Irruptive receives authorization for Pimenton drilling

2026-11-17 15:41 ET - News Release

Mr. Alfredo Bazo reports

IRRUPTIVE METALS PREPARES FOR DRILLING SEASON ON PIMENTON CU-AU PROJECT, CHILE

Irruptive Metals Corp. has provided an update regarding its exploration and drilling plans for the fourth quarter of 2026 and the first quarter of 2027 at the Central copper-gold porphyry system within its Pimenton project, located in Region V of central Chile.

The company has received authorization that will allow for up to 10,000 metres of diamond drilling during the 2026/2027 drilling season. This authorization, together with the company's current cash position, is expected to allow the company to substantially scale up its exploration program at the Central system. The company is advancing snow removal and rehabilitation of the access road to the project. This work has been hampered by an unusually severe and extended winter season associated with the El Nino phenomenon, which has brought significant precipitation and heavy snowfall throughout the central Andes of Chile.

Irruptive Metals' president and chief executive officer, Alfredo Bazo, commented: "Our initial 3,084-metre drill program demonstrated that the Central system has significant potential as a copper-gold porphyry system. With authorization secured, our team is positioned to execute a diamond drilling campaign of up to 10,000 metres this season. We expect the current drilling program, together with the approximately 2,900 metres of historical drill core resampled to date, to support the expansion of the mineralized envelope as the company advances toward the estimation of a maiden inferred mineral resource prepared in accordance with NI 43-101."

Outlook and next steps -- fourth quarter of 2026 and first quarter of 2027:

  • Drilling expansion: Up to 10,000 metres of diamond drilling are planned for the coming field season, subject to weather conditions, with the objective of advancing the project toward resource definition.
  • Historical core resampling: Approximately 2,900 metres of historical drill core have been resampled. Assay results for historical drill holes PP18, PP04 and PP13 are expected late in the fourth quarter of 2026.
  • Target focus: The drilling campaign for the fourth quarter of 2026 and the first quarter of 2027 is intended to test the lateral and depth extensions of the Central system, where mineralization identified to date remains open.
  • Path to maiden resource: Data from the expanded drilling program and the historical core resampling are expected to be incorporated into an updated technical report prepared in accordance with National Instrument 43-101, Standards of Disclosure for Mineral Projects, which the company anticipates will include a maiden inferred mineral resource estimate for the project. The updated technical report is expected in the fourth quarter of 2027.
  • Additional fieldwork, metallurgical testing and permitting:
    • Conduct geometallurgical sampling and mineralogical/metallurgical test work (SGS Chile) to support the estimation of copper-gold recoveries for the anticipated maiden mineral resource estimate;
    • During January to February, 2027, conduct detailed geological mapping and geochemical sampling to refine early-stage targets (Ridge-Bx, SE, Maria Elena and Verde) in support of the next drilling program;
    • Seek environmental authorization (by way of a carta de pertinencia, a formal determination as to whether an environmental impact assessment is required) to conduct drilling at the Central, Ridge-Bx and Maria Elena targets between the fourth quarter of 2027 and the second quarter of 2029;
    • Advance preparation of a declaracion de impacto ambiental (DIA, an environmental impact statement) for submission in the fourth quarter of 2027, with the objective of progressing toward a prefeasibility study commencing in the third quarter of 2029.

No mineral resource or mineral reserve has been estimated on the project, and there is no certainty that the planned work will result in the estimation of a mineral resource. Mineralization described in this news release is not necessarily indicative of the presence of a mineral resource or mineral reserve.

Quality assurance and quality control

Drill core from the company's initial 3,084-metre drill program was logged, photographed and sampled by company geologists at the company's secure core logging facility in Los Andes, Region V, Chile. Core was sawn in half, with one-half sent for analysis and the other half retained for future reference. Sample intervals were generally two metres in length, adjusted to respect geological and lithological contacts. Samples were bagged, sealed and kept under the company's chain of custody until delivered to the AGS-Cotecna laboratory in Coquimbo, Region IV, Chile, which is accredited to ISO/IEC 17025 and is independent of the company.

Samples were prepared by crushing to 70 per cent passing two millimetres and pulverizing a split to 85 per cent passing 75 microns. Gold was analyzed by 30-gram fire assay with atomic absorption finish, and copper and other elements were analyzed by four-acid digestion (HF-HNO3-HClO4-HCl) followed by ICP-OES, with overlimit copper samples reanalyzed by ore-grade methods. The company's QA/QC program includes the insertion of certified reference materials (5 per cent), blanks (2.5 per cent) and field duplicates (2.5 per cent) at regular intervals, in addition to the laboratory's internal QA/QC procedures. No material QA/QC issues were identified in the data reviewed.

Intervals are reported using a cut-off grade of 0.2 per cent copper equivalent (CuEq), with a maximum of three consecutive samples (six metres) of internal dilution below cut-off and no top-cut applied. CuEq is calculated as copper per cent plus (gold grams per tonne multiplied by 0.86), using two-year average (2024/2025) metal prices of $4.95 (U.S.) per pound Cu and $2,918 (U.S.) per ounce Au. No metallurgical recovery test work has been completed on the project; equal recoveries have been assumed for all metals for illustrative purposes only. CuEq is used for comparison purposes only and the reported CuEq values may not be representative of recoverable or economically recoverable metal.

All reported intervals are downhole core lengths. True widths have not yet been determined and are expected to be less than the reported downhole lengths. The qualified person has verified the data disclosed in this news release, including the sampling, analytical and test data underlying the information, by reviewing assay certificates, QA/QC results and drill logs. There were no limitations on the verification process.

Qualified person

The scientific and technical information in this news release has been reviewed and approved by Claudio Burgoa, PGeo, chief geologist of Irruptive Metals, who is a qualified person for purposes of NI 43-101 and is registered as qualified person (No. 535) with the Comision Minera de Chile.

About Irruptive Metals Corp.

Irruptive Metals is a Canadian copper-gold exploration company focused on unlocking value from high-quality mineral projects in Chile. The company's flagship Pimenton project is strategically located within one of the world's most prolific porphyry copper-gold belts and has been the subject of extensive historical exploration by major mining companies, underscoring its significant discovery potential.