
TORONTO -- (Business Wire)
Americas Silver Corporation (TSX: USA) (NYSE American: USAS) (“Americas
Silver” or the “Company”) today announced consolidated production and
operating cost results for the third quarter of 2017 and individually
for its Cosalá Operations and Galena Complex. All figures are in U.S.
dollars unless otherwise indicated.
Third Quarter Highlights
-
Consolidated silver production for the quarter of approximately
565,000 silver ounces and 1.1 million silver equivalent1
ounces, representing an increase of 1% and decrease of 6%,
respectively, when compared to Q2, 2017, and a decrease of 5% and
increase 1%, respectively, year-over-year.
-
Consolidated cash costs2 for the quarter were approximately
$12.61 per silver ounce, an increase of 26% year-over-year, while
consolidated all-in sustaining costs2 were approximately
$15.92 per silver ounce, an increase of 24% year-over-year.
-
The Company processed 69,000 tonnes of silver-copper El Cajón ore
producing 160,000 ounces of silver. El Cajón ore was mined in the
second quarter as transitional feed to bridge the period until the
commencement of San Rafael production. It was not determined to be in
commercial production and was omitted from the quarterly consolidated
cost calculations. Adjusting for this production, consolidated cash
costs and all-in sustaining costs would have been $11.75 and $14.18
per silver ounce, respectively.
-
San Rafael ore development continued to increase to approximately
1,000 tonnes per day at the end of October. The Company expects San
Rafael to be the sole source of mill feed by mid-November 2017 with
commercial production expected before the end of the fourth quarter.
The project remains fully funded and is tracking well to budget.
-
The Company has performed two test runs of San Rafael ore, one at the
end of September and the second at the end of October to test the new
flotation and concentrate re-grind circuits. Both tests confirmed
circuit performance predicted in the San Rafael Prefeasibility Study.
-
Guidance for 2017 remains at 2.0 - 2.5 million ounces of silver
production and silver equivalent production of 5.0 - 5.5 million
ounces with projected cash costs at the high end of the $4.00 - $5.00
per silver ounce and all-in sustaining cash costs of $9.00 - $10.00
per silver ounce ranges depending on the timing of the declaration of
commercial production of San Rafael.
-
The Company has cash and cash equivalents of $8.7 million at September
30, 2017. The Company expects to release its third quarter financial
results on or before November 14, 2017.
“The Cosalá team has done an effective job at managing the development
and operations of three different mines and a successful drill program
during 2017,” said Americas Silver President and CEO Darren Blasutti.
“We expect this strong performance to continue through to the end of
2017 and into 2018 with San Rafael coming into production on time and on
budget in the next couple of weeks. We made a prudent decision to
process El Cajón ore in the third quarter that increased costs in order
to free up working capital that otherwise would have been inaccessible
for years.”
Consolidated Third Quarter Production Details
Consolidated silver production for the third quarter of 2017 was 564,833
silver ounces which represents an increase of 1% over the previous
quarter and a decrease of 5% year-over-year. Silver equivalent
production was approximately 1.1 million ounces, a decrease of 6% over
the previous quarter and an increase of 1% year-over-year. The decrease
in silver and silver equivalent production is primarily due to lower
tonnage and grade at the Galena Complex, partially offset by continuing
strong production from the Nuestra Señora and El Cajón mines as the
Cosalá Operations prepares to commence commercial production from San
Rafael later in the quarter.
