07:32:44 EDT Sun 19 May 2024
Enter Symbol
or Name
USA
CA



Gratomic Inc (2)
Symbol GRAT
Shares Issued 195,088,454
Close 2023-05-09 C$ 0.31
Market Cap C$ 60,477,421
Recent Sedar Documents

Gratomic outlines engineering work at Aukam plant

2023-05-09 11:41 ET - News Release

Mr. Arno Brand reports

GRATOMIC INFORMS OPERATIONAL UPDATE ON THE AUKAM MINE SITE

Gratomic Inc. has provided the following operational update for its 100-per-cent-owned Aukam graphite mine and processing plant located 200 kilometres east of the port of Luderitz in Namibia.

In April, Gratomic's technical team arrived at the Aukam mine site to advance the plant in order to batch process 100 tonnes of a high-purity graphite concentrate which will be shipped to industry partners in Asia, Europe and United States for integration into end-user applications. This program completes the company's operational readiness ahead of commercial production and is contemplated to run through mid-August. This work will complete the installation of the polishing mill and the stirred media mill. These two mills are designed to remove minor impurities from the surface of graphite particles to attain the specification required by customers. This circuit should be installed at the Aukam site by mid-June.

The processing plant is designed to operate optimally at a graphite feed grade of 35 per cent. From previous programs and test results, Gratomic was able to achieve an average grade between 94.8 per cent and 97.3 per cent, with a recovery between 87 per cent and 94 per cent (see press release of Dec. 20, 2021, with metallurgical results).

Within the next 60 days, the company's engineering team will carry out the following actions to prepare for delivery of the final product:

  • Complete the final assembly of the modified flotation columns and spargers;
  • Set up and level the base frames for the flotation columns;
  • Install a cover for the reagent area;
  • Install the dosing pumps for the frother;
  • Assemble and install the conditioning tanks;
  • Construct the sumps for the flotation columns;
  • Connect the air lines for the flotation columns;
  • Connect the water feed for the flotation columns;
  • Install the upgraded cyclones at the mill discharge;
  • Install the mill feed water control system;
  • Install the head chute of CV1 conveyor belt;
  • Retrofit the CV2 and CV8 conveyor with chevron belts;
  • Install the spill boards for the run-of-mine (ROM) bin;
  • Assemble fencing for the core storage and mine access.

This work is expected to be completed in approximately 60 days.

Arno Brand, president and chief executive officer of Gratomic, stated: "We are very pleased with the progress at Aukam and look forward to the completion of our final stages and the commencement of production. I'd like to thank our entire Gratomic team for their efforts and we look forward to enhancing shareholder value and servicing our global customers."

Gratomic wishes to emphasize that no preliminary economic analysis, preliminary feasibility study or feasibility study has been completed to support any level of production. In fact, no mineral resources, let alone mineral reserves demonstrating economic viability and technical feasibility, have been delineated on the Aukam property.

The company is working toward completing a feasibility study (FS) on the Aukam processing plant. The study, its recommendations and their subsequent implementation will provide conclusions and recommendation at an FS level of comfort relating to the scale-up of the existing processing plant to a commercial-scale processing facility capable of producing the desired concentrate grades and production rates.

Gratomic wishes to emphasize that the supply of graphite is conditional on Gratomic being able to bring the Aukam project into a production phase, and for any graphite being produced to meet certain technical and mineralization requirements. Gratomic continues to move its business toward production, and as part of its business plan, expects to file a National Instrument 43-101 Standards of Disclosure for Mineral Projects resource estimate in Q3 2023.

Risk factors

No mineral resources, let alone mineral reserves demonstrating economic viability and technical feasibility, have been delineated on the Aukam property. The company is not in a position to demonstrate or disclose any capital and/or operating costs that may be associated with the processing plant until the FS (feasibility study) is completed.

The company advises that it has not based its production decision on even the existence of mineral resources, let alone on a preliminary feasibility study or FS of mineral reserves, demonstrating economic and technical viability, and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially minable deposit.

Historically, such projects have a much higher risk of economic and technical failure. There is no guarantee that production will begin as anticipated or at all or that anticipated production costs will be achieved.

Failure to commence production would have a material adverse impact on the company's ability to generate revenue and cash flow to finance operations. Failure to achieve the anticipated production costs would have a material adverse impact on the company's cash flow and future profitability.

About Gratomic Inc.

Gratomic is a multinational company with projects in Namibia, Brazil and Canada. The company aims to become a leading graphite supplier and to secure a strong position in the electric vehicle battery supply chain through the development of its flagship Aukam graphite mine and continuing exploration at the Capim Grosso property. The company will continue to explore graphite opportunities that show the potential to produce the specific flake size and purity required for active anodes.

Large quantities of high-quality vein graphite have been shipped for testing to confirm its suitability as anode material. Gratomic is confident that the test results will provide a unique competitive advantage in the desired target markets. The company will continue to update the public on the status of these tests and will share results as they become available.

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.