Nevada Copper creates Pumpkin Hollow development plan

2017-11-20 08:18 ET - News Release

Mr. Robert McKnight reports

NEVADA COPPER ANNOUNCES DEVELOPMENT PLAN FOR OPTIMIZED UNDERGROUND MINE AND APPOINTS CHIEF OPERATING OFFICER

Nevada Copper Corp. has created a development plan to swiftly advance the Pumpkin Hollow underground mine project at its 100-per-cent-owned Pumpkin Hollow copper property to construction phase, with the objective of making a construction decision by mid-2018 and realizing first copper production in 2019.

Highlights:

  • Completion of optimized underground project study: release of the results of a prefeasibility study on the underground project (the PFS), with a new focus on reduced capital costs, and a mine plan oriented toward the extraction of higher-grade, higher-margin ore;
  • Chief operating officer appointment: the appointment of Phillip Day as chief operating officer, as Nevada Copper moves forward with a construction restart of the underground project;
  • Financial support: financial support from Pala Investments, Nevada Copper's largest shareholder, to deliver a project financing package for the construction of the underground project, together with existing and new investors;
  • Development plan: development milestones and timeline for the underground project;
  • Open-pit project optimization: significant opportunities identified for open-pit optimization.

Highlights of the underground project prefeasibility study

The Pumpkin Hollow property encompasses the only fully permitted copper project of scale in the United States, comprising two potential copper mines:

  1. The high-grade underground project;
  2. A large-scale open-pit and underground project with reserves of five billion pounds of copper, 760,000 ounces of gold and 27,600 oz of silver (1).

The two projects benefit from over $220-million of prior expenditures which financed a significant amount of engineering work and technical studies, and allowed for the construction of a production-sized head frame and hoist, warehouse, a 1,900-foot-deep, 24-foot-diameter concrete-lined production size shaft and over 600 feet of lateral development.

The PFS for the underground project leverages the substantial existing infrastructure at the site, including power, water, road access, plus a production shaft and lateral mine development. The objective of the PFS has been to optimize the previously defined underground portion of the mineral resources at Pumpkin Hollow with a focus on:

  • Reduced capital cost;
  • Higher mined ore grades;
  • Reduced operating cost profile;
  • Derisked construction plan, including brownfield assets, EPC construction approach and contract mining during ramp-up;
  • A philosophy on focusing on margin over tons, while maintaining expansion and extension optionality.

Sedgman Engineering and Mining Plus have taken advantage of the existing infrastructure to improve capital cost accuracy and reduce development risk, and worked with Nevada Copper's project team, supported by Pala Investments as technical adviser, on preparation of the PFS.

A detailed overview of the PFS is provided below, and the project highlights include the following.

  • Robust project economics (2):
    • Average annual copper production of 50 million pounds (60 million lb in years one to five);
    • First five-year copper grades averaging 1.81 per cent (2.01 per cent Cu equivalent (3));
    • First five-year C1 cash costs of $1.69/lb of payable copper;
    • Average annual operating margins of $67-million per annum ($86-million in years one to five);
    • Pretax net present value 5 per cent of $356-million and internal rate of return of 27.2 per cent (4);
    • After-tax NPV 5 per cent of $301-million and IRR of 25.2 per cent;
  • Low initial capital requirements: $182-million;
  • Short lead time to first production:
    • Fully permitted for construction and operation;
    • Planned commencement of construction by mid-2018 (subject to board approval and financing);
    • Target first production in mid-2019;
  • Development plan focused on minimizing execution risk:
    • Utilizes the existing 1,900-foot-deep, 24-foot-diameter concrete-lined, production-sized shaft, associated head frame and hoist, and existing surface infrastructure;
    • Process plant construction under fixed price engineering, procurement and construction (EPC) contract for which engineering designs are well advanced;
    • Experienced mining contractor to be utilized for underground development and mine ramp-up, for which initial contractor tenders have been completed;
  • Full optionality retained over large-scale fully permitted open pit:
    • Underground does not impact Nevada Copper's ability to develop a future project on the adjacent deposits accessible by open pit methods;
    • Significant optimization opportunities identified for open pit project, including potential to:
      • Convert assumed waste material to potential mineral resources, and eventually ore, through drilling in Northern Extension and Connector zones and additional engineering studies;
      • Reduce project costs through updated project estimation;
      • Reduce capital costs by optimizing project scale.

