Barsele JV drills six metres of 33.46 g/t Au at Barsele

2017-01-17 09:58 ET - News Release

Mr. Gary Cope reports

OPERATIONAL UPDATE FOR THE BARSELE AU-VMS PROJECT

Barsele Minerals Corp. has provided its eighth operational progress update for the current exploration program within the Barsele gold-VMS (volcanogenic massive sulphide) project area in Vasterbottens Lan, northern Sweden. The exploration program is being operated by joint venture partner Agnico Eagle Mines Ltd. Ownership in the project is 55 per cent Agnico Eagle and 45 per cent Barsele.

During the month of November, diamond drilling with four machines was focused within and along the trend of the Avan, Central and Skirasen zones, where validation, conversion and expansion drilling has taken place. The highlight conversion hole SKI16010 yielded six metres core length (estimated four metres true thickness) grading 33.46 grams per tonne (g/t) gold uncut (6.33 g/t gold cut) at a depth of 180 metres below surface, plus 178 metres core length (estimated 125 metres true thickness) grading 1.68 g/t gold uncut (1.51 g/t gold cut) at a midpoint depth of 320 metres below surface. In addition, expansion hole CNT16017 yielded 31 metres core length (estimated 23.3 metres true thickness) grading 2.65 g/t gold uncut (2.6 g/t gold cut) at a midpoint of 410 metres below surface. This last intercept expands the known Central zone by 175 metres toward the Avan zone.

Twelve holes were completed during the month of November, of which five were validation holes and seven were conversion holes that verify continuity of mineralization. During November, 4,935 metres were drilled for a cumulative 2016 total of 30,432 metres in 79 holes. During November, there were 6,218 samples sent for analysis, with 8,014 assay results received. Basal till sampling results are yet to be received.

Barsele's president, Gary Cope, stated: "We continue to receive positive results in validation, conversion and expansion drilling at Barsele, and we remain confident in Agnico Eagle's deposit development methodology. The 178-metre hole in the Skirasen zone is very supportive of continuity in this sector of the deposit."

 
               HIGHLIGHT RESULTS FROM THE NOVEMBER, 2016, REPORTING PERIOD                    
                                                              
Hole          Category      From        To      Core        True       Au    Top-capped at
                              (m)       (m)   length   thickness     (g/t)       20 g/t Au
                                                  (m)         (m)                     (g/t)

