Borealis sets fiscal 2027 gold production guidance

2026-10-22 20:13 ET - News Release

Mr. Kelly Malcolm reports

BOREALIS PROVIDES FISCAL 2027 PRODUCTION AND OPERATING GUIDANCE

Borealis Mining Company Ltd. has released its production, operating and development guidance for the fiscal year ending July 31, 2027, covering the period from Aug. 1, 2026, through July 31, 2027.

Following the restart of open-pit mining operations at the Borealis mine in Nevada during fiscal 2026, the company is focused on increasing gold production, improving operating efficiencies and establishing a sustainable production profile while continuing to advance its wholly-owned Sandman project toward future development.

Fiscal 2027 guidance highlights:

  • Gold production: targeting 15,250 to 19,250 ounces of gold;
  • Mining operations: approximately six million tons of total material mined at an average waste-to-mineralized material strip ratio of approximately 2.4:1;
  • Mine sequencing: the majority of fiscal 2027 gold production is expected to be sourced from the Deep Ore Flats pit, supplemented by production from the East Ridge and Freedom Flats pits;
  • Crushing and stacking: approximately 717,960 tons of crushed mineralized material and 1,055,850 tons of run-of-mine (ROM) material to be stacked on the heap-leach pads;
  • Processing optimization: following metallurgical test work, Borealis is incorporating ROM heap leaching alongside its conventional crushing and stacking operations to relieve crusher bottlenecks, increase stacking volumes, and support additional gold production and revenue potential;
  • Capital projects: commence engineering and permitting for a new heap-leach pad targeting eight million to 12 million short tons of stacking capacity, with construction to begin following required approvals; planned adsorption-desorption-recovery (ADR) upgrades are intended to increase maximum processing throughput and improve operational efficiency;
  • Sandman development: continued advancement of engineering, metallurgical testing, mine planning and permitting activities to support a future construction decision.

Management commentary

Kelly Malcolm, president and chief executive officer of Borealis, commented: "Fiscal 2027 is focused on building consistent gold production at the Borealis mine. The Deep Ore Flats pit is expected to provide the majority of our annual production, supported by East Ridge and Freedom Flats, giving us flexibility in mine scheduling and material delivery.

"Following metallurgical test work, we are incorporating direct stacking of selected ROM material alongside our conventional crushing and stacking operations. This approach is designed to relieve crusher bottlenecks and increase the volume of material under leach, with the potential to generate additional gold production and revenue. We will closely monitor recovery performance as we refine material selection and operating practices.

"Our priorities are safe and reliable operations, disciplined execution and effective use of our existing infrastructure. Alongside these operating priorities, we continue to advance the technical and permitting work at the Sandman project to support a future development decision. We believe these initiatives position Borealis to deliver meaningful production growth and build a stronger Nevada-focused gold mining company."

Fiscal 2027 production and operating guidance

The following table summarizes the company's operating guidance for the 12 months ending July 31, 2027.

Guidance reflects management's current operating plans and assumptions and is subject to changes in operating conditions, equipment availability, contractor performance and metallurgical recoveries. The gold production range reflects uncertainty in the timing and extent of heap-leach recovery, including variations in material grade, metallurgical characteristics, heap permeability, solution pH and leach kinetics.

Borealis mine -- production growth and operations optimization

The Borealis mine, located near Hawthorne, Nev., is a fully permitted open-pit, heap-leach gold operation with established infrastructure, active heap-leach pads and an operating ADR facility.

Following the restart of open-pit mining operations during early 2026, the company has progressively increased mining, crushing and stacking activities while building mineralized inventory under leach.

Fiscal 2027 mining operations will be primarily focused on the Deep Ore Flats pit, which is expected to account for the majority of the company's annual gold production. Mining activities at Deep Ore Flats will be supplemented by planned production from the East Ridge and Freedom Flats pits, providing additional mineralized material and operational flexibility throughout the fiscal year.

