NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR
DISSEMINATION IN THE UNITED STATES
HIGHLIGHTS
- Record of 3,853 tonnes of copper in concentrate produced in month of
June 2012
- Concentrate grade of 26.2% exceeds nameplate capacity
- Stage 1 HMS plant on track to achieve production level of 35,000 tonnes
per annum
PERTH, Western Australia, July 25, 2012 /CNW/ - Tiger Resources Limited
(ASX/TSX: TGS, "Tiger") is pleased to provide an update on the recent
production performance of the Stage 1 HMS (heavy media separation)
plant at its Kipoi Copper Project in the Democratic Republic of Congo
(DRC).
During the month of June 3,853 tonnes of copper was produced in
concentrate, exceeding the previous record production achieved in March
of 3,506 tonnes. Copper produced in concentrate for Q2 2012 was a
record 10,233 tonnes.
| | | | | | | | | | | | | | | | | | | | | |
Kipoi Copper Project | | |
| | | April | | | May | | | June | | | Q2 2012 | | | Q1 2012 | | | YTD 2012 |
Ore processed
| | |
Tonnes
| | |
88,637
| | |
89,036
| | |
87,173
| | |
264,866
| | |
230,805
| | |
495,671
|
Head Grade
| | |
%
| | |
6.30%
| | |
6.44%
| | |
7.79%
| | |
6.83%
| | |
6.57%
| | |
6.71%
|
Recovery
| | |
%
| | |
54.1%
| | |
58.5%
| | |
56.8%
| | |
56.5%
| | |
51.0%
| | |
54.0%
|
Concentrate produced
| | |
Tonnes
| | |
14,205
| | |
13,216
| | |
14,680
| | |
42,101
| | |
37,506
| | |
79,607
|
Copper produced
| | |
Tonnes
| | |
3,020
| | |
3,360
| | |
3,853
| | |
10,233
| | |
7,733
| | |
17,966
|
Concentrate grade
| | |
%
| | |
21.3%
| | |
25.4%
| | |
26.2%
| | |
24.3%
| | |
20.6%
| | |
22.6%
|
The production performance represents a significant step-up in the
quarterly production statistics.
Tiger believes that earlier teething issues experienced during the HMS
plant's ramp-up phase have now been successfully resolved.
Consistency in the plant's operational performance has enabled
management to focus on process enhancement and efficiency, as evidenced
by the improvement in the copper concentrate grade in June to 26%.
Mr Brad Marwood, the Managing Director of Tiger said: "The HMS plant
produced 17,966 tonnes of copper in the first half of 2012, and at this
rate is well on track to meet its expected annual average production
level of approximately 35,000 tonnes".
"The HMS plant is demonstrating levels of performance and product
consistency that have made it possible for us to commit to export
sales. Our team is now focussing on driving cost efficiencies to
maximise cash generation from the plant."
Tiger plans to use cash flows generated from the Stage 1 HMS operations
to construct a Stage 2 SXEW (solvent extraction electro-winning)
processing plant at Kipoi with a capacity to produce 50,000 tonnes per
annum of copper cathode. The definitive feasibility study (DFS) for
the Stage 2 SXEW processing plant is progressing well. Tiger has
appointed a Project Manager to commence the Stage 2 tender process and
project implementation planning, to run in parallel with the completion
of DFS activities, in anticipation of an early commitment to the Stage
2 development.
Background
The Kipoi Project (Tiger: 60%) covers an area of 55 square km and is
located 75km north‐north‐west of the city of Lubumbashi in the Katanga
Province of the DRC. The project contains a 12km sequence of
mineralised Roan sediments that host at least five known deposits:
Kipoi Central, Kipoi North, Kileba, Judeira and Kaminafitwe.
The Company has reported JORC-compliant resources at three of the
deposits: Kipoi Central, Kipoi North and Kileba. The principal deposit
is Kipoi Central, which contains a zone of high grade copper
mineralisation within a much larger, lower grade global resource.
The Company has adopted a staged development approach at the Kipoi
Project. The high grade zone of mineralisation at Kipoi Central is
being exploited during the Stage 1 development. During the three-year
operation of Stage 1, 900,000tpa of 7% Cu is planned to be processed
through the HMS plant with a recovery rate of 55%, to produce the
equivalent of approximately 35,000tpa of copper.
Caution Regarding Forward Looking Statements: The forward-looking
statements made in this news release are based on assumptions and
judgments of management regarding future events and results. Such
forward-looking statements involve known and unknown risks,
uncertainties, and other factors which may cause the actual results,
performance or achievements of the Company to be materially different
from any anticipated future results, performance or achievements
expressed or implied by such forward-looking statements. Such factors
include, among others, the actual results of current exploration, the
actual results of future mining, processing and development activities,
changes in project parameters as plans continue to be evaluated, as
well as those factors disclosed in the Company's filed documents.
The information in this report that relates to Exploration Results,
Mineral Resources or Ore Reserves is based on information compiled by
Mr. Brad Marwood who is a Fellow of The Australasian Institute of
Mining and Metallurgy. Mr Marwood is a Director and full-time employee
of the Company.
Mr Marwood has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration and to the
activity which he is undertaking to qualify as a Competent Person as
defined in the 2004 Edition of the 'Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves'. Mr Marwood
consents to the inclusion in the report of the matters based on his
information in the form and context in which it appears.
SOURCE: Tiger Resources Limited
<p> For further information in respect of the Company's activities please contact: </p> <p> <b>Brad Marwood</b><br/> Managing Director<br/> Tel: (+61 8) 6188 2000<br/> Email: <a href="mailto:bmarwood@tigerez.com">bmarwood@tigerez.com</a> </p> <p> <b>Stephen Hills</b><br/> Chief Financial Officer<br/> Tel: (+61 8) 6188 2000<br/> Email: <a href="mailto:shills@tigerez.com">shills@tigerez.com</a> </p> <p> <b>Nathan Ryan</b><br/> Investor Relations<br/> Tel: (+61 0)420 582 887<br/> Email: <a href="mailto:nryan@tigerez.com">nryan@tigerez.com</a><br/> <br/> <b>Company website: </b><a href="http://www.tigerresources.com.au">www.tigerresources.com.au</a> </p>