VANCOUVER, May 15, 2012 /CNW/ - Great Basin Gold Ltd. ("Great Basin
Gold" or the "Company"), (TSX: GBG) (NYSE: GBG) (Amex: GBG) (JSE: GBG)
announces that its interim consolidated financial statements and
Management Discussion and Analysis for the quarter ended March 31, 2012
have been filed, and the Company refers the reader to those materials
for further information. All currency values in this release are
stated in Canadian dollars unless otherwise indicated. The Company
will review the results during an investor conference call scheduled
for May 15, 2012.
|
|
3 months ended
|
| March 31 2012
| March 31 2011
|
|
Recovered Au eqv oz
|
22,911
|
29,593
|
|
Au eqv oz sold
|
21,555
|
20,118
|
|
Realized Au eqv price
| $1,548 | $1,309 |
|
Revenue ($'000)
| $33,373 | $26,343 |
|
Loss from operating activities ($'000)
|
($7,650)
|
($377)
|
|
Net loss for the quarter ($'000)
|
($17,770)
|
($20,341)
|
|
Cash generated from (utilized by) operations ($'000)
| $565 |
($9,482)
|
|
Adjusted loss per share
|
($0.03)
|
($0.02)
|
Hollister
The Nevada operations produced 16,240 Au eqv oz1 for the quarter (Q1 2011: 24,082 Au eqv oz), compared to the forecast
of 19,749 Au eqv oz. Ineffective carbon stripping, while the final
upgrade to the acid wash and carbon regeneration circuit was being
completed, resulted in lower than planned Au (87%) and Ag (62%)
recoveries at the Esmeralda mill during the quarter. The upgrade to
this circuit was completed in late April 2012. All doré will be poured
on site starting May 2012.
Although lower than Q1 2011, Au and Ag grades as well as tonnes
extracted from trial mining were in-line with the production plan and
good progress has been made in improving mining flexibility through
additional focus on ore development. 15,357 Au eqv oz were sold during
the quarter (Q1 2011: 17,324) with the amount of Au eqv oz locked up in
carbon and awaiting processing through third party refiners increasing
by 1,352 to 14,447 Au eqv oz on March 31, 2012. It is expected that
this carbon will be treated during Q2 2012 and inventory levels will
return to normalized levels by the end of Q2 2012. Cash costs per ounce
of $850/oz were recordedfor the quarter (Q1 2011: $670); costs were impacted by the lower
recoveries achieved as well as the additional transportation costs
incurred to process the carbon at the Rand Refinery in South Africa.
Following the recent receipt of the Dam Safety Permit (which authorizes
the impounding of tails, slimes and water on the TSF) and the updated
reclamation bond, construction commenced on the three-phase expansion
of the tailings storage facility (TSF). At the currently planned
production rates, Phase 1 and 2 will provide tailings storage capacity
for the next 6 years and the completion of Phase 3 can extend this to
25 years. The current facility has sufficient capacity for the
impoundment of tails until the planned completion of the expanded
tailings facility.
Burnstone
The Burnstone operations produced 6,671 Au oz for the quarter (Q1 2011:
5,511 Au oz), compared to the forecast of 6,327 Au oz. Production
volumes were generally in-line with the production plan with a slightly
higher stoping Au grade compensating for minor volume variances. Square
meters available for stoping more than doubled from December 31, 2011
with over 14,000 square meters being available at March 31, 2012.
Available square meters has increased further since that time with
approximately 16,200 square meters being available for stoping at the
end of April 2012. Good progress was made during the quarter on
infrastructure upgrades that will enable the mine to maintain its
momentum to meet increasing development and production targets. Cash
costs per ounce for the quarter of $2,181 were recorded (Q1 2011:
$2,471) and were impacted by additional water handling and employee
related costs incurred.
