06:03:08 EDT Fri 03 May 2024
Enter Symbol
or Name
USA
CA



African Gold Group Inc
Symbol AGG
Shares Issued 159,341,737
Close 2014-11-24 C$ 0.045
Market Cap C$ 7,170,378
Recent Sedar Documents

African Gold Group releases NI 43-101 Kobada PEA

2014-11-25 09:14 ET - News Release

Mr. Declan Franzmann reports

AFRICAN GOLD GROUP, INC.: UPDATED PRELIMINARY ECONOMIC ASSESSMENT ESTABLISHES LOW CAPEX AND HIGH RETURNS FOR THE KOBADA GOLD PROJECT

African Gold Group Inc. has completed a scoping study and updated preliminary economic assessment (PEA) for the Kobada gold project, located in Mali, West Africa.

Highlights: low capital and operating costs for scalable gold production

  • The completion of the scoping study demonstrates robust project economics for a 1.6-million-tonne-per-annum gravity concentration and concentrate leaching operation;
  • Annual production in first two years of more than 50,000 gold ounces. Life-of-mine average gold production of 44,000 ounces for a 15-year mine life;
  • Cash costs of $482 (U.S.) per ounce for the first two years of operations, with cash costs of $694 (U.S.) per ounce life of mine. All in sustaining costs (AISC) of $792 (U.S.) per ounce life of mine;
  • Total preproduction capital of $46.6-million (U.S.) includes contingency of $6.1-million (U.S.);
  • Project payback in 18 months from initial production;
  • Project net present value at 5 per cent of $172-million (U.S.);
  • Project internal rate of return of 62 per cent;
  • Significant exploration and brownfields expansion potential to be financed from project cash flow with the potential to quickly develop additional shallow (within 25 metres of surface) resources for inclusion in the mine plan.

Scoping study parameters and results

The scoping study indicated that the project will generate $278-million (U.S.) in pretax cash flow over a mine life of 15 years. The net present value of the project at a discount rate of 5 per cent was estimated to be $172-million (U.S.) and the internal rate of return (IRR) was 62 per cent at a gold price of $1,250 (U.S.) per troy ounce.

Gold production is estimated to exceed 50,000 ounces per annum for the first two years, and the life-of-mine average is expected to be more than 44,000 ounce per annum.

Processing

The scoping study considered the construction of a mine to process 1.6 million tonnes per annum (Mtpy) through preconcentration and gravity concentration, followed by intensive leaching of the concentrates, electro-winning and smelting to produce gold bar (dore).

The processing concept is to remove most of the gangue material (the matrix of rock that does not contain gold) in the initial stage of the process. It is a metallurgical characteristic of the Kobada deposit that allows this to occur in the initial process, at low cost. Traditional carbon-in-pulp (CIP) plants rely on the crushing and grinding of 100 per cent of the feed for the leaching process. This requires large, power-intensive crushing and milling equipment, which is expensive to purchase and operate. The Kobada process flow sheet requires washing of the ore and the subsequent crushing of a small percentage of the coarser quartz rocks within the saprolite. It is expected that this crusher (a vertical impact crusher) will have installed power of only 200 kilowatts.

The next process step is preconcentration via two stage hydro-cyclones that reject the fine (minus-0.02 millimetre) size fraction. The testwork indicated that between 57 per cent and 61 per cent of the total mass of material is rejected with around 96-per-cent recovery of gold.

Gravity concentration then occurs, further reducing the volume of the material from preconcentration. This step can be considered a classification process where the process flow is separated based on density, with lighter material being rejected while the heavier material is upgraded to a concentrate. Testwork completed by Gekko Systems Pty. Ltd. indicated that the concentrate consisted of 1 per cent to 2 per cent of the total feed but recovering up to 87 per cent of the gold. More specifically, from 1.6 million tonnes of feed material from mining, a concentrate of 16,000 to 32,000 tonnes is produced.

This concentrate is then milled traditionally before passing to an intensive leach reactor. The significance of the preconcentration and gravity concentration means that rather than milling 1.6 Mtpa, less than 32,000 tonnes per annum of concentrate will be milled. The installed power for the regrind mill is only 75 kw which is 40 times smaller than that required to grind 1.6 Mtpa.

The net outcome for this process route is recovery of 85 per cent of the gold for a cost of $7.19 (U.S.) per tonne processed. This places Kobada into a processing cost regime similar to a heap-leach operation but with higher, faster and more reliable recovery of gold.

The processing plant will be modular, designed and fabricated in Australia, precommissioned in Australia prior to being shipped to Mali for assembly. This presents very low construction risk for the project and offers opportunities to relocate the plant in order to maintain optimal haulage distances.

The low capital cost of this style of plant also offers opportunities to grow the production profile as increases in the resource base are established. This can be done in a cost-effective and incremental manner adding a parallel circuit to the process.

Mining and production

The updated scoping study indicates that the project has robust economics through a 15-year mine life and the first two years can be considered exceptional from a financial perspective. The waste-to-ore strip ratio is less than 0.73 to 1 for the first three years as a result of the outcropping mineralization. A head grade of more than 1.1 grams per tonne gold can also be maintained for the first two years production, resulting in pretax cash flows of more than $37-million (U.S.) per annum in years one and two.

