2026-11-17 09:03 ET - News Release

Mr. Cliff Cain reports

PULSAR HELIUM RECEIVES TSX VENTURE EXCHANGE FINAL ACCEPTANCE FOR COMMERCIAL-SCALE HELIUM LIQUEFACTION AND CO2 PLANT

Further to its announcements dated June 30, 2026, Aug. 3, 2026, and Oct. 1, 2026, Pulsar Helium Inc. has received final acceptance from the TSX Venture Exchange of the commercial proposal entered into by the company, through its wholly owned subsidiary, Pulsar Helium MN Inc., with Chart Energy & Chemicals Inc., a wholly owned subsidiary of Baker Hughes Company, for the supply of equipment for Pulsar's proposed rare-gas hub in Minnesota.

The proposal provides for the supply of equipment for: (i) a helium purification and liquefaction plant with capacity of 861 litres per hour, equivalent to approximately 7.5 million litres of liquid helium (approximately 200 million standard cubic feet of gaseous helium) annually at continuous nameplate operation; and (ii) a CO2 (carbon dioxide) plant with 300-tonne-per-day capture capacity, expected to produce over 100,000 tonnes of liquid CO2 annually.

Certain additional components relating to the CO2 plant, including CO2 storage and loading and site support services, are outside the current equipment supply scope and will be addressed separately. Equipment manufacture is scheduled to take place over an approximately two-year period following receipt of the Milestone 2 (as defined below) payment. Certain equipment included in the proposal and relating specifically to the helium liquefaction system has already been manufactured.

The aggregate equipment supply price is $85.5-million (U.S.), payable entirely in cash in stages on achievement of milestones. The price is not the total installed cost of the plant and excludes taxes, duties and tariffs, installation and commissioning, site infrastructure and interconnections, and certain other owner and third party costs.

Following receipt of TSX-V final acceptance on Nov. 3, 2026, the company has paid to Chart $5,025,000 (U.S.) under the proposal from existing cash resources (the first payment). The first payment comprised the 5-per-cent initial milestone of $4,275,000 (U.S.) (Milestone 1) and the $750,000 (U.S.) milestone payment under the existing limited notice to proceed (LNTP). All LNTP amounts (totalling $1-million (U.S.), including the $250,000 (U.S.) deposit previously paid) are credited dollar for dollar against amounts payable under the proposal.

A payment of $8.55-million (U.S.) is scheduled for Jan. 31, 2027, and will authorize procurement of long-lead items (Milestone 2). If it is not paid by that date, the project automatically enters a suspension period of up to 180 days, during which the reserved helium liquefaction equipment remains protected, Pulsar has no obligation to pay Milestone 2, and no cancellation charge arises solely from the suspension. At the end of the suspension period, the parties will seek to agree whether to proceed, amend the commercial arrangements or terminate the project. The company currently intends to finance this payment out of existing cash resources.

The remaining milestones, which together with the above comprise the full $85.5-million (U.S.), are tied to engineering, procurement, manufacture and delivery readiness activities, including issuance of piping and instrumentation diagrams (P&IDs) for hazard and operability review and for manufacturing, ordering of pretreatment and column major materials, confirmation that all major equipment is ready for shipment, and Chart's submission of final documentation. The company continues to advance financing alternatives for the remaining payments.

Cancellation provisions

If Pulsar terminates for convenience, cancellation payments depend on the stage of work completed, ranging from 0 per cent at project award to a maximum of 70 per cent of the total contract value after Chart delivers final project documentation, and no cancellation payment arises for a milestone unless its payment had become due and been paid.

No finders' fees are payable in connection with the transaction. Chart is an arm's-length party to the company.

About Pulsar Helium Inc.

Pulsar Helium is a publicly traded company quoted on the AIM (Alternative Investment Market) of the London Stock Exchange (United Kingdom) and listed on the TSX-V with the ticker PLSR (Canada) as well as on the OTCQB with the ticker PSRHF (United States). Pulsar's exploration and development portfolio comprises its flagship Topaz helium project in Minnesota and the Falcon project in Michigan (both in the United States) and the Tunu helium project in Greenland. Pulsar is the first mover in these project locations, with primary helium occurrences not associated with the production of hydrocarbons identified at each. Separately, the company is advancing its proposed rare-gas hub in Minnesota.