Note that a future stand-alone open-pit project development option is not part of the technical report (5). Both the underground and open-pit projects are located within privately held land inclusive of surface and mineral rights.

A technical report prepared in accordance with National Instrument 43-101 will be filed on SEDAR within the 45 days from the date of this announcement and will be made available on Nevada Copper's website.

Appointment of chief operating officer

Nevada Copper is pleased to announce the immediate appointment of Phillip Day as vice-president, chief operating officer.

Mr. Day has significant project delivery and operating experience, and brings key project management skills required to advance the underground project into construction phase. Mr. Day's project construction experience includes senior roles with AMEC Americas, where he managed a number of major projects, including the brownfields expansion of Corrego do Sito gold project and the $1-billion Gramalote gold study for AngloGold Ashanti. Previously he worked in managerial, operational and technical roles for BHP Billiton and WMC Resources as well as commissioning and operation of the Minara Resources Murrin Murrin nickel laterite project. Mr. Day is presently head of technical and operations at Pala Investments.

Commenting on the appointment and the release of the PFS, Mr. Day stated: "I am excited to join Nevada Copper. I see significant opportunities at Pumpkin Hollow, as we now have a robust underground project ready to advance into construction in the near term. The ability to leverage the existing infrastructure and previous studies will allow us to significantly derisk project development. Importantly, for the flagship Pumpkin Hollow open pit, I also see substantial scope for optimization and value creation that can be advanced in parallel with the near-term production from the underground mine. In particular, drilling of the Northern Extension and Connector zones, combined with ongoing technical studies, has the potential to add open-pit tons and grade, which has the potential to enhance project economics by converting material currently classified as waste into ore."

Financial support from Pala Investments

To support Nevada Copper in swiftly advancing the underground project to the construction phase, Pala Investments has advised that it will provide financial support to Nevada Copper, including the potential backstop of future equity financings, in connection with delivering a project financing package for the construction of the underground project. In this regard, Pala Investments is currently working closely with Nevada Copper and its senior lender, Red Kite Mine Finance, and existing and new investors, on delivering a project financing package for the construction of the underground project. Nevada Copper will provide an update as soon as more details are available.

Underground project development plan

In light of the positive results of the PFS and the financial support of Pala Investments, Nevada Copper is pursuing a development plan to efficiently transition into a mid-tier copper producer. Key milestones include:

  • Release of results of PFS of the optimized underground project -- complete;
  • Execution of EPC contract with Sedgman Engineering and contract mining agreement -- first quarter 2018;
  • Construction decision -- second quarter 2018;
  • First production -- Q2 2019.

A construction decision on the underground project will be determined by the board of directors of Nevada Copper subject to completion of remaining project engineering, financing and market conditions at the relevant time.

Open-pit optimization opportunities

In addition to its plan to transition to a copper producer in the near term, Nevada Copper has also identified multiple opportunities to optimize a future open-pit mining option, including the following.

Drilling of extension zones:  A drilling program is being developed to test the Northern and Connector zones of the open-pit deposits. Positive results, combined with continuing technical studies, would have the potential of converting material classified as waste to ore; the resultant increase in tons and reduction in waste stripping requirements would improve project economics.

Updated project estimation:  Updated project cost estimation in light of current market conditions has the potential to reduce overall project costs.

Optimized project scaling:  Depending on the results of extensional drilling and a review of project cost estimation, opportunities may exist to pursue a smaller start-up option with reduced capital requirements.

Nevada Copper intends to progress these optimization opportunities during 2018 in parallel with its objective to advance construction of the underground project.

Giulio Bonifacio, president and chief executive officer of the company, commented: "The announcement of the PFS results against the backdrop of improving copper prices, sets the stage for the next steps towards financing and a construction decision at Pumpkin Hollow.

"Pala has continued to provide both financial and technical support to Nevada Copper. Their technical input has been invaluable in the optimization of the underground project, and the ongoing optimization of the open pit, with a focus on profitability and constructability.

"We welcome Mr. Day to our senior management team as we further advance Pumpkin Hollow towards construction. Pumpkin Hollow is a truly unique, robust base metal asset that is fully permitted in a top tier location while also possessing significant built-in growth potential and upside both by way of the underground deposits and the large open-pit deposits. Our stated objective is to be the next significant new copper producer in the Americas by way of a staged development of the underground mine followed by the open pit operation at Pumpkin Hollow."