| Table 1 | |
| Consolidated Production Highlights | |
|
|
| Q3 2017 |
| Q2 2017 |
| Change |
| Q3 2016 |
| Change | |
|
Processed Ore (tonnes milled)
| |
174,677
| |
179,427
| |
-3%
| |
166,770
| |
5%
| |
|
Silver Production (ounces)
| |
564,833
| |
557,892
| |
1%
| |
596,855
| |
-5%
| |
|
Silver Equivalent Production (ounces)
| |
1,107,874
| |
1,175,836
| |
-6%
| |
1,107,110
| |
1%
| |
|
Silver Grade (grams per tonne)
| |
111
| |
107
| |
4%
| |
124
| |
-11%
| |
|
Cost of Sales ($ per equiv. ounce silver)1 | |
$9.17
| |
$11.00
| |
-17%
| |
$10.25
| |
-11%
| |
|
Cash Costs ($ per ounce silver)1 | |
$12.61
| |
$7.21
| |
75%
| |
$10.00
| |
26%
| |
|
All-in Sustaining Costs ($ per ounce silver)1 | |
$15.92
| |
$10.65
| |
50%
| |
$12.86
| |
24%
| |
|
Zinc Production (pounds)
| |
1,433,961
| |
2,904,374
| |
-51%
| |
2,183,814
| |
-34%
| |
|
Lead Production (pounds)
| |
5,369,482
| |
6,435,048
| |
-17%
| |
7,991,507
| |
-33%
| |
|
Copper Production (pounds)
| |
507,285
| |
273,475
| |
85%
| |
326,639
| |
55%
| |
1 Cost of sales per silver equivalent ounce, cash costs per
silver ounce, and all-in sustaining costs per silver ounce for Q3, 2017
and Q2, 2017 excludes pre-production of 160,128 and 22,549 silver
ounces, respectively, and 238,919 and 32,955 silver equivalent ounces,
respectively, mined from El Cajón during its commissioning period, and
for Q3, 2017 excludes pre-production of 5,146 silver ounces and 30,161
silver equivalent ounces mined from San Rafael during its commissioning
period. Pre-production revenue and cost of sales from El Cajón and San
Rafael are capitalized as an offset to development costs.
Consolidated cash costs increased 75% to $12.61 per silver ounce
compared to the previous quarter and 26% year-over-year. All-in
sustaining costs increased 50% to $15.92 per silver ounce compared to
the previous quarter and 24% year-over-year. The increase in cash costs
and all-in sustaining costs was primarily due to lower tonnage and grade
at the Galena Complex as the mine progressed through lower grade areas
of the mine while catching up on development in higher grade areas and
the processing of El Cajón ore in the quarter. The impact of this
beneficial work will be realized starting in the fourth quarter.
Approximately 69,000 tonnes of ore from the El Cajón mine was milled in
Q3, 2017 as the stockpiled El Cajón silver-copper ore could not be
processed with either silver-zinc-lead Nuestra Señora or San Rafael ore.
The material yielded concentrates containing approximately 160,000
ounces of silver and 462,000 pounds of copper. By processing this ore
before the San Rafael production start-up, approximately $3.4 million of
pre-production revenue was realized that would have stayed on the
stockpile until the end of the San Rafael mine life. The criteria
necessary to declare sustainable commercial production of this
transitional ore were determined not to have been met. As a result, the
by-product revenues and pre-production costs were omitted from the
consolidated cash costs and all-in sustaining cost costs calculation. If
El Cajón pre-production revenues and costs were included, the adjusted
consolidated cash costs would have been approximately $11.75 per silver
ounce and all-in sustaining costs would have been approximately $14.18
per silver ounce for the quarter.
Cosalá Operations Production Details
During Q3, 2017, the Cosalá Operations progressed its transition from
the existing Nuestra Señora and El Cajón mines to initial production
from the San Rafael mine. Production for the Cosalá Operations was
primarily sourced from the silver-zinc-lead-copper Nuestra Señora mine
during the first two months of Q3, 2017 and silver-copper El Cajón ore
in September. Nuestra Señora was originally planned to cease production
in early Q2, 2017, but has been extended to take advantage of additional
material sourced from various areas of the existing workings. It is
expected that stockpiled Nuestra Señora ore will be processed during Q4,
2017 up to the commencement of San Rafael ore processing in mid-late
November.
The Cosalá Operations produced 277,752 ounces of silver during the third
quarter of 2017 and 528,823 ounces of silver equivalent inclusive of El
Cajón and pre-production material from San Rafael. Excluding the El
Cajón and San Rafael material, the Cosalá Operations produced 112,478
ounces of silver during the third quarter of 2017 and 259,743 ounces of
silver equivalent during the same period at cost of sales of $1.32 per
silver equivalent ounce, cash costs and all-in sustaining costs of $3.16
per silver ounce. While silver production increased 15% compared to the
previous quarter and 14% year-over-year, silver equivalent production
decreased 6% compared to the previous quarter as a result of lower
by-product production of zinc and lead from Nuestra Señora partially
offset by increased copper production. Cash costs and all-in sustaining
costs improved year-over-year by 68% and 73%, respectively, as Nuestra
Señora ore was produced with lower operating costs and minimal
development work.
