02:44:27 EDT Thu 02 May 2024
Enter Symbol
or Name
USA
CA



Equinox Gold Corp (2)
Symbol EQX
Shares Issued 312,939,507
Close 2023-08-01 C$ 6.60
Market Cap C$ 2,065,400,746
Recent Sedar Documents

Equinox's Greenstone work continues on schedule, budget

2023-08-01 10:06 ET - News Release

Mr. Greg Smith reports

EQUINOX GOLD'S GREENSTONE PROJECT: ON SCHEDULE, ON BUDGET

Equinox Gold Corp. has provided an update on construction progress at its Greenstone project in Ontario, Canada. The Greenstone project is being developed as a 60/40 partnership by Equinox Gold and Orion Mine Finance Group, respectively, and will be one of the largest gold mines in Canada, with average annual gold production of more than 400,000 ounces over the first five years and more than five million ounces of gold over its initial 14-year mine life.

All dollar amounts are shown in United States dollars unless otherwise noted.

Greenstone project construction progress is documented weekly in a photo gallery on Equinox Gold's website.

Recent highlights (at July 21, 2023, unless otherwise noted):

  • Schedule -- the Greenstone project is 85 per cent complete. A third independent quantitative risk assessment completed in Q2 2023 concluded that the Greenstone project remains on schedule to pour gold in the first half of 2024.
  • Budget -- the Greenstone project remains on schedule for a total spend of $1.23-billion. At June 30, 2023, $937-million (76 per cent) of the budget had been spent (100 per cent basis), with approximately $170-million remaining for Equinox Gold's share to finance through to project completion.
  • Facilities completed -- with construction of the following facilities completed, the operations team has assumed responsibility for the permanent effluent water treatment plant, truck shop, warehouse, sewage treatment plant, potable water treatment plant, pit and plant site fuel stations, reagent storage, and site mixed emulsion (explosives) plant. The new Ministry of Transportation patrol yard was turned over to the ministry and dismantling of the old patrol yard is complete. The natural gas pipeline to site has been commissioned and is operational.
  • Construction progress -- all major equipment is now on site. Mechanical installations are 75 per cent complete, and electrical and piping installations are both 67 per cent complete. Power plant construction is complete and precommissioning commenced in Q2 2023. The Highway 11 relocation is substantially complete and ahead of schedule, with handover planned for Q3 2023. With all auxiliary facilities now handed over to operations, the remaining construction effort is focused on completion of the process plant and tailings storage facility.
  • Preproduction mining -- the first two Epiroc Pit Viper 235 drill rigs and the eighth CAT 793F haul truck were commissioned during the quarter. Mine preproduction activities have been operating 24/7 since Q4 2022, with more than 10.6 million tonnes of material moved to date. The current priority for mined material continues to be supplying waste rock for the tailings storage facility and other construction activities. Mining of ore for the commissioning stockpile is expected to commence in Q4 2023.
  • Commissioning and operational readiness -- the commissioning team and commissioning plans are in place, and operational readiness activities are under way.

Greg Smith, president and chief executive officer of Equinox Gold, commented: "The Greenstone project continues to advance on budget and on schedule. With most ancillary facilities complete and transferred to the operations team, and construction activities 83 per cent complete, our focus is shifting toward commissioning and operational readiness as we advance to construction completion and first gold pour in the first half of 2024, and then achieving commercial production."

Results of independent quantitative risk assessment

Valency Inc., a global provider of construction project assurance solutions and quantitative risk assessments, completed the Greenstone project's second quantitative risk assessment (QRA) during Q2 2023. The QRA concluded that the schedule and budget remain achievable, and the Greenstone project remains on schedule to pour gold in the first half of 2024.

An update on Greenstone 2024 operating costs and production estimates will be reported in connection with the company's annual production and cost guidance in Q1 2024.

Remaining project milestones

Important construction milestones include:

  • Process plant steel erection under way: June, 2022;
  • Administration building complete: July, 2022;
  • Delivery and assembly of preproduction fleet of four trucks and excavators: Q2 to Q3 2022;
  • Permanent water effluent treatment plant ready for use: Q3 2022;
  • Commence installation of gensets in power plant, power building enclosed: Q3 2022;
  • Start of preproduction mining: Q3 2022;
  • All main buildings enclosed: Q1 2023;
  • Leach tanks installed: Q4 2022;
  • Ball mills received and installed: Q1 to Q3 2023;
  • Highway 11 realignment complete: August, 2023;
  • Crushers installed: Q3 2023;
  • Commence precommissioning of crushing circuit: Q4 2023;
  • Power plant operational: Q4 2023;
  • Tailing storage facility complete and ready for use: Q4 2023;
  • Commissioning: Q1 to Q2 2024;
  • Gold pour: H1 2024

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.