19:17:35 EDT Thu 13 Aug 2026
Enter Symbol
or Name
USA
CA



West Red Lake Gold Mines Ltd
Symbol WRLG
Shares Issued 413,947,977
Close 2026-08-12 C$ 0.78
Market Cap C$ 322,879,422
Recent Sedar+ Documents

West Red Lake completes phase 1 Madsen refurbishment

2026-08-13 13:50 ET - News Release

Mr. Shane Williams reports

WEST RED LAKE GOLD COMPLETES PHASE ONE MADSEN MINE SHAFT REFURBISHMENT

West Red Lake Gold Mines Ltd. has provided an update on the phased refurbishment of the Madsen mine shaft, an important infrastructure project that is expected to increase material handling capacity, improve mining efficiency and lower operating costs while supporting higher production rates as mining and development activities advance to deeper levels of the Madsen mine, located in the Red Lake mining district of Ontario.

Key take-aways:

  • The company has successfully completed phase 1 of the refurbishment program, demonstrating the ability to safely hoist gold ore and waste material through the existing shaft;
  • Initial phase 1 capacity supporting approximately 200 tonnes per day;
  • Additional infrastructure upgrades planned as part of phase 2 and phase 3, which are expected to optimize the system and support higher hoisting rates to 700 tonnes per day and 2,000 tonnes per day;
  • All major equipment required for phase 2 of the shaft refurbishment is now on site, with installation and associated upgrade work under way;
  • Phase 1 and phase 2 reach Level 10 at approximately 500 metres depth, which can hoist material from the active mining complexes in Austin and South Austin while phase 3 will support material haulage from deeper in the mine, potentially at Level 17;
  • The phased approach allows the company to progressively commission the shaft while continuing to invest in the infrastructure required to unlock its full long-term value.

Shane Williams, president and chief executive officer, commented: "The phased refurbishment of the Madsen shaft represents an important investment in the long-term growth of the mine. As mining advances to deeper levels, the shaft will complement underground truck haulage by providing an additional means of moving ore and waste to surface at much lower costs while reducing haulage distances and improving operational flexibility. While underground trucks will continue to play an important role throughout the mine, the shaft is expected to improve operating efficiency and contribute to lower operating costs and all-in sustaining costs over time."

Phase 1 has successfully demonstrated an initial hoisting capability of approximately 200 tonnes per day, and the company will continue advancing the remaining infrastructure upgrades before increasing the shaft's hoisting capacity. Planned work includes upgrades to the hoisting system intended to maximize the long-term efficiency, reliability and capacity of the shaft.

Background

Historically, the Madsen shaft served as the mine's primary material haulage system for approximately five decades, providing access to mining operations as deep as Level 26, which is the bottom of the shaft. The current refurbishment program is designed to restore the shaft to its historical design capacity of approximately 2,000 tonnes per day, supporting the company's long-term mine plan as mining advances into deeper levels of the mine.

Qualified person

The technical information presented in this news release has been reviewed and approved by Will Robinson, PGeo, vice-president of exploration for West Red Lake Gold and the qualified person for exploration at the West Red Lake Project, and Hayley Halsall-Whitney, PEng, vice-president of operations for West Red Lake Gold and the qualified person for technical services at the West Red Lake project, as defined by National Instrument 43-101, Standards of Disclosure for Mineral Projects. Mr. Robinson and Ms. Halsall-Whitney are not independent of West Red Lake Gold.

About West Red Lake Gold Mines Ltd.

West Red Lake Gold Mines is a Canadian gold producer and developer advancing a high-grade, district-scale opportunity in the Red Lake district of Ontario. The company's flagship Madsen mine has recently achieved commercial production and is positioned as the central hub of a growing multiasset platform. The company controls a 47-square-kilometre land package in one of the world's most prolific mining districts, which has historically produced over 20 million ounces of gold from high-grade systems. West Red Lake also owns the Rowan property in Red Lake, covering 31 square kilometres, which includes three past-producing mines (Rowan, Mount Jamie and Red Summit) and represents a key source of future production growth.

We seek Safe Harbor.

© 2026 Canjex Publishing Ltd. All rights reserved.