17:23:11 EDT Mon 29 Apr 2024
Enter Symbol
or Name
USA
CA



Equinox Gold Corp (2)
Symbol EQX
Shares Issued 312,980,933
Close 2023-11-20 C$ 6.54
Market Cap C$ 2,046,895,302
Recent Sedar Documents

Equinox's Greenstone work continues on schedule, budget

2023-11-20 10:14 ET - News Release

Mr. Greg Smith reports

EQUINOX GOLD'S GREENSTONE PROJECT: 96% COMPLETE, COMMISSIONING UNDERWAY

Equinox Gold Corp. has provided an update on construction and commissioning progress at its Greenstone project in Ontario, Canada. The Greenstone project is being developed as a 60/40 partnership, respectively, by Equinox Gold and Orion Mine Finance Group, and will be one of the largest gold mines in Canada, with average annual gold production of more than 400,000 ounces over the first five years and more than five million ounces of gold produced over its initial 14-year mine life.

All dollar amounts are shown in United States dollars unless otherwise noted.

Greenstone project construction progress is documented weekly in a photo gallery on Equinox Gold's website.

Recent highlights (at Nov. 10, 2023, unless otherwise noted):

  • Schedule -- the Greenstone project is 96 per cent complete. Precommissioning activities are continuing in most of the main process plant areas, including the crushing and grinding circuits, and wet commissioning is under way in select areas.
  • Budget -- the Greenstone project remains on target for a total spend of $1,225-million. At Sept. 30, 2023, $1,087-million (89 per cent) of the budget had been spent (100 per cent basis).
  • Facilities completed -- the realigned 4.7 kilometres of Highway 11 was opened to traffic in August and the power plant was turned over to the operations team in September, both ahead of plan. The permanent effluent water treatment plant, truck shop, warehouse, sewage treatment plant, potable water treatment plant, pit and plant site fuel stations, reagent storage, site mixed emulsion (explosives) plant, and natural gas pipeline to site were previously turned over and are all in operation.
  • Construction progress -- all major equipment is now on site and construction is 96 per cent complete. The focus is on remaining electrical and instrumentation installations in the process plant. In October, the tailings storage facility (TSF) was completed to planned elevation. Commissioning of the TSF is on schedule for December, 2023.
  • Commissioning -- precommissioning activities are ramping up in co-ordination with final construction activities, with systems checks under way at the crusher, ball mills, ore storage dome and high-pressure grinding rolls (HPGR) areas. Wet commissioning has commenced at the leach tanks and in the crusher area.
  • Preproduction mining -- the third Epiroc Pit Viper 235 drill has been commissioned. Commissioning of CAT 793F haul trucks nine and 10 are under way, and haul trucks 11 to 14, and the LeTourneau 1850 loader will be ready for service in early Q1 2024. More than 15 million tonnes of material has been moved to date, and buildup of the ore stockpile is ahead of plan and on target to exceed the 800,000-tonne start-up target.
  • Operational readiness -- operational readiness activities and hiring are progressing in line with plan. An update on Greenstone 2024 operating costs and production estimates will be reported in connection with the company's annual production and cost guidance in Q1 2024.

Greg Smith, president and chief executive officer of Equinox Gold, commented: "With the Greenstone project 96 per cent complete and the power plant fully operational, the priority is now on completion and commissioning of the process plant, commissioning of the TSF, and ramp up of mining and operations. The project continues to advance on budget and on schedule. We look forward to pouring gold in the first half of 2024 and then achieving commercial production."

Remaining project milestones

Remaining milestones to achieve production include:

  • Tailing storage facility complete and ready for use: December, 2023;
  • Process plant hot commissioning1: Q1 to Q2 2024;
  • Gold pour: H1 2024.

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.