Further details of the technical report

Background

The technical report discloses the proposed development of the underground project at a preliminary feasibility level. This is the primary focus of the technical report and is presented as "Case A" in the technical report. For further clarity, the underground project will also be referred to interchangeably as Case A in the descriptions below.

The technical report also includes feasibility-level information on the potential development of a large 70,000-ton-per-day mine at Pumpkin Hollow with feed mainly from the nearby open-pit deposits, but also from the same underground mineral resources as accessed in the underground project. This is referred to within the technical report as the "integrated project" or "Case B." The integrated project was originally the subject of an NI 43-101 2015 feasibility study technical report (6) for which the scientific and technical information is materially unchanged and remains a viable development option.

The technical report that will be filed will therefore contain a summary of both:

  • A prefeasibility study on the underground project;
  • A feasibility study on the integrated project, an integrated underground and open pit project for Case B, based on the 2015 IFS.

Note: Unless specifically stated, all descriptions and results below refer to the underground project: a 5,000-ton-per-day underground mine development scenario as described in the technical report. A summary and results of the integrated project are disclosed at the end of this document.

Mineral resources

The mineral resource estimate for Pumpkin Hollow is unchanged from that disclosed in the 2015 IFS and includes the eastern deposits amenable to underground mining methods and the western deposits amenable to open-pit mining methods as disclosed in the tables. Both the underground project and the integrated project are based on mineral reserves converted from the same mineral resource estimate for Pumpkin Hollow. Development of the underground project and the integrated project are mutually exclusive development alternatives as presented in the technical report.

The open-pit cut-off grade has been approximated at 0.15 per cent Cu prior to completion of cost optimization and has been applied for purposes of the resource statement only. To further approximate the reasonable prospects of economic extraction, a cut-off grade of 0.15 per cent Cu has been applied to measured, indicated and inferred resources constrained within a Geovia Whittle pit optimization assuming a copper price of $3.75/lb and the parameters used for the reserve pit optimization. Value has only been attributed to copper for the pit optimization constraint. Iron is reported as a byproduct to the Cu-Au-Ag resource blocks.

The underground cut-off grade has been approximated at 0.75 per cent Cu prior to completion of cost optimization and has been applied for purposes of the mineral resource statement only. To further approximate the reasonable prospects of economic extraction, reporting of resources has been constrained to within the mineralized domains, with the exception of waste amongst the mineral zone interpretation that was confined with a waste solid for purposes of internal waste inclusion for the mine plan. Metals prices of $3/lb, $1,250/oz and $18/oz for copper gold and silver respectively were used for resource estimation.

                             MINERAL RESOURCES EASTERN UNDERGROUND DEPOSITS

                            Tons  Copper    Gold   Silver  Contained copper    Contained gold   Contained silver
Classification*             000s       %  oz/ton   oz/ton           000s lb                oz                 oz

Measured                  12,143    1.60   0.006    0.127           389,000            74,000          1,541,000
Indicated                 41,948    1.33   0.005    0.112         1,114,000           217,000          4,716,000
Measured plus indicated   54,090    1.39   0.005    0.116         1,503,000           291,000          6,257,000
Inferred                  29,167    1.09   0.003    0.064           636,000            87,000          1,875,000
                                                                                                    


                MINERAL RESOURCES NORTH, SOUTH & SOUTHEAST (OPEN-PIT DEPOSITS)

                            Tons  Copper    Gold   Silver  Contained copper    Contained gold   Contained silver
Classification*             000s       %  oz/ton   oz/ton           000s lb                oz                 oz

Measured                 271,291    0.42   0.001    0.048         2,299,000           394,000         12,932,000
Indicated                295,118    0.43   0.001    0.046         2,541,000           356,000         13,690,000
Measured plus indicated  566,409    0.43   0.001    0.047         4,840,000           750,000         26,622,000
Inferred                   8,009    0.52   0.001    0.052            83,000             6,000            414,000
                                                                                                   
The mineral resources have an effective date of April 15, 2015. The independent qualified person for the mineral 
resources is Dr. Rex Bryan, RM, SME, of TetraTech.  Tables may not add due to rounding.

Underground project: project mineral reserve -- East and E2 deposits

With respect to the underground project (Case A) in the PFS, the mineral reserves for the East and E2 deposits were developed from the deposits' measured and indicated mineral resources after the application of a net smelter return (NSR) cut-off grade of $46/ton minable shape optimizer (MSO) was conducted on the mining block models. The results generated from MSO were utilized for generating detailed and refined crosscut and stope designs within Deswik CAD.

