinn to site, replacement of and additions to surface mobile equipment, reclamation costs, and additional expenditures to expand the capacity of the TSF. A breakdown of the major components of the sustaining costs is set out in the table.

                                                           
                     LOM SUSTAINING CAPITAL                    
Area                                                       $M

Mining                                                    707
Tailings                                                  333
BC Hydro                                                  200
Total sustaining capital                               $1,240

Operating costs

LOM site unit operating cash costs, net of capitalized prestripping and other predevelopment costs, are $13.33 per tonne milled, as summarized in the table.

                                              
          LOM OPERATING COSTS

Area                    LOM $/t milled

Mining                            6.56
Processing                        4.87
Tailings facility                 0.22
Depot services                    0.52
Surface services                  0.34
General and administration        0.82
Total                            13.33

Open-pit mining cash costs average $6.56 per tonne of ore mined, including waste and ore mining costs. The in situ life-of-mine average strip ratio (waste to ore) is estimated to be 2 to 1.

LOM copper production total and cash costs per produced pound, including mine site operating costs, smelter and refining charges, and concentrate transport cost, average $2.09/pound and $1.15/pound, respectively.

Economic analysis summary

The project economics were evaluated whereby revenues and costs are projected into the future on an annual basis. Annual net cash flows are then discounted at a rate of interest to reflect the time value of money to yield an NPV. The analysis includes all site operating costs, smelter charges, transport costs and royalties.

The most significant input which affects project economics is projected future metals prices. The four economic cases using the previously discussed input parameters are set out in the table.

                                                                                                 
                                     SUMMARY OF ECONOMIC RESULTS
                                   
Item                                 Base case  3-year avg case*  Spot price case**  Real options case

Metal price                                                                                      
Copper (US$/lb)                           3.25             3.63              3.69                 3.25
Gold (US$/oz)                         1,445.00         1,445.00          1,736.00             1,445.00
Silver (US$/oz)                          27.74            27.74             32.71                27.74
Molybdenum (US$/lb)                      14.64            14.64             11.34                14.64
Exchange rate (US:Cdn)                    0.97             0.99              1.02                 0.97
Pretax economic results                                                                         
Operating cash flow ($M)                10,746           12,065            12,161               11,284
NPV (at 5%) ($M)                         1,694            2,348             2,419                2,665
NPV (at 8%) ($M)                           513              967             1,024                1,382
NPV (at 10%) ($M)                           25              388               437                  836
IRR (%)                                  10.13             11.9             12.14                 15.4
Payback (yr)                              6.48             5.81               5.7                  4.9
Cash cost/lb Cu ($/lb)                    1.15             1.19              1.12                 1.15
Total cost/lb Cu ($/lb)                   2.09             2.14              2.07                 2.09
Avg annual operating cash flow*** ($M)     371              414               425                  640

* Between Oct. 15, 2009, to Oct. 15, 2012.
** On Oct. 15, 2012.
*** Years one to five.

At the prices used in the base case for this study, total estimated taxes payable on Schaft Creek profits are $1,858-million over the 21-year mine life. The components of the various taxes that will be payable are in the table.

                                       
        ESTIMATED TAXES PAYABLE  
       
Tax component                 LOM amount  
                                     ($M)

Corporate tax (federal)              841
Corporate tax (provincial)           561
Provincial resource tax              456
Total taxes                        1,858

                                                              
                  AFTERTAX ECONOMIC RESULTS     
             
Description                                Base case  ROV case

Net cash flow ($M)                             4,270     5,133  
Discounted cash flow NPV at 5% ($M)              956     1,260  
Discounted cash flow NPV at 8% ($M)               67       529   
Payback (years from start of mill operations)    6.8       5.7   
IRR (%)                                          8.3      12.7

Qualified persons

On Jan. 15, 2010, Copper Fox commissioned Tetra Tech to complete the Schaft Creek project feasibility study in accordance with NI 43-101. A team of qualified persons from Tetra Tech, McElhanney Consulting Services Ltd., Moose Mountain Technical Services (MMTS) and Knight Piesold Ltd. (KP) prepared and reviewed the feasibility study.

The detailed mine plan was prepared by MMTS under the direction of Greg Trout, PEng. The scientific and technical information in this release has been reviewed by Marten Regan, senior project manager, Tetra Tech, overall manager for the feasibility study.

Other qualified persons involved in the feasibility study were:

  • Tetra Tech: Ali Farah, PEng; Dr. Robert Morrison, PhD, MAusIMM (CP), PGeo; Hassan Ghaffari, PEng; Dr. John Huang, PhD, PEng; Dr. Monica Danon-Schaffer, PhD, PEng; Rui Adanjo, PEng; Dr. Sabry Hafez, PhD, PEng; and Harvey Stoyko, PEng;
  • KP: Daniel Friedman, PEng; and Daniel Yang, PEng;
  • McElhanney: David Pow, PEng.

This release was also reviewed by Elmer Stewart, PGeol, MSc, president and chief executive officer of Copper Fox, non-independent qualified person within the meaning of NI 43-101.

Readers should refer to the feasibility study technical report for further details of the project development. The feasibility study technical report will be filed in accordance with NI 43-101 on SEDAR within the required 45-day statutory period and will be made available on Copper Fox's website.

We seek Safe Harbor.

© 2025 Canjex Publishing Ltd. All rights reserved.