The company's mine plan anticipates total material movement of approximately 6.0 million tons, including approximately 1,773,800 tons of mineralized material, at an average waste-to-mineralized material strip ratio of 2.4:1. Individual pit strip ratios are expected to vary. Sequencing of mining activities across the three pits is designed to optimize mineralized material delivery, maintain consistent stacking operations and support the company's annual gold production objectives.

Introduction of run-of-mine heap leaching

Following metallurgical test work, including size-fraction analyses and column leach testing, Borealis is incorporating direct stacking of selected ROM material into its fiscal 2027 operating plan alongside conventional crushing and stacking.

Suitable ROM material bypasses the crushing circuit and is placed directly onto the heap-leach pads. This approach is designed to relieve crusher bottlenecks and increase total stacking volumes without requiring a corresponding increase in crusher throughput.

Management believes the use of both crushed and ROM material will provide flexibility in mine scheduling, material handling and processing. Material routing will consider grade, metallurgical characteristics, anticipated recoveries and leaching times. By placing additional suitable material under leach, the company aims to increase recoverable gold ounces and revenue potential.

During fiscal 2027, Borealis expects to stack 717,960 short tons of crushed mineralized material and 1,055,850 short tons of ROM material, for total planned heap-leach placement of 1,773,800 short tons.

Management anticipates that ROM stacking will avoid the crushing step for selected material, but its overall benefit will depend on actual recoveries, leaching times and material-handling requirements. ROM material may exhibit lower ultimate recoveries and slower leach kinetics than crushed material, and metallurgical test work may not fully represent performance at operating scale.

The company will monitor gold recovery, leach kinetics and solution management across both material streams and adjust material selection and stacking practices as operating results become available.

Capital projects -- heap-leach capacity and ADR upgrades

During fiscal 2027, Borealis plans to commence engineering and permitting for a new heap-leach pad and begin construction following receipt of the required approvals. The proposed pad is targeting a total stacking capacity of eight million to 12 million short tons, subject to final engineering and permitting. This additional capacity is intended to support future mining activities and provide flexibility for continued placement of crushed and ROM mineralized material.

The company also plans upgrades to its existing ADR facility, including increased stripping-vessel capacity, electrowinning (EW) cell capacity and furnace capacity. These upgrades are intended to increase the facility's maximum processing throughput and improve operational efficiency across the stripping, electrowinning and smelting stages.

Together, these projects are designed to align heap-leach and gold-recovery infrastructure with the company's longer-term operating plans. Final project scope and implementation schedules will depend on engineering results, applicable approvals and equipment delivery timelines.

Sandman gold project -- advancing toward development

Borealis continues to advance its wholly owned Sandman project in Humboldt county, Nevada, as the company's principal development-stage asset.

The updated preliminary economic assessment (PEA) announced Feb. 19, 2026, outlined a conventional open-pit, heap-leach operation with average annual gold production of approximately 38,000 ounces over a nine-year mine life from the Sandman project. These estimates relate to the PEA and do not form part of fiscal 2027 production guidance. The PEA is preliminary and incorporates inferred mineral resources whose geological uncertainty prevents their classification as mineral reserves on the basis of the assessment. There is no assurance that the projected results will be achieved. Mineral resources that have not been converted to mineral reserves have not demonstrated economic viability.

During fiscal 2027, the company plans to advance the project through the following work programs:

  • Metallurgical testing: completion and interpretation of metallurgical testing to further define gold recoveries, reagent consumption and processing parameters;
  • Engineering and mine planning: advancement of pit designs, mine sequencing, infrastructure requirements and process engineering;
  • Permitting: continued environmental baseline studies, regulatory engagement, and advancement of applicable state and federal permitting requirements;
  • Development planning: further evaluation of capital requirements, construction sequencing and opportunities to integrate the Sandman project with existing Borealis infrastructure;
  • Exploration: evaluation of opportunities for resource expansion and additional mineralization within the Sandman project and the surrounding district.

The company expects to complete these studies and be in a position to submit a mining permit application within fiscal 2027, subject to technical results and regulatory requirements.