The mineral reserves reflect the transverse mining method, primary and secondary stope sequence along with the use of cemented paste fill, unconsolidated paste fill and rock fill within the respective stope sequencing. Dilution and mine loss percentage estimates have been applied in the reserves. Stope dilutions range between 2.5 per cent and 10 per cent and stope recoveries range between 95 per cent and 96 per cent.

        UNDERGROUND PROJECT:  MINERAL RESERVES -- EAST AND E2 UNDERGROUND DEPOSIT                                    
              Mineral reserves -- eastern underground deposits (East and E2)
    
                                                          Contained   Contained   Contained
                       Ore   Copper       Gold   Silver      copper        gold      silver   Copper equiv.
Classification   000s tons        %     oz/ton   oz/ton     000s lb          oz          oz               %

Proven               7,400     1.85      0.007    0.144     273,800      51,000   1,064,000            2.01         
Probable            16,500     1.47      0.006    0.138     485,100     102,000   2,269,000            1.61         
Total               23,900     1.59      0.006    0.139     758,900     153,000   3,333,000            1.74         

(1) Copper equivalency calculations are based on $3 per pound for copper, $1,343 per ounce gold and $19.86 
    per ounce silver, and metallurgical recoveries of 92 per cent, 78 per cent and 70 per cent for copper, 
    gold and silver, respectively.
 
The independent qualified person for the underground project mineral reserves is Neil Schunke, PEng, of 
Mining Plus. The effective date of the underground project mineral reserves is July, 2017.  Tables may not 
add due to rounding.

Approximately 44 per cent of the total East and E2 deposits' measured and indicated mineral resources were converted to a mineral reserve by the underground project mine plan. Pumpkin Hollow's eastern deposits mineral resource is composed of resources located in the East and E2 deposits and the deeper JK-34 deposit. The current underground project mine plan does not include material from the JK-34 deposit.

Integrated project: mineral reserves

The mineral reserves summarized in the table were disclosed in the 2015 IFS as filed on SEDAR with an effective date of April 15, 2015, and reflect the various mining and operating assumptions detailed in that report. They remain unchanged as of the date of the technical report. The integrated project mineral reserves are not additive to the underground project mineral reserves.

                 MINERAL RESERVES NORTH AND SOUTH OPEN-PITTABLE DEPOSITS

                       Ore   Copper     Gold   Silver   Contained copper   Contained gold   Contained silver
Classification   000s tons        %   oz/ton   oz/ton            000s lb               oz                 oz

Proven             265,520     0.40    0.001    0.046          2,111,000          318,000         12,236,000         
Probable           273,765     0.38    0.001    0.043          2,100,000          274,000         11,703,000         
Total              539,285     0.39    0.001    0.044          4,211,000          592,000         23,939,000         
                                                                                                   
                                                                                                   
                    MINERAL RESERVES EAST AND E2 UNDERGROUND DEPOSITS (7)
 
                       Ore   Copper     Gold   Silver   Contained copper   Contained gold   Contained silver
Classification   000s tons        %   oz/ton   oz/ton            000s lb               oz                 oz

Proven               8,923     1.59    0.006    0.124            283,000           53,000          1,109,000
Probable            23,680     1.17    0.001    0.109            556,000          116,000          2,589,000
Total               32,603     1.29    0.005    0.113            839,000          169,000          3,698,000
                                                                                                   
                                                                                                   
            COMBINED MINERAL RESERVES NORTH AND SOUTH AND EAST AND E2 DEPOSITS                                   
                       Ore   Copper     Gold   Silver   Contained copper   Contained gold   Contained silver
Classification   000s tons        %   oz/ton   oz/ton            000s lb               oz                 oz

Proven             274,443     0.44    0.001    0.049          2,394,000          371,000         13,345,000
Probable           297,445     0.45    0.001    0.048          2,656,000          390,000         14,292,000
Total              571,888     0.44    0.001    0.048          5,050,000          761,000         27,637,000
                                                                                                   
The independent qualified persons for the integrated project mineral reserves are Ed Lips, PEng, of TetraTech, 
for the open-pit and Mel Lawson, RM, SME, of Stantec, for the underground. Tables may not add due to rounding.