Financial results and corporate matters
Revenue of $33 million was recorded for the quarter, an increase of 27%
over the comparative period in 2011. The increase in revenue can be
ascribed to a 7% increase in ounces sold as well as an 18% increase in
the realized gold price. The increase in cash and non-cash costs had a
negative impact on the loss from operations which amounted to $7.7
million (2011: $0.4 million). A $2 million increase in net interest
paid when compared to Q1 2011 is due to interest for January 2011 being
included in the Burnstone project development costs. A further $2.6
million impairment charge on the loan advanced to our Black Economic
Empowerment partner (TranterBurnstone (Pty) Ltd ("Tranter")) was recorded as a result of the decline
in the Company's share price. The valuation of the zero-cost-collar
hedge structures was immaterial for the quarter as a result of the
relative sideways movement in gold prices during this period.
The Company closed the previously announced $50 million public offering
(see press release March 15, 2012) on March 30, 2012 with the 15%
over-allotment option granted to the Underwriters closing on April 5,
2012. Net proceeds from the Offering, totalling $54 million, will be
used as working capital for the development and production ramp up at
Burnstone. At March 31, 2012, the Company had net working capital of
$15 million, which included $44 million in cash reserves, and also had
$10 million available to be drawn upon under the US$150 million term
facility.
Following negotiations between the Company, Tranter and Investec Bank
Limited ("Investec"), a Term sheet was agreed to in late April 2012 to
settle a mutually beneficial proposal whereby the Company provides
Tranter with further financial assistance over a period of 18 months to
enable them to meet their proposed restructured loan repayment
obligations to Investec and thereby remove their current breach of the
loan agreement. In terms of the proposal, Investec will remove all cash
margin requirements and also restructure the repayment in such a matter
that the required assistance from the Company does not impact on its
short term cash requirements. The parties are currently working on
finalizing the legal agreements and obtaining the required approvals to
enter into the binding legal agreements. It is anticipated that this
restructured loan and financial assistance agreement will be executed
before May 30, 2012.
Ferdi Dippenaar, Great Basin Gold President and CEO, commented: "Good progress has been made at both Hollister and Burnstone during the
first quarter of 2012. The focus has been to improve mining
flexibility through the increase in ore development and the
establishment of additional stopes, thereby enabling the Company to
meet its annual production targets.
Burnstone achieved its planned quarterly production targets whilst
addressing short-term infrastructural challenges, which impacted on
efficiencies in late 2011 and the first few months of 2012. This has
resulted in a 6% increase in ore development meters, up from a monthly
average of 845 meters in Q1 2012 to over 900 meters in April 2012. In
addition, ore development ends at the end of April were 62, which is an
improvement of 48% over the 42 ends available on March 31, 2012.
Continued infill drilling has shown no further geological challenges
similar to the Graben fault that significantly influenced our
production build-up at Burnstone in 2011.
The operational benefit from increased flexibility at our Hollister Mine
and the completion of the acid wash and carbon regeneration circuit at
the Esmeralda Mill is expected to allow cash costs from trial mining
activities to decrease to the planned levels for the year."
Ferdi Dippenaar
President and CEO
Shareholders of the Company are reminded that they may request a hard
copy of the complete audited financial statements free of charge upon
request from any of the Investor Services personnel above or from the
Company's Corporate Office at Tel: +27 (0) 11 301 1800, Fax: +27 (0) 11
301 1840 or Email: info@za.grtbasin.com.
