Mr. Ian Harris reports
COLOMBIAN STATE VERIFIES COPPER GIANT'S DELIVERY ON PRIOR CONSULTATION COMMITMENTS AT MOCOA
The Colombian State has recorded Copper Giant Resources Corp.'s delivery on its prior consultation agreements with the Resguardo Inga de Condagua, the nearest indigenous community to the Mocoa copper-molybdenum project in Putumayo, Colombia. At the formal follow-up session convened by the Ministry of Interior on Nov. 22, 2026, the community, the company and the Ministry signed minutes recording seven of the nine agreements, which run through 2027, as fulfilled and accomplishment of every commitment due to date.
Prior consultation is the stage at which projects in Colombia most often stall. In 2025, Copper Giant, through its Colombian subsidiary, Libero Cobre Ltda., completed the first full indigenous prior consultation at exploration stage in Colombia (refer to news release dated Oct. 9, 2025). Fourteen months later, delivery is on the official record, shaped by decisions of the community's own assembly.
The company also announces that it has filed an independent technical report prepared by Apex Geoscience Ltd. in accordance with National Instrument 43-101 -- Standards of Disclosure for Mineral Projects in support of the updated mineral resource estimate (the updated MRE) effective Sept. 24, 2026, for its Mocoa copper-molybdenum project announced in Oct. 14, 2026.
Highlights
-
Recorded by the Colombian state: Minutes of the follow-up session convened by the Ministry of Interior's National Directorate of Prior Consultation (DANCP), held in the Condagua territory before the Procuraduria General de la Nacion and the Defensoria del Pueblo, were signed by the community, the company and the DANCP.
-
Delivered on schedule: Seven of the nine agreements, which run through 2027, are already fulfilled and every commitment due to date has been met. The remaining two are scheduled for 2027, one of them reallocated by decision of the community.
-
Led by the community: The community decided how part of the resources would be used, completing its planetarium and Cabildo offices, and is building its own football field.
"Fourteen months ago, we gave our word to the Resguardo Inga de Condagua Community. Today, the community itself confirmed that we have kept it. Every classroom, every chagra and every space we built together shows that development and ancestral identity can grow side by side. Prior consultation does not end with a signature; it lives through trust, and we will keep earning it, together," stated Thyana Alvarez, vice-president, corporate development, and country manager, Colombia.
Progress on the protocolized agreements
The September, 2025, protocolization established nine agreements for 2025 to 2027, organized around the Inga principles of air (Waira), soil (Alpa Mama), water (Yaku), biodiversity (Tukui Kausai) and community governance (Atun Taita Kunapa Nambi Iachai). Status as recorded in the official minutes of the Nov. 22, 2026, follow-up session.
Community governance shaped delivery throughout. At the community's request, the educational project was expanded to four new classrooms. Following technical recommendations, the planned second floor of the Casa Cabildo was replaced by improvements to the existing building, with the Cabildo offices being built at another site. By decision of its assembly, the community reassigned the resources of agreement 8 to complete the Casa Cabildo offices, the planetarium and the football field, a proposal the company supported. The community is building the football field itself. Construction of the planetarium and of the Cabildo offices is nearing completion.
A long-term relationship
Beyond the protocolized commitments, Copper Giant has responded to the community's requests for support focused on children and education, and has built a long-term relationship with the Resguardo Inga de Condagua Community through its social plans, which are designed to strengthen the community's own uses and customs rather than replace them:
-
Bilingual education: At the beginning of 2026, the Resguardo's school was approved as a bilingual institution, a milestone for the preservation of the Inga language and identity. The company's social plans support this through the new classrooms, preschool equipment, a computer room and STEM workshops with students.
-
A shared vision of the territory: The Planetarium and Research Centre (Iuiaridiru Wasi) reflects the community's vision of conservation grounded in both ancestral and scientific knowledge. It will serve as a space for education, observation and research on the territory's natural heritage, and for sustainable tourism.
-
Continuous engagement: The relationship is sustained through ongoing dialogue with the Cabildo authorities, joint work on chagras and medicinal plants, and training of company staff by the community's traditional knowledge holders.
Next steps
The follow-up stage of the consultation remains open until the two outstanding agreements are completed: the final two medicinal plant workshops (agreement 3) and the works funded through the reassignment of agreement 8, scheduled for the first half of 2027. The community will also deliver its final report on the chagras and the technical document on the moss research. Progress will continue to be reviewed in follow-up sessions convened by the DANCP.
About the consultation process
Prior consultation with the Resguardo Inga de Condagua Community was ordered by the DANCP in Resolution No. 1450 of Sept. 26, 2022, in connection with the exploration plan for concession contract FJT-141 (DANCP project proY-02365), now part of the unified Mocoa concession (refer to news release dated April 28, 2026). Following preconsultation in 2024 and formal consultation in 2025, the agreements were protocolized on Sept. 20, 2025 (refer to news release dated Oct. 9, 2025). The Nov. 22, 2026, session corresponds to the follow-up stage (seguimiento de acuerdos) of the process, under DANCP convocation, and with the participation of the Public Ministry and the authorities identified above.
The session was attended by the Gobernadora and members of the community, the company, the Putumayo Governor's Office, the Mocoa Mayor's Office, the Procuraduria General de la Nacion, the Defensoria del Pueblo, and the National Mining Agency (ANM). The session was convened by the DANCP and held in the Condagua territory. The Gobernadora presented the status of each agreement, supported by the community's own compliance report, and the parties carried out a verification tour and handover of the completed works. The DANCP recorded that the session was conducted as a space for intercultural dialogue in good faith, in accordance with ILO Convention 169, and the minutes were read, approved and signed by the parties.