Exploration, resource growth and permitting

In addition to its production and development activities, Borealis intends to continue evaluating exploration opportunities across its Nevada property portfolio.

At the Borealis mine, exploration activities will focus on identifying additional mineralized material that could potentially extend mine life and support future production growth. The company is also working to permit an exploration program on the eastern portion of the Borealis project to test both historical mineralization and newly identified epithermal targets.

At the Sandman project, exploration will focus on opportunities to expand known mineralized zones and evaluate additional targets across the broader project area. The majority of the Sandman project is covered by an exploration plan of operations permit.

The company also plans an inaugural drilling program at the Big Balds project in Nevada, where drilling authorization was recently obtained through the notice of intent program.

Operating outlook

Borealis's fiscal 2027 operating priorities are to maintain reliable mining and material delivery, co-ordinate crushed and ROM stacking, and improve the conversion of mineralized inventory under leach into gold production.

Gold production is not expected to occur evenly throughout the fiscal year. The timing of production will depend on pit sequencing, material grades, stacking rates, leach kinetics and recovery performance. Gold recovered during fiscal 2027 may include material stacked in earlier periods, while some gold contained in material stacked during fiscal 2027 may be recovered in subsequent periods.

Guidance reflects the company's current operating plan and assumptions concerning mining rates, equipment availability, material characteristics, processing performance and permit conditions. Borealis will assess performance against these assumptions throughout the year.

Cautionary statement regarding mineral resources, mineral reserves and production

The Borealis mine does not have current mineral resources or mineral reserves established in accordance with National Instrument 43-101, Standards of Disclosure for Mineral Projects. Historical estimates are not being treated by the company as current mineral resources or mineral reserves and should not be relied upon as such.

The company's decision to undertake and expand mining operations at the Borealis mine, including the fiscal 2027 operating plan and guidance presented in this release, relies on internal modelling and management's understanding of the property. These activities are proceeding without a preliminary economic assessment, prefeasibility study or feasibility study supporting the production decision and establishing its economic and technical viability.

Consequently, the operating plan and production guidance carry greater uncertainty and a higher risk of technical or economic failure. Actual mineralized tonnages, grades, strip ratios, recoveries and production rates could differ materially from expectations. Mining and processing could also prove more difficult or costly than anticipated. There is no assurance that fiscal 2027 guidance will be achieved or that operations will be economically viable.

Qualified person

Technical information contained in this press release has been reviewed and approved by Kelly Malcolm, PGeo, a non-independent qualified person as defined under NI 43-101.

Borealis mine

The Borealis mine, located near Hawthorne, Nev., holds permits for current mining and processing operations and includes existing open pits, heap-leach pads and an operating ADR facility that produces dore bars. The project has historically produced over 600,000 ounces of gold from an open-pit heap-leach operation. It is an underexplored property and has not been drilled since 2011, aside from Borealis's efforts in 2024 and 2025. The property possesses high-grade expansion potential with robust historical drilling results, along with a number of untested regional targets. Please see the Borealis mine technical report entitled "NI 43-101 Technical Report, Project Status Report, Borealis Mine, Nevada, U.S.A.," written by Douglas Reid, PEng, of SRK Consulting, dated Feb. 16, 2024. The report can be found on SEDAR+ or the Borealis website.

The Borealis project holds existing federal and state permits for mining and processing operations. However, certain permit modifications may be required for expanded production, and the timeline for such approvals is subject to regulatory review. The company cannot guarantee the timing or success of any permit modifications that may be required for future expansions.

About Borealis Mining Company Ltd.

Borealis is a Nevada-focused gold mining and exploration company operating the Borealis mine and advancing the Sandman gold project. Located near Hawthorne, Nev., the Borealis mine includes open-pit mining infrastructure, heap-leach pads and an adsorption, desorption and recovery (ADR) facility for gold recovery and dore production. The company's strategy combines production from its existing operations with exploration and development opportunities across its Nevada portfolio.