| Table 2 | |
| Cosalá Operations Highlights | |
|
|
| Q3 2017 |
| Q2 2017 |
| Change |
| Q3 2016 |
| Change | |
|
Processed Ore (tonnes milled)
| |
134,273
| |
134,778
| |
-1%
| |
121,875
| |
10%
| |
|
Silver Production (ounces)
| |
277,752
| |
242,523
| |
15%
| |
242,916
| |
14%
| |
|
Silver Equivalent Production (ounces)
| |
528,823
| |
564,112
| |
-6%
| |
436,774
| |
21%
| |
|
Silver Grade (grams per tonne)
| |
74
| |
66
| |
12%
| |
75
| |
-1%
| |
|
Cost of Sales ($ per equiv. ounce silver)1 | |
$1.32
| |
$7.57
| |
-83%
| |
$9.96
| |
-87%
| |
|
Cash Costs ($ per ounce silver)1 | |
$3.16
| |
($2.81)
| |
213%
| |
$9.84
| |
-68%
| |
|
All-in Sustaining Costs ($ per ounce silver)1 | |
$3.16
| |
($2.81)
| |
213%
| |
$11.72
| |
-73%
| |
|
Zinc Production (pounds)
| |
1,433,961
| |
2,904,374
| |
-51%
| |
2,183,814
| |
-34%
| |
|
Lead Production (pounds)
| |
793,058
| |
1,351,258
| |
-41%
| |
885,560
| |
-10%
| |
|
Copper Production (pounds)
| |
507,285
| |
273,475
| |
85%
| |
326,639
| |
55%
| |
1 Cost of sales per silver equivalent ounce, cash costs per
silver ounce, and all-in sustaining costs per silver ounce for Q3, 2017
and Q2, 2017 excludes pre-production of 160,128 and 22,549 silver
ounces, respectively, and 238,919 and 32,955 silver equivalent ounces,
respectively, mined from El Cajón during its commissioning period, and
for Q3, 2017 excludes pre-production of 5,146 silver ounces and 30,161
silver equivalent ounces mined from San Rafael during its commissioning
period. Pre-production revenue and cost of sales from El Cajón and San
Rafael are capitalized as an offset to development costs.
The Company provided an exploration update for its Cosalá properties on
August 24, 2017. The Company expects to complete up to 12 additional
holes in Q4, 2017 to further define the geological controls and extent
of mineralization in and around the known Zone 120 resource. Further
exploration drilling is being proposed for 2018. Results from the
ongoing 2017 drilling are expected to be released in early 2018.
San Rafael Update
The Company continued to advance towards production at the San Rafael
project during the quarter. Underground development is progressing as
expected with ore production ramping up from multiple working faces. The
reconfigured Los Braceros mill has been successfully tested with San
Rafael ore. Concentrates containing approximately 5,000 ounces of
silver, 211,000 pounds of zinc and 134,000 pounds of lead were produced
from approximately 6,000 tonnes processed during the quarter. A second
trial campaign of approximately 7,000 tonnes occurred in late October to
further refine operating parameters. The results of the two campaigns
were positive with recoveries and concentrate grades supportive of
estimates used in the April 2016 Prefeasibility Study. The surface ore
stockpile contains approximately 20,000 tonnes of San Rafael ore and is
increasing by nearly one thousand tonnes per day. The mill is expected
to shift to San Rafael ore on a full-time basis in mid-November with
commercial production to be declared before the end of the quarter. The
project remains fully funded and tracking well to budget.
Galena Complex Production Details
The Galena Complex produced 287,081 ounces of silver during the third
quarter of 2017 and 579,051 ounces of silver equivalent during the same
period at cost of sales of $12.69 per silver equivalent ounce, cash
costs of $16.31 per silver ounce and all-in sustaining costs of $20.92
per silver ounce. Silver and silver equivalent production decreased 9%
and 5%, respectively, compared to the previous quarter, and decreased
19% and 14%, respectively, year-over-year. Cash costs increased by 15%
compared to the previous quarter and 61% year-over-year and all-in
sustaining costs were up 4% compared to the previous quarter and 53%
year-over-year. Both silver and lead production were below expectations
in the third quarter due to a shortfall in tonnage and grade. With the
San Rafael transition going as expected, management is focused on
returning Galena to an acceptable level of operating performance by
advancing several planning-related initiatives, including grade
optimization, in order to recapture and build on the gains which were
made in 2015 and 2016.