Why it matters
-
Verified compliance: Under ILO Convention 169 and Colombian law, prior consultation agreements are binding. Follow-up under DANCP supervision, with the Procuraduria and Defensoria present, creates an independent, official record of the company's delivery.
-
A stronger foundation for Mocoa: Timely delivery to the nearest indigenous community strengthens the long-term social foundation of the project, alongside the company's agreement with the Montclar community.
-
A direct relationship: The relationship with the Resguardo Inga de Condagua Community is direct, without intermediaries and is managed by the company's own team in Putumayo.
In 2026, the company has advanced through three separate processes administered by the Colombian state: the unification of the Mocoa concession under a long-term development framework (refer to news release dated April 28, 2026), the competitive award of the Chaparral block by the National Mining Agency (refer to news release dated Oct. 26, 2026), and the DANCP-supervised verification of its prior consultation agreements at Mocoa. With agreements in place with both of the project's neighbouring communities, Condagua and Montclar, the social and regulatory groundwork for Mocoa is advancing through the same institutional channels that any future development would require.
National Instrument 43-101 technical report filed
Further to its news release dated Oct. 14, 2026, the company has filed the independent technical report prepared by Apex in accordance with NI 43-101 in support of the updated mineral resource estimate for the Mocoa project. The report, entitled "Technical Report and Updated Mineral Resource Estimate for the Mocoa Project, Putumayo Department, Colombia," is dated Nov. 27, 2026, has an effective date of Sept. 24, 2026, and is available under the company's profile on SEDAR+ and on the company's website.
The report was prepared by Warren Black, MSc, PGeo, and Alfonso Rodriguez, MSc, PGeo, of Apex and Frank Wright, PEng, of F. Wright Consulting Inc., each an independent qualified person within the meaning of NI 43-101. There are no material differences between the mineral resource estimate in the report and the estimate disclosed on Oct. 14, 2026: indicated mineral resources of 290 million tonnes at 0.54 per cent CuEq (copper equivalent) (0.33 per cent Cu and 0.038 per cent Mo (molybdenum)) containing 2.13 billion pounds of copper and 0.24 Blb of molybdenum and inferred mineral resources of 1.60 billion tonnes at 0.40 per cent CuEq (0.27 per cent Cu and 0.025 per cent Mo) containing 9.36 Blb of copper and 0.89 Blb of molybdenum.
Qualified person
Edwin Naranjo Sierra, vice-president of exploration for Copper Giant, is the designated qualified person within the meaning of NI 43-101, and has reviewed and approved the scientific and technical information in this news release. Mr. Naranjo holds an MSc in earth sciences and is a fellow of the Australasian Institute of Mining and Metallurgy (FAusIMM). Mr. Naranjo is not independent of the company.
About the Mocoa porphyry system
The Mocoa project is located in Colombia's Department of Putumayo, approximately 10 kilometres from the town of Mocoa in the country's south. Copper Giant controls more than 128,300 hectares of district-scale tenure through granted titles and applications, covering a significant portion of the Jurassic porphyry belt; an underexplored and highly prospective metallogenic corridor within the northern Andes.
Mocoa was first identified in 1973 through a regional geochemical survey conducted by the United Nations and the Colombian government. Follow-up programs between 1978 and 1983 included geological mapping, IP and magnetic geophysics, surface sampling, drilling, and metallurgical testing. Subsequent drilling by B2Gold in 2008 and 2012 refined the geological interpretation and confirmed the large scale of the system.
The deposit is hosted in Middle Jurassic dacite and quartz-diorite porphyries intruding andesitic to dacitic volcanics of the Central Cordillera in Colombia, a 30-kilometre-wide tectonic belt that extends into Ecuador and also contains major porphyry systems such as Mirador, Warintza, San Carlos and Panantza. Mocoa exhibits classic porphyry-style zonation with a potassic core surrounded by sericite and propylitic alteration. Mineralization consists principally of disseminated chalcopyrite and molybdenite, accompanied locally by bornite and chalcocite, and is associated with stockwork veining and hydrothermal breccias.
The deposit demonstrates more than 1,100 metres of vertical continuity, with multiple intrusive phases, brecciation episodes and vein generations reflecting a dynamic and long-lived magmatic-hydrothermal evolution, likely influenced by more than one porphyry centre. Mocoa remains open along several directions and several satellite targets across the broader land package support the interpretation of a district-scale mineralized system.
Mocoa's mineral resource estimate comprises indicated resources of 0.29 billion tonnes (Bt) at an average grade of 0.54 per cent CuEq (0.33 per cent Cu and 0.038 per cent Mo), containing 2.13 Blb of copper and 0.24 Blb of molybdenum; and inferred resources of 1.60 Bt at an average grade of 0.40 per cent CuEq (0.27 per cent Cu and 0.025 per cent Mo), containing 9.36 Blb of copper and 0.89 Blbs of molybdenum.
About Copper Giant
Resources Corp.
Copper Giant Resources is part of the Fiore Group, a private and well-established Canadian organization known for building successful, high-impact companies across the natural resource sector. Copper Giant was formed with a singular focus: to advance high-quality copper projects beyond resource definition; responsibly, efficiently and with long-term positive impact.
Copper Giant's current focus is the Mocoa copper-molybdenum deposit in southern Colombia, one of the largest undeveloped resources of its kind in the Americas. Recent exploration success has revealed potential well beyond its original footprint, highlighting Mocoa as a broader district-scale opportunity, and the catalyst for the company's name and evolution.
We seek Safe Harbor.
© 2026 Canjex Publishing Ltd. All rights reserved.