Permitting

Both the underground project and integrated project development scenarios have been fully permitted in order to retain future development flexibility. It is expected that changes during final engineering design will require notification and submission of revised designs to the respective Nevada state agencies. These design changes are considered "engineering design changes," or minor modifications, to the permit and will not require a new permit application, nor the associated public notice and review.

Infrastructure

The project area is well supplied with nearby local infrastructure. -related infrastructure expenditures include an upgraded power line and substation and, for the integrated project only, a new water line that connects to the City of Yerington's water system. An energy cost of 5.6 cents per kilowatt-hour during production was used for the underground project PFS purposes, based on NV Energy estimated rates. Existing state and county roads will be used to access the mine site. Copper concentrates will be trucked directly from the mine site to a transload facility, where they will be transported to a U.S. west coast port or to domestic smelters. Process makeup water for underground project will derived from on-site wells. The company also has a water service agreement with the City of Yerington, that could be used for either the underground project or integrated project development plans. Housing and regional services are available in Yerington and the surrounding communities of Silver Springs, Smith Valley, Fernley, Dayton, Fallon, Carson City and Hawthorne, all of which are within commuting distance. These communities have an existing labour pool and housing, including a construction and an operations work force.

Mining

The underground project has one mining area, the eastern area, that is planned to be mined by underground methods, specifically, long-hole stoping, with predominantly cemented paste fill methods. The mining methods and the mining sequence were developed to maximize grades in the early production years to the extent possible. Underground mining zones included in the mine plan extend between the 1040 and 2840 levels. Access to the mine will be via the existing 24-foot-diameter vertical shaft. Vent and secondary egress shafts will be constructed as required.

Mining will be performed using the productive mechanized transverse long-hole mining method, with cemented paste fill (CPF) in the primary and some secondary stopes, and uncemented paste fill (UPF) or unconsolidated rock fill of remaining secondary stopes. Once at steady-state production, all waste rock is planned to remain underground to be used as backfill for secondary stopes. Until then, waste rock will be hoisted to surface.

One production/service shaft and three ventilation/emergency egress shafts are included in the mine design. Stopes will be 100 feet high by 50 feet wide for East South, 100 feet high by variable widths for E2 zones and 75 ft high by 50 ft wide for East North zone. Mining will be carried out using longhole drilling and blasting, with ore and waste material mucked using load, haul, dump equipment (LHDs), direct to ore passes or to remuck bays situated for optimum materials handling. Ore material will be transported via haul trucks and/or ore passes to the coarse ore bins (COB) for storage before being hoisted out of the mine. Haul trucks will be used to transport ore material from the remuck bays to the COBs, or to transport waste to the backfill levels. The majority of the underground mobile mining fleet will be battery powered. Primary crushing is located on the surface. Uncrushed rock will be conveyed to skips and hoisted to the surface, then crushed and stockpiled, for either direct feed to the processing plant or stockpiling to the low-grade stockpile. For all stopes that will be backfilled using CPF or UPF, a bulkhead will be constructed at all access points and the stopes will be filled with paste delivered by a piping network from the paste plant. The paste plant will be located on the surface and booster pumps will be used where necessary to transfer paste fill through the mine workings to the fill point.

Process plant

Ore will be hoisted to the surface, crushed and conveyed to a coarse ore stockpile and reclaim located near the 5,000-ton-per-day concentrator. The concentration circuit is conventional with a combined semi-autogenous (SAG)/ball mill circuit with cyclone classification, flotation circuits, followed by thickening and pressure filtration to produce a concentrate grading 26 per cent copper or greater, and containing payable gold and silver. ed metallurgical recoveries are 92 per cent, 78 per cent and 70 per cent, for copper, gold and silver, respectively.

Dry stack tailings (DST), in conjunction with underground paste backfill, are the preferred means of final deposition as this method contains substantially less water than tailings discharged directly from a concentrator. DST will be produced by filtering the final flotation tailings. The underground paste backfill portion of the tailings will be combined with cement before being deposited in the underground mine workings.

Filtration of tailings allows for better process water management and control. Process water will be recycled from the tailings and concentrate thickener overflows. Fresh water will generally be used only for pump gland service, mill lube cooling, SAG mill ring motor cooling, reagent preparation and safety showers/eyewash stations.

Metals production

ed ore tonnage and grades, and recovered metals production to the copper concentrate is summarized in the table. Life-of-mine (LOM) copper recovered to concentrates is estimated to be 698 million pounds.

