CANADIAN COPPER PROVIDES MURRAY BROOK PROJECT UPDATE
Canadian Copper Inc. has provided several updates regarding its Murray Brook project including the continuing metallurgical program, permitting activities and the project financing status.
Metallurgical program update
The metallurgical testwork program was awarded to SGS Canada Inc. in Lakefield, Ont., on Nov. 11, 2025. This testwork is designed to further refine process plant operating costs and recovery performance as outlined in the 2025 preliminary economic assessment (PEA) next steps. Further, the objective of these flotation tests is to simulate the planned plant flowsheet as outlined in the PEA.
Approximately 3,100 kilograms from fresh diamond drill cores totalling about 244 metres of material was selected from the 1,000-metre drill program completed. It comprised 10 new drill holes targeting the initial phases of the mine design. Samples are in transit to SGS for assay preparation and testing. Examples of the massive sulphide intervals intersected include pyrite, chalcopyrite (copper) and sphalerite (zinc) sulphides.
To ensure desired grades were collected for SGS's eventual composites preparation, the company twinned historical holes drilled between 2012 to 2013. Based on the visual logging of the 2025 cores obtained from drilling, the geologic and resource model reconciled well.
Permitting update
The company first engaged the technical review committee (TRC), which comprises provincial and federal departments, in July, 2025, to discuss the combined strategy. The objective of this engagement is to share the project details early and understand TRC questions prior to environmental impact assessment (EIA) registration in H1 2026. The company is preparing answers to questions received from the TRC related to emissions sources and water management infrastructure now.
Baseline environmental data collection programs to support the EIA registration are complete for the 2025 field season. These programs included field work relating to archaeology, fish habitat, avian and other wildlife species, vegetation, and wetlands. Desktop studies related to surface water and groundwater, air quality and climate are currently under way. Technical data reports for these field programs and desktop studies are being completed now and will be incorporated into the EIA registration document, with expected delivery in H1 2026.
Funding strategy update
The company is advancing several project funding discussions. The objective is to secure capital for both the required predevelopment steps (design, permitting, early works, team formation) and the project construction capital. The company expects to select its path and partners in H1 2026. In parallel, the company will engage various government sources through Natural Resources Canada (NRCan) and their Critical Minerals Infrastructure Fund (CMIF), as well as new programs under way based on the 2025 federal budget.
About Canadian Copper Inc.
Canadian Copper is a Canadian-based mineral exploration company with a copper and base metals portfolio of historical resources and grassroots projects. The company is focused on the prolific Bathurst mining camp (BMC) of New Brunswick, Canada. There are currently 184,148,752 shares issued and outstanding in the company.