10:48:40 EDT Thu 02 May 2024
Enter Symbol
or Name
USA
CA



Cerrado Gold Inc
Symbol CERT
Shares Issued 98,255,238
Close 2023-11-29 C$ 0.70
Market Cap C$ 68,778,667
Recent Sedar Documents

Cerrado Gold loses $404,000 (U.S.) in Q3

2023-11-29 11:07 ET - News Release

Mr. Mark Brennan reports

CERRADO GOLD REPORTS Q3 OPERATING RESULTS

Cerrado Gold Inc. has released operational and financial results for the third quarter of 2023 at its Minera Don Nicolas (MDN) gold project in Santa Cruz province, Argentina, and has provided an update on its continuing activities at the Monte Do Carmo (MDC) gold project in Brazil. Production results at MDN were previously released on October 24, 2023. The Company's quarterly financial results are reported and available on SEDAR as well as on the Company's website (www.cerradogold.com).

  • Q3 Production of 10,082 Gold Equivalent Ounces("GEO")
  • Q3 results impacted by severe weather conditions
  • Operations back on track in October and November with shipments of approximately 5,600 and 5,470 GEO, respectively
  • Minera Don Nicolas ("MDN") Expansion Capital Expenditure program now largely complete

(All numbers reported in US dollars)

Q3 2023 Minera Don Nicolas ("MDN")Financial Highlights:

  • Gold production of 10,082 GEO in Q3/23, an 11 per cent decrease year-on-year ("yoy").
  • AISC of $1,703 per ounce duringQ3/23 due to difficult operating conditions seen in the quarter resulting in lower production rates.
  • Operating performance has returned to normal in October and November, with sales of approximately 5,600 and 5,470 GEO, respectively.
  • MDN capital program now largely complete, $34.3m invested in Expansion Capital year to date to develop heap leach facility (US$23.9m), pre-stripping of Calandrias Norte (US$5.0m) and exploration (US$5.4m).
    • Expansion program largely funded via short term notes in Argentina to be rolled over to longer maturity.
  • Production expected to ramp up into 2024, generating significant cash flows to rapidly reduce debt levels.
  • Significant opportunity to see a reduction in operating costs and increased cash flow in US dollar terms going forward should depreciation in applicable exchange rate continue post-election.

Mark Brennan, CEO and Chairman, stated: "While these results reflect very severe winter weather conditions resulting in lower production in Argentina, the team at MDN has rapidly enabled us to ramp up production while completing our capital projects and expansion plans from October. With our initial heap leach project operating and Calandrias Norte now in production, we now look to reap the benefits of these capital investment programs moving into 2024 through increased production and significant operating cash flow." He added "Post-election, we remain optimistic for a more accommodative fiscal regime providing for significant accretion to cash flow allowing us to restructure our debt and develop a healthy balance sheet at Cerrado."

MDN Outlook

Going forward into Q4/2023 and 2024, Cerrado's MDN operations are now positioned to benefit from the completion of its recent expansionary capital expenditure program to grow production with its new heap leach operations, while sustaining high-grade CIL production. The Company has invested approximately US$23.9m to complete the Heap Leach facilities at Las Calandrias in 2023 and US$5.0m to pre-strip Calandrias Norte to access high-grade ore for the CIL plant. Exploration spending has totaled US$5.4m and will continue into 2024 as we continue to grow the life of mine at MDN.

Results in October and November are already demonstrating more normalized operations as a result of these investments, with shipments for the two months totaling approximately 11,070 GEOs. With operations returning to normal, the Company anticipates a significant improvement in cash generation, which should be significantly enhanced with an improved fiscal policy and a more normalized FX regime in Argentina supporting lower operating costs in US dollar terms. While the near-term cash generating profile continues to improve, the company is also actively working to term out the maturity of its current short term debt profile and roll a significant amount of these obligations as is customary in Argentina.