This document contains "forward-looking statements" that were based on
Great Basin Gold's expectations, estimates and projections as of the
dates as of which those statements were made. Generally, these
forward-looking statements can be identified by the use of
forward-looking terminology such as "outlook", "anticipate", "project",
"target", "believe", "estimate", "expect", "intend", "should" and
similar expressions. Forward-looking statements are subject to known
and unknown risks, uncertainties and other factors that may cause the
Company's actual results, level of activity, performance or
achievements to be materially different from those expressed or implied
by such forward-looking statements. These include but are not limited
to:
-
uncertainties and costs related to the Company's exploration and
development activities, such as those associated with determining the
extent of mineral resources or reserves which exist on a property;
-
uncertainties related to feasibility studies that provide estimates of
expected or anticipated costs, expenditures and economic returns from a
mining project; uncertainties related to expected production rates,
timing of production and the cash and total costs of production and
milling;
-
uncertainties related to the ability to obtain necessary licenses,
permits, electricity, surface rights and title for development
projects;
-
operating and technical difficulties in connection with mining
development activities;
-
uncertainties related to the accuracy of our mineral reserve and mineral
resource estimates and our estimates of future production and future
cash and total costs of production, and the geotechnical or
hydrogeological nature of ore deposits, and diminishing quantities or
grades of mineral reserves;
-
uncertainties related to unexpected political, judicial or regulatory
proceedings;
-
changes in, and the effects of, the laws, regulations and government
policies affecting our mining operations, particularly laws,
regulations and policies relating to
-
mine expansions, environmental protection and associated compliance
costs arising from exploration, mine development, mine operations and
mine closures;
-
expected effective future tax rates in jurisdictions in which our
operations are located;
-
the protection of the health and safety of mine workers; and
-
mineral rights ownership in countries where our mineral deposits are
located, including the effect of the Mineral and Petroleum Resources
Development Act (South Africa);
-
changes in general economic conditions, the financial markets and in the
demand and market price for gold, silver and other minerals and
commodities, such as diesel fuel, coal, petroleum coke, steel,
concrete, electricity and other forms of energy, mining equipment, and
fluctuations in exchange rates, particularly with respect to the value
of the U.S. dollar, Canadian dollar and South African rand;
-
unusual or unexpected formation, cave-ins, flooding, pressures, and
precious metals losses (and the risk of inadequate insurance or
inability to obtain insurance to cover these risks);
-
changes in accounting policies and methods we use to report our
financial condition, including uncertainties associated with critical
accounting assumptions and estimates;
-
environmental issues and liabilities associated with mining including
processing and stock piling ore;
-
geopolitical uncertainty and political and economic instability in
countries which we operate; and
-
labour strikes, work stoppages, or other interruptions to, or
difficulties in, the employment of labour in markets in which we
operate mines, or environmental hazards, industrial accidents or other
events or occurrences, including third party interference that
interrupt the production of minerals in our mines.
Cautionary Note regarding Non-GAAP Measurements
Cash cost per ounce/tonne is a not a generally accepted accounting
principles ("GAAP") based figure but rather is intended to serve as a
performance measure providing some indication of the mining and
processing efficiency and effectiveness of operations. It is determined
by dividing the relevant mining and processing costs including
royalties by the ounces produced/tonnes milled in the period. There may
be some variation in the method of computation of "cash cost per
ounce/tonne" as determined by the Company compared with other mining
companies. Cash costs per ounce/tonne may vary from one period to
another due to operating efficiencies, waste to ore ratios, grade of
ore processed and gold recovery rates in the period. We provide this
measure to our investors to allow them to also monitor operational
efficiencies. As a Non-GAAP Financial Measure cash costs should not be
considered in isolation or as a substitute for measures of performance
prepared in accordance with GAAP. Adjusted loss per share is also a
Non-GAAP measure and is calculated by excluding the impact of certain
fair-value accounting charges and once-off transactions. We also make
reference in our disclosures to "working capital" which is also a
Non-GAAP measure and includes cash and cash equivalents, trade and
other receivables, current inventories, trade payables and accrued
liabilities. There is material limitations associated with the use of
such Non-GAAP measures.
For further information on Great Basin Gold, investors should review the
Company's annual Form 40-F filing with the United States Securities and
Exchange Commission www.sec.com and home jurisdiction filings that are available at www.sedar.com.
_________________________
1 Gold equivalent ounces calculated using metal price of US$1,400/oz for
Au and US$30/oz for Ag.
<p> For additional details on Great Basin Gold Ltd. and its gold properties, please visit the Company's website at <a href="http://www.grtbasin.com">www.grtbasin.com</a> or contact Investor Services: </p> <p> Tsholo Serunye in South Africa 27 (0)11 301 1800<br/> Michael Curlook in North America 1 888 633 9332<br/> Barbara Cano at Breakstone Group in the USA (646) 452-2334 </p>