Mr. Cliff Grandison reports
ALASKA HYDRO ANNOUNCES CALL FOR POWER & INTEREST FOR CAPACITY
Alaska Hydro Corp. has submitted its interest in BC Hydro's Call for
Power 2025 and the request for expressions of interest (RFEOI) in supplying baseload power
capacity. BC Hydro's Call for Power 2025 is a request for power (RFP) due on or before Jan. 5,
2026. A mandatory interconnection request submission (CEAP) is due on or before Sept. 1,
2025, with a deadline for CEAP amendments of Oct. 2, 2025. The company has not yet
undertaken the CEAP. Optional registration is due on or before Sept. 12, 2025, and the company
has filed the required registration form. The RFP requires a minimum first nation equity
participation of 25 per cent. At this time, the company does not have any undertaking with the first nation
regarding equity participation, and the company is not assured that the first nation will participate.
BC Hydro's RFEOI is to due for submission on or before Sept. 8, 2025. The company has already
made a submission, which may be amended should comments from BC Hydro arise.
The company's project is a proposed 75-megawatt hydroelectric plant and includes a dam and storage
reservoir. The proposed facility would be located on More Creek in northwestern British Columbia.