| Table 3 | |
| Galena Complex Highlights | |
|
|
| Q3 2017 |
| Q2 2017 |
| Change |
| Q3 2016 |
| Change | |
|
Processed Ore (tonnes milled)
| |
40,404
| |
44,649
| |
-10%
| |
44,895
| |
-10%
| |
|
Silver Production (ounces)
| |
287,081
| |
315,369
| |
-9%
| |
353,939
| |
-19%
| |
|
Silver Equivalent Production (ounces)
| |
579,051
| |
611,724
| |
-5%
| |
670,336
| |
-14%
| |
|
Silver Grade (grams per tonne)
| |
233
| |
231
| |
1%
| |
258
| |
-10%
| |
|
Cost of Sales ($ per equiv. ounce silver)
| |
$12.69
| |
$13.98
| |
-9%
| |
$10.44
| |
22%
| |
|
Cash Costs ($ per ounce silver)
| |
$16.31
| |
$14.20
| |
15%
| |
$10.10
| |
61%
| |
|
All-in Sustaining Costs ($ per ounce silver)
| |
$20.92
| |
$20.03
| |
4%
| |
$13.63
| |
53%
| |
|
Lead Production (pounds)
| |
4,576,424
| |
5,083,790
| |
-10%
| |
7,105,947
| |
-36%
| |
About Americas Silver Corporation
Americas Silver is a silver mining company focused on growth in precious
metals from its existing asset base and execution of targeted accretive
acquisitions. It owns and operates the Cosalá Operations in Sinaloa,
Mexico and the Galena Mine Complex in Idaho, USA. The Company has
acquired an option on the San Felipe development project in Sonora,
Mexico.
Daren Dell, Chief Operating Officer and a Qualified Person under
Canadian Securities Administrators guidelines, has approved the
applicable contents of this news release. For further information please
see SEDAR or americassilvercorp.com.
Cautionary Statement on Forward-Looking Information:
This news release contains “forward‐looking information” within the
meaning of applicable securities laws. Forward‐looking information
includes, but is not limited to, the Company’s expectations intentions,
plans, assumptions and beliefs with respect to, among other things, the
realization of operational and development plans (including the
successful completion of the San Rafael project), the Cosalá Operations
and Galena Complex as well as the Company’s financing efforts. Often,
but not always, forward‐looking information can be identified by
forward‐looking words such as “anticipate”, “believe”, “expect”, “goal”,
“plan”, “intend”, “estimate”, “may”, “assume” and “will” or similar
words suggesting future outcomes, or other expectations, beliefs, plans,
objectives, assumptions, intentions, or statements about future events
or performance. Forward‐looking information is based on the opinions and
estimates of the Company as of the date such information is provided and
is subject to known and unknown risks, uncertainties, and other factors
that may cause the actual results, level of activity, performance, or
achievements of the Company to be materially different from those
expressed or implied by such forward looking information. This includes
the ability to develop and operate the Cosalá and Galena properties,
risks associated with the mining industry such as economic factors
(including future commodity prices, currency fluctuations and energy
prices), ground conditions and factors other factors limiting mine
access, failure of plant, equipment, processes and transportation
services to operate as anticipated, environmental risks, government
regulation, actual results of current exploration and production
activities, possible variations in ore grade or recovery rates,
permitting timelines, capital expenditures, reclamation activities,
social and political developments and other risks of the mining
industry. Although the Company has attempted to identify important
factors that could cause actual results to differ materially from those
contained in forward-looking information, there may be other factors
that cause results not to be as anticipated, estimated, or intended.
Readers are cautioned not to place undue reliance on such information.
By its nature, forward-looking information involves numerous
assumptions, inherent risks and uncertainties, both general and specific
that contribute to the possibility that the predictions, forecasts, and
projections of various future events will not occur. The Company
undertakes no obligation to update publicly or otherwise revise any
forward-looking information whether as a result of new information,
future events or other such factors which affect this information,
except as required by law.
1 Silver equivalent production throughout this press release
was calculated based on silver, zinc, lead and copper realized prices
during each respective period.
2 Cash cost per ounce and all-in sustaining cost per ounce
are non-IFRS performance measures with no standardized definition. For
further information and detailed reconciliations, please refer to the
Company’s 2016 year-end and quarterly MD&A. The performance measures for
the quarter ended September 30, 2017 are preliminary throughout this
press release subject to refinement from the Company’s third quarter
financial results to be released on or before November 14, 2017.

View source version on businesswire.com: http://www.businesswire.com/news/home/20171031006483/en/
Contacts:
Americas Silver Corporation
Darren Blasutti, 416‐848‐9503
President
and CEO
Source: Americas Silver Corporation
© 2026 Canjex Publishing Ltd. All rights reserved.