                                                 Year 1 to 5 
                                       Units   (from Q4 2019)             LOM

Ore milled                              tons       8,970,000       23,909,000
Ore milled                          tons/day           4,915            5,000
Copper grade                               %           1.81%            1.59%
Copper grade                       % CuEq (1)           1.98%            1.74%
Copper in concentrates                   Klb         297,843          698,637
Copper in concentrates                Klb/yr          59,569           53,327
Gold in concentrates                      Oz          53,300          119,700
Silver in concentrates                    Oz       1,021,000        2,333,300
Gold grade                            Oz/ton           0.008            0.006
Gold grade                           g/tonne            0.26             0.22
Silver grade                          Oz/ton           0.163            0.139
Silver grade                         g/tonne            5.58             4.78
 
(1) Based on copper $3/lb, gold $1,300/oz, silver $17/oz and metallurgical 
    recoveries of 92 per cent, 78 per cent and 70 per cent, respectively.
                                                                                                                           


Capital costs

The underground project initial capital costs are estimated at $182.4-million as of September, 2017, with an accuracy of pus or minus 25 per cent. The major direct cost items include: underground mine development initially on the East deposits, process plant, tailing storage facility and site infrastructure. Indirect costs include such major areas as engineering and procurement, construction management, freight and commissioning, spares inventory, first fills, and owner's costs, such the owners personnel, local taxes, insurance and other site office costs.

                INITIAL CAPITAL COSTS

Area                                                       US$ M
Directs (1)                                                  
Mining                                                     $42.3 
Process facility                                            80.2 
Tailings                                                     4.0  
Infrastructure                                              22.2 
Subtotal directs                                           148.7
Indirects                                                    
Engineering, procurement, construction management (EPCM)     7.0  
Sales and use tax on purchased equipment                     3.3  
Construction indirects                                       4.6  
Owner's costs                                                8.8  
Spares                                                       0.1  
First fills                                                  0.5  
Commissioning and start-up                                   0.4  
Subtotal indirects                                          24.7 
Subtotal direct and indirects                              173.4
Contingency                                                  9.0  
Total initial capex                                        182.4

(1) EPC fee and freight are included in directs.
                                                             


The working capital required to finance capital expenditures and operating losses during ramp-up operations is estimated to be up to $22-million.

The initial capital cost excludes expenditures previously incurred by Nevada Copper from 2006 to September, 2017, which were used to finance the 1,900-foot-deep, 24-foot-diameter concrete-lined production size shaft and lateral development, surface facilities including a production hoist, head frame, power line and substation, water management infrastructure, and site buildings such as offices, warehouse, maintenance shop and mine dry.

Sustaining capital

Life-of-mine sustaining capital costs is a total of $110.6-million with an accuracy of plus or minus 25 per cent as summarized below, which include continuing underground mine development and equipment replacement, and expenditures for expansion of the tailings storage facility.


    SUSTAINING CAPITAL COSTS    

Area                      US$ M

Underground                67.7 
Surface                    22.6 
Infrastructure              9.7  
Deferred capital            3.5  
Underground contingency     7.1  
Total sustaining capex    110.6
                            


Operating costs

LOM site unit operating cash costs are projected to average $44.52 per ton milled, as summarized in the table.

LOM UNIT OPERATING COST SUMMARY  

                        $/ton 
Area                   milled

Development              5.83        
Diamond drilling         0.68        
Production              22.30       
Equipment leasing        2.41        
Total mining cost       31.22       
Milling cost             9.03        
Dry stack operations     1.05        
G&A cost                 3.22        
Total operating costs   44.52       
                                 


Continuing underground mine development costs are included in sustaining capital. Copper C1 production costs per payable pound, including site operating costs and copper conversion costs such as smelter charges and concentrate transport, net of gold and silver revenue credits, are estimated to average $1.69/lb for years one to five and $1.85/lb for LOM.

Concentrate marketing

The projected copper concentrate grade averages 26 per cent copper and contains payable gold and silver values. The concentrates are considered to be of good quality. The concentrates will be marketed to domestic smelters, and to Asia via a west coast port. Average concentrate transportation costs were estimated to be $75/dry metric tonne. Long-term smelter treatment and refining charges of $75/tonne concentrates and 7.5 cents/lb payable copper, respectively were used.