Argentinian Currency Controls

Starting October 11 2023, by means of Joint Resolution No. 1/23 of the certain Ministries of the Argentinian Government, exporters of gold, silver and their concentrates were allowed to settle their exports at a preferential exchange rate resulting from settling 75 per cent of such exports through the Local Exchange Market and the remaining 25 per cent through blue chip transactions ("Mining Dollar"). The effect of the Mining Dollar allowed for an approximate 30 per cent depreciation of local costs in dollar terms at MDN during the month of October. While there is an attractive Mining Dollar in place currently, there is no certainty that such preferential rates will continue. The Company is optimistic that the election of Javier Milei as President of Argentina, will result in positive changes to the fiscal regime in Argentina and a reduction in or eventual removal of currency controls, which could result in a significant improvement in company cash flows in the short to medium term.

Third Quarter 2023 Operational and Financial Performance

Q3/23 and Full Year Operational Highlights Minera Don Nicolas

The Company produced 10,082 GEO ("Gold Equivalent Ounces") during the three months ended Sept. 30, 2023, as compared with 11,284 GEO in the three months ended Sept. 30, 2022. Production was 11 per cent lower in the three months ended Sept. 30, 2023, due to poor weather conditions; with flooding resulting in wet feed which then froze, impacting on throughput and lower than expected overall head grade values.

The average quarterly gold head grade of 3.19 g/t recorded in the third quarter of 2023 represents a 28 per cent decrease as compared with the average head grade of 4.40 g/t in the third quarter of 2022. Ore feed to the mill was impacted by poor operating conditions during the quarter, most notably extremely poor wet winter weather conditions followed by freezing temperatures, resulting in lower than planned mined ore production rates and lower than planned ore grades processed through the mill. Wet ore also reduced plant throughput. Gold recovery of 93 per cent represents a 2 per cent increase in recovery as compared with 91 per cent recorded in the third quarter of 2022. Silver recovery of 65 per cent was 2 per cent lower than the silver recovery achieved in the third quarter of 2022.

Stripping at Calandrias Norte commenced during the quarter with over 1.6MM tonnes of material moved. A further 2.7MM tonnes is to be stripped in October and November and fresh ore is set to feed the mill from December onwards. Results in Q4 are expected to show significant improvement and benefit from access and limited future stripping required for the Calandrias Norte material and the further ramp up of the heap leach operations. This new pit is planned to be the primary source of ore in 2024.

During Q3/2023, the team continued exploration efforts to advance several greenfield and brownfield targets with the aim of increasing mine life and expanding the overall resource endowment, while continuing to support the move to underground mining at Paloma.

Las Calandrias Heap Leach Project

At the new Calandrias heap leach project, work continued as the operation remained in the commissioning phase during the quarter. Initial ramp up was impacted by freezing conditions reducing initial irrigation rates which has now been addressed. Finalization of the crushing plant has now been completed, which should also see more consistent feed to the pad and improve overall performance going forward. Approximately 538 ozs were produced in the quarter. Production is set to achieve nameplate production rates from January thereafter.

Given weather production disruption in Q3/23 full production is now targeted for January 2024. The Calandrias Heap Leach is the first step in Cerrado's plans for growing production capacity at MDC. All Argentinian projects continue to be funded by operating cash flow and local debt facilities.

Monte Do Carmo Project, Brazil

During Q3/2023, the Company, together with its numerous advisors, completed the bankable feasibility study ("FS") announced on November 7, 2023 showing MDC to be an extremely high quality, low-cost robust economic project. A summary of the key highlights is presented below:

Highlights

  • After-Tax NPV of US$369 million and IRR of 32 per cent
  • Average annual gold production of 94,797 ounces per annum over 9 year Life of Mine ("LOM")
  • Average AISC of US$711 per ounce over LOM
  • Initial Capex of US$186.6 million (including US$15.8 million contingency)
    • 2:1 ratio of NPV over Initial Capex
  • Annual average free cash flow of $85 million over the LOM, with total cumulative after-tax free cash flow of $562 million over LOM
  • Initial Proven and Probable Reserves of 895 koz of Gold (16.8 Mt at 1.66 g/t Au)
  • Updated Measured and Indicated Resources of 1,012 koz of Gold (18.4 Mt at 1.72 g/t Au) and Inferred Resources of 66 koz of Gold (1.1 Mt at 1.95 g/t Au)

In addition, regional exploration continues on the greater project area aimed at growing the known resources and extending the potential mine life. During the quarter, the exploration focus has been on the Northern extension of the Serra Alta deposit, to the East of the south pit and to the north of Gogo, as well as on testing more greenfield targets such as Divisa and Bit-3 for ongoing development.

