Monument Mining begins Selinsing plant production

2024-01-19 00:31 ET - News Release

Ms. Cathy Zhai reports

MONUMENT ANNOUNCES UPDATE AT THE SELINSING GOLD MINE IN MALAYSIA

Monument Mining Ltd. has provided an update at the Selinsing gold mine, where the company recently achieved commercial production of its newly constructed flotation processing plant.

President and chief executive officer Cathy Zhai commented: "We are very pleased with the continued progress and optimization of the Selinsing sulphide gold flotation plant. The production is expected to be stabilized in the 2024 calendar year and cash flow sustained. Longer-term offtake contracts are in progress. Export permits continue to be renewed every six months with government support. Gold prices are above the $2,000-per-ounce level in the new year, which is in our favour."

Ms. Zhai emphasizes: "In 2024, we will provide further training to our senior management with a value-added approach to lead to excellent performance. Our corporate focus in 2024 is business development in Malaysia, Western Australia and elsewhere. We are positioning Monument to be a fully funded producing company with upside growth potential to realize shareholder value in the marketplace."

At the opening of this new year, the production objective of the Selinsing gold mine is to streamline and optimize the flotation plant and operations to achieve the best financial performance. The company continues to improve operational efficiencies through consolidating Selinsing operating activities and resources, and removal of bottlenecks including: plant performance improvements, mining cycle harmonization, tailing storage facilities upgrade, refining the gold concentrate warehousing, the shipping and sales process, and security enhancements.

Plant process improvements

The flotation plant achieved the design capacity of 119 tonnes per hour in early December, 2023; however, mill feed rate continues to be hampered by the bottleneck at the McLanahan filter press. Recent improvements to the filter press operation have included the installation of pressure regulators to reduce the compressed air pressure for the core blow and cake dry cycles. The pressure reduction has certainly reduced the frequency of filter cloth failure. Torn filter cloths have been replaced as required by local and internationally sourced cloths. Worn filter plates are being repaired locally, and new units have been ordered from the manufacturer and are expected to arrive at site in March, 2024.

Continuing plant improvements included an upgrade to the concentrate thickener underflow pipeline to the filter press surge tank. One of the concentrate thickener overflow pumps was replaced with a bigger pump along with a new pipeline. A standby pump will be installed once refurbishment work is completed. Modifications to the cleaner flotation circuit were initiated to allow cleaning of the first rougher concentrate to produce a cleaner final concentrate during processing of transition ore types.

Flotation recovery continued to be variable due to the inconsistent quality of the transition ores processed. New flocculant was received for the water recovery thickener, allowing the flotation circuit to operate at the design of pH 9.0 to 9.5. Dosing of the sulphidizing agent sodium sulphide continued along with copper sulphate as activator. Daily recoveries of over 80 per cent and some times 90 per cent were recorded, with reconciled recovery of 73.6 per cent reported for December, 2023.

Construction of the concentrate shed has been completed, and the lighting power supply connected. Roofing was installed over the rougher and cleaner flotation cells. The one-tonne bulk bagging system was delivered to Port Klang and transported to the Selinsing site. The contract for the new flotation tailings hopper was awarded and fabrication initiated. Civil works commenced in mid-December, 2023, and installation of the tailings hopper and associated pipework is scheduled in the first week of February, 2024.

The procurement plan and strategies have been tabled for review by focusing on critical spare parts for the sulphide flotation plant and by allocating resources to enhance this improvement with the aim to avoid any unforeseen stoppage of plant operations.

Mining and ore stockpile buildup

Mining of Buffalo Reef pits continued with stages 1 and 2 mined at BRC2 and BRC3 pits and Stage 1 started at BRC4. Delivery of fresh and transition ore continued, and the run-of-mine (ROM) stockpile was increased to 255,000 tonnes, which is over three months processing plant capacity, at the end of December, 2023, and critically ahead of the imminent northeastern monsoon season.

A new three-year mining contract was negotiated with the long-term mining contractor Minetech, starting Jan. 1, 2024. Ten grade control drilling rigs are currently operational and performing well. The Minetech fleet of eight excavators and around 40 dump trucks have shown good availability.

To smooth mining cycle, capacity of the preparation lab has been reviewed and improved with two new pulverizers installed at the new sample preparation laboratory. The ventilation system has been installed, and is under commissioning to improve the working environment and avoid contamination.

Routine deliveries of ammonium nitrate emulsion to the Austin powder explosives depot continued. The site-based 13-tonne capacity emulsion tanker was replaced by a 16-tonne capacity unit, and blasting was carried out on up to five days per week as required.

Construction of the TSF upgrade resumed in August, 2023. Zone A and Zone C fill to 540 metres relative level was completed at the main embankment, and the upstream slope was lined with rip-rap to protect against erosion. Construction of the TSF south embankments was completed, and rip-rap placed on the upstream slopes. The new spillway will be constructed in January, 2024, followed by the installation of the seepage sumps and related pipework at the toe of the main embankment. The overall TSF upgrade is expected to be completed by February, 2024.

Gold concentrate shipments and sales

To date, the flotation plant has produced over 16,000 tonnes of concentrates at a grade of 37 grams per tonne gold. Shipments have been made to three separate buyers, and negotiations continue with several potential new customers. To date, over 12,500 tonnes of concentrate have been delivered to Johor and Port Klang free zones. Export permits have been renewed with the relevant state authorities as required. Transport of the latest delivery of 3,500 wet metric tonnes to Port Klang free zone has been completed with vessel to depart in mid-January, 2024. Sale of a further 3,000 tonnes of concentrate currently available has been finalized, and shipment preparation of the concentrate to the port is in progress.

Warehouse review and improvements are continuing, including tightening up of security features.

Stock compensation

To reward the success of placing the sulphide gold project into commercial production, the company also announces that the board has granted under its equity compensation plans a total 3.4 million restricted share units and 3.8 million incentive stock options to its directors, officers and employees. Each stock option is exercisable at a price of 14.5 cents for a term of five years from the date of grant with a three-year vesting period.

About Monument Mining Ltd.

Monument Mining (TSX Venture Exchange: MMY and Frankfurt Stock Exchange: D7Q1) is an established Canadian gold producer that 100 per cent owns and operates the Selinsing gold mine in Malaysia and the Murchison gold project in the Murchison area of Western Australia. It has a 20-per-cent interest in the Tuckanarra gold project, jointly owned with Odyssey Gold Ltd., in the same region. The company employs approximately 250 people in both regions, and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighbouring communities.