Economic analysis summary

economics were evaluated using a cash flow analysis, with future revenues and costs projected into the future to yield annual net cash flow and a net present value. The cash flows are calculated both before and after corporate income taxes, and include the cost of all royalties, local property taxes and Nevada net proceeds of mining tax. Cash flows were discounted at 5 per cent to reflect the time value of money and risk factors. An internal rate of return (IRR) and payback period for the project were also calculated. Variance in metals prices will have the most significant impact on the projected revenues and cash flows. The metal price scenarios in the attached tables were used.

1. Base metal price scenario

Base case metals prices were assumed from analysts' consensus prices, as published by Consensus Economics Inc. as displayed in the table.

                          Year->     2017     2018     2019     2020     2021    2022+       

Consensus copper prices     $/lb    $2.62    $2.66    $2.83    $3.05    $3.14    $3.20       
Consensus gold prices       $/oz   $1,254   $1,268   $1,276   $1,285   $1,284   $1,325      
Consensus silver prices     $/oz   $17.31   $18.21   $18.77   $19.40   $19.53   $20.01      

Source: Consensus Economics Inc. August, 2017.  

Spot metals prices on Kitco on Oct. 25, 2017, were copper: $3.17/lb, gold: $1,271/oz 
and silver: $16.95/oz.
                                                                                                                                                            


2. Alternative metal price scenarios

Alternative low and high copper price scenarios of $2.60/lb and $3.50/lb respectively were also used. A gold price of $1,300/oz and a silver price of $17/oz were used for both scenarios and all prices were held constant for these alternative scenarios.

Summary of economic results

A summary of key economic indicators for the underground project development option is summarized in the table.

                                                   Low case        Base case    High case

Copper price                               $/lb       $2.60        Consensus**      $3.50
Gold price                                 $/oz      $1,300        Consensus**     $1,300
Silver price                               $/oz         $17        Consensus**        $17

                                                       US$M             US$M         US$M

Net smelter revenue*, after royalty         LOM      $1,582           $1,941       $2,150
Operating margin                            LOM        $518             $876       $1,085
Operating margin                         Avg/yr         $40              $67          $83
Cumulative cash flow                     Pretax        $224             $582         $791
Cumulative cash flow                  After tax        $212             $496         $658
NPV 5%                                   Pretax        $108             $356         $510
NPV 5%                                After tax        $100             $301         $421
IRR                                      Pretax       13.4%            27.2%        36.8%
IRR                                   After tax       12.8%            25.2%        33.6%
Payback period                            years        6.50             4.75         4.00

* Note: Net revenues less smelter charges, concentrate transport and site operating costs.  

** Consensus prices as shown in the attached table.

Royalties and taxes

The economic results include the costs of all third party royalties, an estimate of local property taxes and Nevada net proceeds of mining tax payable on income from operations. The effects of corporate income taxes on project cash flows are also estimated by Nevada Copper on a stand-alone project basis. Income tax calculations related to mining income can be complex in the United States. Although nominal corporate tax rates are 35 per cent, deductions such as undepreciated accumulated tax pools, percentage depletion deductions and others available to mining operations typically reduce the effective tax rate to 20 per cent or less. The undepreciated accumulated tax pools available to shelter the project from corporate income taxes are substantial based on the prior expenditures made on the project. The tax calculation is an estimate only; actual corporate taxes payable may be higher or lower than those presented based on other future corporate activities, such as any proposed further development of the open-pit mineral resources. Readers should consult a tax adviser should they require more definitive information on taxation of income derived from mining operations in Nevada.

opportunities

mineralization in the East and E2 deposits remains open in several directions, and has not been drilled since 2015. Nevada Copper expects to resume drilling on the East and JK-34 deposits from underground drill stations once operations have commenced. Reserve expansion in these areas will likely extend mine life beyond the current 13 years and an underground definition drilling program will better define tonnages and grades.

Additionally, the potential for development of the mineral resources associated with the western open-pit deposits remains fully intact.

Case A underground project development schedule

Subject to the approval of the board of directors of the company and conclusion of project financing arrangements, detailed engineering and ordering of key long-lead-time mining and process equipment is targeted to commence in January, 2018. Ramp-up of underground development is anticipated to commence in late 2018 and early 2019 with mill ramp-up starting anticipated starting in Q2 of 2019.