The Preliminary License ("LP") was issued from the Instituto Natureza do Tocantins("NATURATINS") on May 29, 2023 and the License of Installation/Construction ("LI")is expected to follow within 90 - 120 days of the LP issuance.

The Company also continues to pursue project funding from the UK Export Credit Agency("UKEF"), which is progressing well, and subject to successful due diligence and other review, is expected to be completed approximately during Q3 2024.

Q3/2023 Financial Highlights

The Company generated revenue of $21.6 million for the three months ended Sept. 30, 2023, from the sale of 11,374 GEO at an average realized price per gold ounce sold of $1,897 and price per silver ounce sold of$23.48. For the three months ended Sept. 30, 2022, the Company generated revenue of $17.8 million from the sale of 10,788 GEO. Revenue from sales of gold and silver for the current period was higher than the three months ended Sept. 30, 2022, due to the higher realized price in the current period.

Cash costs per ounce sold were $1,689 per ounce in the three months ended Sept. 30, 2023, as compared with cash costs per ounce sold of $1,461 per ounce in the three months Sept. 30, 2022, a 16 per cent increase. The 16 per cent increase is a result of higher consumables and material costs compared with the third quarter of 2022, due to lower tonnage milled and processed.

Cash provided by operating activities during the third quarter ended Sept. 30, 2023, was $10.3 million compared with cash used in operating activities of $0.6 million for the third quarter ended Sept. 30, 2022. Cash provided by operating activities before working capital changes in 2023 consisted of $2.3 million as compared with $0.7 million of cash used in operating activities before working capital changes in 2022.

Adjusted EBITDA was $0.1 million in the third quarter of 2023 as compared with $0.7 million in the third quarter of 2022. Current year adjusted EBITDA was lower due to higher expenses, offset by a lower tax expense in Q3/2023.

Net loss for the three months ended Sept. 30, 2023 was $0.4 million, as compared with a $6.6 million net loss for the three months ended Sept. 30, 2022, a difference of $6.2 million.The decrease in net loss is primarily a result of an increase in mine operating margin of $1.2 million, a decrease in finance expense of $0.5 million, a decrease in non-cash remeasurement loss on the secured notes and stream of $1.6 million, and an increase in general and administrative expenses of $0.4 million recorded in the third quarter of 2023 as compared with the third quarter of 2022.

Basic and diluted loss per share for the three months ended Sept. 30, 2023,was $0.00, compared with the basic and diluted loss per share of $0.08 for the three months ended Sept. 30, 2022, a $0.08 per share decrease as a result of higher mine operating margin and lower other expenses.

Review of Technical Information

The scientific and technical information in this press release has been reviewed and approved by Sergio Gelcich,P.Geo., Vice President, Exploration for Cerrado Gold Inc., who is a Qualified Person as defined in National Instrument 43-101

About Cerrado

Cerrado Gold is a Toronto-based gold production, development, and exploration company focused on gold projects in South America. The Company is the 100 per cent owner of both the producing Minera Don Nicolas and Las Calandrias mine in Santa Cruz province, Argentina, and the highly prospective Monte Do Carmo development project, located in Tocantins State, Brazil. In Canada, Cerrado Gold is developing it's 100 per cent owned Mont Sorcier Iron Ore and Vanadium project located outside of Chibougamou, Quebec.

In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas operation through continued operational optimization and is growing production through its operations at the Las Calandrias Heap Leach project. An extensive campaign of exploration is ongoing to further unlock potential resources in our highly prospective land package in the heart of the Deseado Masif.

In Brazil,Cerrado is rapidly advancing the Serra Alta deposit at its Monte Do Carmo Project, through feasibility and into production. Serra Alta is expected to be a high-margin and high-return project with significant exploration potential on an extensive and highly prospective 82,542 hectare land package.

In Canada,Cerrado holds a 100 per cent interesting the Mont Sorcier Iron Ore and Vanadium Project,which has the potential to produce a premium iron ore concentrate over a long mine life at low operating costs and low capital intensity. Furthermore, its high grade and high purity product facilitates the migration of steel producers from blast furnaces to electric arc furnaces contributing to the decarbonization of the industry and the achievement of SDG goals.

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.