AVA16012     Expansion    202.00    213.00     11.00        8.30     2.80             2.62                
AVA16013     Expansion    174.00    186.00     12.00        9.00     2.38                            
AVA16014     Expansion    604.00    612.00      8.00        5.00     2.03                           
AVA16015    Validation    117.00    131.00     14.00        7.50     1.46                      
AVA16016    Validation     18.00     30.00     12.00        7.00     1.46       
AVA16017    Validation    135.00    160.80     25.80       18.50     1.33     
AVA16018    Validation    200.00    207.00      7.00        5.00     1.63   
CNT16014    Validation     20.00     40.00     20.00       15.00     4.93             2.35
                           67.00    107.00     40.00       30.00     3.94             3.13
                          142.10    169.00     26.90       20.20     1.02        
                          217.00    240.00     23.00       17.30     1.15     
CNT16015    Validation     29.00     47.00     18.00       12.00     1.70       
                           58.00     67.00      9.00        6.00     2.13                     
                           83.00     99.00     16.00       10.50     1.35                        
                          124.00    148.00     24.00       21.00     1.32                          
                          169.00    174.00      5.00        3.80     2.94                        
                          191.00    238.00     47.00       31.00     1.55      
                          257.00    291.00     34.00       21.00     2.76    
CNT16017     Expansion     61.70     71.00      9.30        7.00     0.95    
                          388.00    395.70      7.70        5.80     1.92        
                          432.00    463.00     31.00       23.30     2.65             2.60 
                          483.00    492.00      9.00        6.80     0.90        
CNT16019    Validation     10.00     21.00     11.00        8.30     4.26        
                           65.00     77.00     12.00        9.00     1.48       
                           88.00    100.00     12.00        9.00     1.27       
                          113.00    144.00     31.00       23.30     1.75       
                          154.00    158.00      4.00        3.00     3.22     
CNT16020    Validation     11.00     29.00     18.00       13.50     1.83        
                           98.00    107.00      9.00        6.80     1.11     
CNT16021    Validation      3.50     16.00     12.50        9.40     0.56        
                           73.00     83.00     10.00        7.50     0.89     
CNT16022    Validation     21.00     76.00     55.00       43.00     1.22     
                           95.00    102.00      7.00        5.50     1.97    
CNT16024     Expansion    495.00    508.00     13.00        6.50     1.75        
                          526.00    541.00     15.00        7.50     1.10        
CNT16025     Expansion    375.00    390.00     15.00        5.00     1.41     
                          493.00    517.00     24.00        8.50     3.61             1.65
                          543.00    578.00     35.00       16.00     0.94    
CNT16026    Conversion    394.00    434.00     40.00       22.00     1.41     
                          480.00    504.00     24.00       13.00     0.89         
                          631.00    639.00      8.00        4.50     2.41    
SKI16008    Conversion    361.00    471.00    110.00       69.00     1.82             1.66
Including                 361.00    403.00     42.00       26.00     2.32             1.89
Including                 415.00    458.00     43.00       27.00     2.16     
SKI16009    Conversion    303.00    317.00     14.00        8.50     0.94      
                          419.00    436.00     17.00       10.50     1.22         
SKI16010    Conversion    243.00    249.00      6.00        4.00    33.46             6.33 
                          285.00    290.00      5.00        3.50    13.29             6.05
                          350.00    528.00    178.00      125.00     1.68             1.51
Including                 420.00    428.00      8.00        5.50     9.55             5.65
Including                 513.00    528.00      15.0       11.00     4.80      
                          625.00    627.00      2.00        1.50     8.00        
SKI16011    Conversion     59.00     66.00      7.00        5.00     1.76         
                          109.00    119.00     10.00        7.50     3.68             2.99
                          192.00    211.00     19.00       14.30     6.42             1.34
                          347.00    352.00      5.00        3.80     3.04        
                          423.00    425.00      2.00        1.50     8.58       
SKI16012    Conversion    248.00    263.00     15.00        7.50     2.69      
                          386.00    413.00     27.00       14.00     3.11             3.01
                          494.00    525.00     31.00       16.00     0.99          
                          534.00    560.00     26.00       14.00     5.01             2.49
                          652.00    659.00      7.00        3.80     3.56     

Drilling continued until Dec. 21, 2016, at which time there was a break until planned resumption in the new year.

As project operator, Agnico Eagle, has developed a community relations program to engage the various stakeholders in the project area. Basic environmental assessment and surface water characterization, species studies, and hydrogeology studies are continuing. Barsele expects that Agnico Eagle will release a new mineral resource estimate for the Avan, Central, Skirasen and Norra deposits in mid-February, 2017.

About the Barsele gold project

The Barsele project is located on the western end of the Proterozoic Skellefte trend, a prolific volcanogenic massive sulphide deposits belt, where it intersects with the Gold Line in northern Sweden. Both polymetallic deposits and intrusive-hosted orogenic gold deposits are present in this region and on the property. Current and past producers in the region include Boliden, Kristineberg, Bjorkdal, Svartliden and Storliden.

On Sept. 25, 2015, mineral resource estimates by Barsele were released for the Barsele project in four zones, the Central, Avan and Skirasen gold zones and the Norra VMS zone. The resource estimate for the Central-Avan-Skirasen zones states an indicated resource of 14.1 million tonnes grading 1.21 g/t gold for 547,000 contained ounces, plus an inferred resource of 20.2 million tonnes grading 0.97 g/t gold for 627,000 contained ounces. The polymetallic Norra zone contains an indicated resource of 110,000 tonnes grading 3.13 g/t gold, 30.3 g/t silver, 0.53 per cent copper and 0.72 per cent zinc, plus an inferred resource of 310,000 tonnes grading 1.62 g/t gold, 12.7 g/t silver, 0.26 per cent copper and 0.42 per cent zinc. All zones were estimated at a cut-off grade of 0.6 g/t gold.

Art Freeze, PGeo, is the qualified person as defined in National Instrument 43-101 and takes responsibility for the technical disclosure contained within this news release.