13:44:03 EDT Fri 26 Apr 2024
Enter Symbol
or Name
USA
CA



TMAC Resources Inc
Symbol TMR
Shares Issued 83,592,066
Close 2017-02-23 C$ 17.46
Market Cap C$ 1,459,517,472
Recent Sedar Documents

TMAC talks Hope Bay production in 2016 results NR

2017-02-23 20:59 ET - News Release

Dr. Catharine Farrow reports

TMAC NEARING COMMERCIAL PRODUCTION AT HOPE BAY

TMAC Resources Inc. has filed its year-end financial statements, management's discussion and analysis, and annual information form for the year ended Dec. 31, 2016, which documents can be found on the company's website or on SEDAR. The highlights provided herein are derived from these documents and should be read in conjunction with them.

Dr. Catharine Farrow, chief executive officer of TMAC, stated: "We are thrilled with our progress in bringing the Doris mine and mill complex into production. At year-end, our high-grade ore stockpile totalled 121,600 tonnes grading 14.5 grams per tonne gold and containing 56,500 ounces of gold. On the processing side, we poured our first gold Feb. 9 and recently completed plant commissioning. The ore stockpile will be used to augment our mill throughput to 1,000 tonnes per day during 2017 as we ramp up mining to 1,000 tpd and our planned expansion to 2,000 tonnes per day starting in early 2018. All of this has been achieved essentially on time and on budget."

She added: "We are now focused on process optimization, on-site operator training and ramp-up to steady-state production in order to attain commercial production this quarter. TMAC's schedule and budgetary successes on its path to production are the result of the tremendous work and dedication by our employees, Gekko, other contractors and consultants. We would also like to acknowledge the great support of the communities of the Kitikmeot region and our Inuit landowners. We look forward to continuing to deliver on our vision to build the Hope Bay belt into a multigenerational mining camp."

The Hope Bay project's path to production overview

The path to production plan covered the 24-month period commencing Jan. 1, 2015, and ended Dec. 31, 2016, and included the completion of construction, assembly and initial commissioning of the processing plant. The project is essentially on target with respect to the original timing as TMAC envisions achieving commercial production of gold during the first quarter of 2017. The path to production plan did not include the finalization of commissioning and ramp-up that are included in the capital expenditures detailed in the 2017 outlook.

With the $9-million of funds raised from the flow-through common share financing in March, 2016, the total estimated cash outflows, including working capital, for the combined 2015 and 2016 years, increased from $325-million to $334-million. As at Dec. 31, 2016, TMAC had incurred $350-million of expenditures, including $8-million of additional environmental bonding required under the Doris water licence, and had completed over 98 per cent of the scope of work with approximately $2-million left to be incurred. The cash outflows to complete the path to production plan are, therefore, expected to be approximately 3 per cent higher than the $308-million budget mainly due to additional expenditures incurred to complete all of the foundation work on the mill building, additional installation costs of processing plant at site and additional costs for vessels for the 2016 sealift, partially offset by cost reductions in other areas, including mining. In addition, the letters of credit supporting environmental rehabilitation bonding are $34-million instead of $26-million. The increase in environmental bonding results from a number of factors essentially not within TMAC's control.

The ore stockpile on surface at Dec. 31, 2016, totalled 121,600 tonnes with 56,500 ounces of contained gold (at 14.5 grams per tonne), compared with TMAC's path to production plan that included having a gold ore stockpile of 110,700 tonnes containing 55,600 ounces of gold (at 15.2 grams per tonne). The stockpile is to provide the processing plant with significant feed at start-up and ensure a smooth production ramp-up to 1,000 tonnes per day in 2017 and, following the delivery and installation of a second Gekko Systems Pty. Ltd. fabricated Python (crushing, grinding and flotation concentrate producing circuit) to site in the 2017 sealift, to 2,000 tpd by the end of 2017.

At Dec. 31, 2016, TMAC had $63-million of cash and cash equivalents excluding restricted cash of $45-million that is composed of a $10-million minimum cash balance in a segregated account in accordance with the debt facility requirements and $35-million invested in guaranteed investment certificates set aside as collateral for the letters of credit that support environmental rehabilitation bonding and provide security for compliance under various agreements with Inuit organizations. The proceeds from a bought deal financing of $60-million are being used for the exploration and development below the diabase dike at Doris North; however, the timing for these expenditures could provide a working capital cushion during ramp-up if needed.

2017 outlook

TMAC completed its first gold pour from its Doris mine on Feb. 9, 2017. TMAC's focus for 2017 remains the orderly, but relatively quick, ramp-up of gold production by the processing plant, the ramp-up of underground production at Doris from the approximately 1,000 tpd to 2,000 tpd that will be required to feed the current 1,000-tonne-per-day capacity Python and a second 1,000-tonne-per-day capacity Python planned for delivery in the 2017 sealift. The key production statistics and expected expenditures in 2017 are provided in the summary of key production statistics section.

Summary of key production statistics and expected expenditures for 2017:

Ore mined:  275,000 tonnes

Average grade mined:  13 grams per tonne

Ore milled:  325,000 tonnes

Gold sold:  130,000 to 140,000 ounces

Cash cost per ounce sold (2):  less than $600 (U.S.)

