Mr. Chris Doornbos of E3 reports
E3 METALS CORP. BEGINS DEVELOPMENT OF A FIELD PILOT PLANT TO TEST ITS RAPID LITHIUM EXTRACTION
E3 Metals Corp. has begun the development of its field pilot plant which will incorporate E3's proprietary concentration technology to further validate the lithium extraction component of the process flow sheet. This technology has the potential to unlock significant value from E3's expansive lithium resources of 6.7 million tonnes of lithium carbonate equivalent (LCE) (inferred) (1) in the Leduc reservoir in Alberta. E3 Metals owns 76 Alberta metallic and industrial minerals permits totalling over 596,000 hectares, or over 1.47 million acres. The company's current resources cover only 34 per cent of the total Leduc reservoir that E3 Metals currently holds.
The further development of E3's lithium production step involved in the generation of lithium hydroxide and lithium carbonate will occur at commercial facilities and with partnering EPC firms. This allows E3 to continue to derisk its proposed lithium production flowsheet and advance toward technical disclosure through a prefeasibility study of its direct-brine process.
Pilot plant design and timeline
E3 Metals has recently partnered with both GreenCentre Canada and the National Research Council of Canada, with support from Alberta Innovates (GCC -- AI) and the NRC's industrial research assistance program (NRC -- IRAP), respectively. These partnerships are to advance E3's ion-exchange technology developed by the Alessi Lab at the University of Alberta to commercial readiness. These facilities are working toward developing a commercially scalable lithium extraction process. The results of this work are expected to provide a commercial chemical sorbent. They will also determine the design parameters for the mechanical equipment required for the ion-exchange process that should provide all of the inputs required for the design of E3 Metals' pilot plant. The development plan for E3 Metals for the next six months includes:
-
Demonstrating repeatability of the University of Alberta's extraction technology development at commercial facilities (GCC -- AI and NRC -- IRAP);
- Increasing the performance efficiencies of the ion-exchange process by increasing recovery, concentration factor and lithium uptake;
-
Developing a commercially scalable ion-exchange sorbent material;
- Constructing ion-exchange equipment in a lab environment to refine the mass balance and generate volumes of concentrate;
- Producing lithium hydroxide at the lab scale;
-
Finalizing the lithium production process flow sheet;
-
Finalizing the design of the pilot plant.
Lithium production process flow sheet
E3's proposed lithium production flow sheet breaks into three main steps. The first step involves pumping the lithium-enriched brine from the Leduc reservoir to the surface. The second step is creating a higher-grade lithium concentrate that utilizes E3's proprietary ion-exchange process. The third step generates the final lithium product (lithium hydroxide or carbonate) by further purification, electrolysis and crystallization.
Step 1: brine production and injection
One of the differentiators that sets E3's project apart is the Leduc reservoir's ability to produce vast quantities of lithium-enriched brine. Unique to this reservoir, a single well could produce more than 10,000 cubic metres per day (116 litres per second). In the Clearwater resource area alone, the reservoir contains enough brine to produce 50,000 tonnes LCE/year for over 35 years. In Alberta, lithium-enriched brine is currently being produced at surface and is subsequently reinjected back into the reservoir through oil and gas production facilities. E3 plans to use this produced water at surface for the pilot project and avoid the capital costs associated with drilling a well.
Step 2: lithium extraction
The development of the lithium extraction technology by E3 Metals, chemically filters the lithium from the brine to form a concentrate, with the lithium void waste stream being reinjected back into the reservoir via a sealed (closed loop) system. E3's technology utilizes ion-exchange, a well-understood process capable of treating large volumes of water. E3 has developed a proprietary chemical sorbent for use in the ion-exchange process that is highly selective for lithium and consequently has very low selectivity for other metals such as magnesium and cadmium (see E3 Metals May 29, 2018, announcement). This process happens rapidly, in about three hours, as opposed to 18 to 24 months for conventional evaporative solars. As such, E3 has demonstrated that it has the ability to rapidly concentrate and clean the brine in one step. This produces a relatively clean and high-grade concentrate feedstock for the third step of the lithium production process.
Step 3: lithium production
E3 Metals is working with several commercial facilities and EPC firms which have infrastructure and expertise in place to take E3's concentrate feedstock and generate a lithium product. One of the benefits of E3's process flow sheet is the flexibility to produce either lithium hydroxide or lithium carbonate. E3 is focusing its efforts on developing a high-purity lithium hydroxide due to the premium paid for the product by battery cathode manufacturers. This process involves electrolysis and crystallization to generate lithium hydroxide and is similar to processes utilized by other lithium companies globally. There are potential capital and operating cost benefits associated with the production of lithium carbonate and E3 is therefore exploring both alternatives in tandem.
Other development goals
The planned operation of the pilot plant and the subsequent testing of E3's concentrate feedstock in conventional lithium extraction process facilities at this scale will allow E3 to complete the front-end engineering design (FEED) for a process facility. During this time, E3 plans to upgrade a portion of its 6.7 million tonnes inferred resource to measured and indicated and complete a full cycle project economics analysis to prefeasibility study (PFS) level. At this point, E3 intends to produce a compliant PFS National Instrument 43-101 report outlining this information to the market.
The spot price for lithium carbonate is between $12,100 (U.S.) and $13,000 (U.S.) and for lithium hydroxide between $18,100 (U.S.) and $18,800 (U.S.).
About E3 Metals Corp.
E3 Metals is a petrolithium company rapidly advancing the development of direct recovery lithium brine projects in Alberta. E3 Metals holds lithium resources at 6.7 million tonnes lithium carbonate (inferred) (1). The company has a compelling competitive advantage by virtue of having access to extensive infrastructure built by the oil and gas industry in Alberta. This has provided E3 Metals with low finding costs, as the company has been able to sample existing wells to define its resource. The company's goal is to develop a commercially viable lithium extraction and production process and to demonstrate an economically viable commercial production process of its Alberta petro-lithium brine resource.
Chris Doornbos, PGeo, CEO and director of E3 Metals, is a qualified person as defined by National Instrument 43-101 and has read and approved the technical information contained in this announcement.