Integrated project (Case B, 2015 IFS) summary of assumptions and economic results

The assumptions and results of the 2015 IFS (noted as Case B herein) were publicly disclosed in July, 2015, as summarized below:

  • mine life of 23 years with low-risk profile located in an ideal mining jurisdiction close to existing infrastructure, an increase of five years from the first published integrated feasibility study;
  • Assuming the base case of $3.15 (U.S.) copper, $1,200 (U.S.) gold and $18 (U.S.) silver, the integrated project generates life of mine (LOM) after-tax net cash flow of $2.5-billion (U.S.), NPV at 5 per cent of $1.1-billion (U.S.), an after-tax IRR of 15.6 per cent with 4.7-year payback;
  • Significant LOM metal production of 4.5 billion pounds (2.25 million tons) of copper, 512,000 ounces of gold and 15.6 million ounces of silver in a quality copper concentrate. Average annual copper production of 275 million pounds in years one to five;
  • The project development contemplates a 63,500-ton-per-day open-pit mine and 6,500-ton-per-day underground mine, feeding a single 70,000-ton-per-day concentrator, generating substantial annual cash flow over LOM;
  • Proven and probable mineral reserves, including open-pit and underground minable, are 572 million tons of ore grading 0.47 per cent copper equivalent (8), containing 5.05 billion pounds of copper, 761,000 ounces of gold and 27.6 million ounces of silver;
  • Initial capital costs are estimated to be $1.04-billion including contingencies, excluding working capital of $33-million. Sustaining LOM capital is $630-million;
  • Low LOM site operating costs of $12.80 per ton of ore-milled (year one to five -- C1 production costs at $1.49/lb payable copper), excluding leased equipment and Nevada State minerals Tax;
  • The 2015 IFS includes drilling data to 2011 for the underground deposits and 2013 for the open-pit deposits. Further upside and optimization potential exists from current drilling in 2015 which is not included in the 2015 IFS;
  • The 2015 IFS confirms the technical and financial viability of constructing and operating a 70,000-ton-per-day copper mining and processing operation at Pumpkin Hollow comprising a single large concentrator with mill feed from both open-pit and underground operation.

Qualified persons

In early 2017, Nevada Copper commissioned Sedgman Ltd. (part of the Cimic Group) as lead, along with Mining Plus Ltd., to complete a technical report including a PFS level study on the Case A underground project, and including the previous disclosure from the 2015 IFS, in accordance with NI 43-101 standards. The scientific and technical information in this news release has been reviewed and approved by John Grady, ChEng, IEA, project manager with Sedgman, and overall manager for the PFS. Mr. Grady is an independent qualified person within the meaning of NI 43-101.

The information and data contained in this news release insofar as Case A have been reviewed by the independent qualified persons, John Grady, ChEng, and Steve Rossetti, ChEng, of Sedgman, and Neil Schunke, PEng, of MiningPlus. The information and data contained in this news release insofar as Case B have been reviewed by the independent qualified persons as identified in the 2015 IFS or an alternative QP if this person is no longer available.

The information and data in this news release were also reviewed by Gregory French, PG, vice-president and project manager of Nevada Copper, and Robert McKnight, PEng, executive vice-president of Nevada Copper, both of whom are non-independent qualified persons within the meaning of NI 43-101.

(1) From mineral reserves table.

(2) All dollar references in this news release are to United States currency unless otherwise indicated.

(3) Copper equivalency calculations are based on consensus metal prices, gold and silver grades as presented in the PFS and metallurgical recoveries of 92 per cent, 78 per cent and 70 per cent for copper, gold and silver respectively.

(4) Pretax, based on analysts average consensus prices for copper, gold and silver (copper $2.66/lb in 2018 rising to $3.20/lb in 2020; similarly gold $1,268 rising to $1,325/oz; silver $18.21/oz rising to $20.01/oz).

(5) Note that a future stand-alone open-pit project development option on the mineral resources contained within the open-pittable deposits is not part of the technical report. The integrated project (Case B) as disclosed in the technical report is a large 70,000 tpd project with feed mostly from the open pit but also from the underground reserves.

(6) This 2015 technical report is a SEDAR-filed NI 43-101 technical report entitled "NI 43-101 Integrated Feasibility Study, Pumpkin Hollow , Yerington, Nev.," with an effective date of April 15, 2015.

(7) Metal prices used in the reserve estimate is Cu $3/lb, Au $1,250/oz, Ag $18/oz. Tons and grade estimates include dilution and recovery allowances.

(8) The copper grade equivalency was determined using base case metals prices and metallurgical recoveries of 89.3 per cent, 67.3 per cent and 56.3 per cent for copper, gold and silver respectively.