All-in sustaining cost per ounce sold (2):  less than $750 (U.S.)

Capital expenditures:

Sustaining:  $15-million

Preproduction and expansion:  $35-million

Exploration and evaluation:  $22-million

(1) Canadian-dollar/U.S.-dollar exchange of 1.30.

(2) A non-international financial reporting standard measure.

(3) The prefeasibility study anticipated 136,000 ounces of gold recovered and sold.

The preproduction and expansion capital for 2017 includes the costs associated with completing the commissioning of the processing plant to commercial production, completing and installing the second Python, including its related equipment and infrastructure, the construction of additional site bed space for 80 people, and the development of the Doris North BTD zone that is dependent on further exploration success but is anticipated to be a future source of ore to feed the expanding capacity of the processing plant. Preproduction and expansion capital in 2017 is forecast to be $35-million and includes a one-time charge of $8-million, payable to Nunavut Tunngavik Inc. in eight equal quarterly instalments, for achieving first gold production at Hope Bay.

Sustaining capital expenditures are estimated to be $15-million and include costs for construction activities in the tailings impoundment area, water discharge, surface equipment, an equipment wash bay, final installation and commissioning of the last two generators at the power plant, and other miscellaneous items.

2017 objectives

Hope Bay project:

  • Achieve commercial production of gold during the first quarter of 2017 and ramp-up to full production;
  • Deliver, in 2017, sealift and install and commission the second Python in the processing plant;
  • Safely deliver consumables, materials, supplies and additional mobile equipment in the 2017 sealift;
  • Explore and develop the Doris North BTD zone for production by early 2018;
  • Construct additional bed space for 80 people at site;
  • Commission the last two generators at the power plant;
  • Conduct 6,500 metres of surface drilling at Madrid North (Naartok);
  • Reopen the Boston camp and conduct 7,500 metres of exploration drilling;
  • Support the technical review of the Madrid-Boston draft environmental impact statement and progress to submission of the final environmental impact statement and Type A water licence application;
  • Obtain the Madrid Type B water licence to allow TMAC to move forward with development of surface infrastructure, underground advanced exploration and bulk sampling.

Financial and corporate:

  • Commence monthly repayments of the debt facility on July 31, 2017.

Financial and operating results

Statement of profit or loss

Net loss and comprehensive loss for the three months ended Dec. 31, 2016, were $7.2-million, compared with a net loss and comprehensive loss of $3.2-million for the three months ended Dec. 31, 2015.

Conference attendance

TMAC will be attending the BMO Capital Markets 2017 Global Metals and Mining Conference in Hollywood, Fla., United States of America, from Feb. 26, 2016, to March 1, 2017. The company will be at booth No. 2500 at the PDAC 2017 International Convention, Trade Show and Investors Exchange from March 5 to 8, 2017, Toronto, Ont., Canada.

About TMAC Resources Inc.

TMAC holds a 100-per-cent interest in the Hope Bay project located in Nunavut, Canada. TMAC is a fully financed, emerging gold producer, with the Doris mine expected to achieve commercial production in the first quarter of 2017. The company has a board of directors with depth of experience and market credibility and an exploration and development team with an extensive record of developing high-grade, profitable underground mines.

Scientific and technical information

Scientific and technical information related to Doris mine development was prepared by, and all other scientific and technical information contained in this document was reviewed and approved by, David King, PGeo, the vice-president, exploration and geoscience, of TMAC, and Paul Christman, PEng, the manager of mining of TMAC, each of whom is a qualified person as defined by National Instrument 43-101 (standards of disclosure for mineral projects).

                                                                                   
                               STATEMENT OF PROFIT OR LOSS           
                           (expressed in millions of dollars)   
                                                                                                        
                                                   Year ended Dec. 31, 2016   Year ended Dec. 31, 2015
General and administrative                                                                            
Salaries and wages                                                     $6.8                       $3.2
Share-based payments                                                    2.8                        2.5
Professional and consulting fees                                        0.5                        1.1
Travel                                                                  0.3                        0.2
Investor relations                                                      0.5                        0.1
Office, regulatory and general                                          1.1                        0.8
                                                                       ----                       ----
                                                                       12.0                        7.9
Writedown of obsolete inventory                                         2.3                          -
Impairment of equipment and assets held for sale                        2.0                        1.4
Loss on sale of equipment                                                 -                        1.3
                                                                       ----                       ----
Loss before the following                                              16.3                       10.6
Finance income                                                         (0.8)                      (0.6)
Finance expense                                                         0.7                        2.0
Business development expenses                                             -                        0.9
Foreign exchange loss (gain)                                            1.2                       (0.9)
Fair value loss (gain)                                                  0.2                       (0.4)
Other                                                                  (0.3)                       0.5
                                                                       ----                       ----
Loss before income taxes for the year                                  17.3                       12.1
Deferred income tax expense (recovery)                                 (4.1)                      (2.5)
                                                                       ----                       ----
Net loss and comprehensive loss for the year                           13.2                        9.6  
                                                                       ====                       ====
Net loss per share,                                                                                    
basic and diluted                                                     $0.16                      $0.15

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.