The mining operation is expected to be simple as the saprolite rocks are completely weathered and free digging, which negates the need to drill and use explosives. This is an important consideration that results in the estimated average mining cost to be $2.56 (U.S.) per tonne of waste and $3.85 (U.S.) per tonne of ore mined. General and administration costs were estimated at $3.03 (U.S.) per tonne processed.

Initial mining is via two starter pits before stripping to the final pit limits begins in earnest in year four, with a consequent rise in strip ratio. The in-pit mining inventory was estimated to be 24 million tonnes at a diluted grade of 1.01 g/t Au, containing more than 778,000 ounces of gold. This inventory comprises the measured, indicated and inferred mineral resource within a pit design based on optimizations using Whittle software. The inventory is detailed in the table.

        DILUTED IN PIT INVENTORY BY RESOURCE CATEGORY       

Resource category         Tonnes            Au            Au 
                              (M)         (g/t)         (koz)

Measured                     7.2          1.06           246
Indicated                    9.5          1.05           318
Inferred                     7.3          0.92           214
Total                       24.0          1.01           778

Preproduction capital expenditure

One of the features of the Kobada project is the relatively small amount of infrastructure required prior to the commencement of operations. Total preproduction capital was estimated to be $46.6-million (U.S.), including a contingency of $6.1-million (U.S.). This includes the following significant items:

  • Modular processing plant -- $21.7-million (U.S.);
  • Upgrade to access road and all-weather crossing of the Fie River -- $3.6-million (U.S.);
  • Accommodation camp -- $3.2-million (U.S.);
  • Power stations -- $2.4-million (U.S.);
  • Process water and pumping infrastructure -- $1.5-million (U.S.);
  • Tailing storage facilities -- $1.43-million (U.S.) for initial three years.

Further studies

Progress on completion of the feasibility study is significant with approximately 80 per cent of the study now complete. Much of the key data and studies that support the PEA are of a very high level of confidence; however, the requirement to complete geotechnical drilling for both the final pit shell design and detailed engineering for the tailings storage facility will require further time, necessitating completion of the final study in early 2015.

The issues which differentiate the current updated PEA from the full feasibility study are not significant from an economic, social or environmental risk perspective. A mining licence application is being planned for near-term submission based on the outcomes of the current updated study that is being presented in this press release.

Availability of debt finance for the project will require the full feasibility study outcomes despite the fact assumptions and parameters used in the current study are conservative. This position offers the opportunity to further improve on the economic outcomes of the project with further detailed work.

Mineral resource estimate

The average grade of the measured, indicated and inferred mineral resource estimate, as contained in this updated study, is now above one gram per tonne gold (as reported above a lower cut-off grade of 0.3 g/t Au). This is a significant development for the Kobada gold project as it is 20 per cent higher than the previous grade estimation, reported in June, 2013. The resource estimation technique used was multiple indicator kriging (MIK), considered to be best industry practice for this style of mineralization. The new resource estimate is presented in the table.

                
     KOBADA GOLD PROJECT MINERAL RESOURCE ESTIMATE ABOVE 0.3 G/T AU     

Resource category                  Tonnes             Au             Au
                                       (M)          (g/t)          (koz)

Measured mineral resource            10.8           1.06            367
Indicated mineral resource           25.2           1.04            843
Total M and I resource               36.0           1.05          1,210
Inferred mineral resource            39.0            1.0          1,205

The company acknowledges that there is significantly more inferred mineral resource than the previous resource estimate stated. Much of the inferred resource has been drilled at closer than 50 m by 50 m drill collar locations; however, much of the drilling in the area of the inferred resource has been drilled in the same orientation or parallel to the strike of the deposit. This has introduced a volumetric uncertainty in the mineralized interpretation because detailed information as to the exact location of the hangingwall and footwall of the mineralization is often not available across the strike of the deposit. That is, the drill hole orientation is parallel to the mineralization rather than across it. This typically occurs at the north and south of the main mineralized zone; however, upon investigation, it does not appear to introduce any bias to grade interpolation. The grade of the inferred resource category is generally lower than the measured and indicated portions of the estimate.

Environmental studies

The company has completed an environmental baseline study for the project and is currently completing the environmental and social impact assessment (ESIA). These documents will be used in the application for the exploitation licence and will ultimately form part of the final feasibility study.

Qualified persons

The preliminary economic assessment was prepared under the supervision of John Dunlop (John Dunlop and Associates), Tim Hughes (Gekko Systems Pty. Ltd.) and Brian Wolfe (International Resource Solutions Pty. Ltd.). All three are independent of African Gold Group and are qualified persons as defined by National Instrument 43-101. Declan Franzmann (chief executive officer of AGG) is the company's designated qualified person for the study. All QPs have reviewed the content of this press release.

Conclusion

Designs and financial modelling have been completed assuming a gold price of $1,250 (U.S.) per ounce. The project displays robust economics at a range of metal prices and the table details the sensitivity of the project to changes in gold price.

                        
                     SENSITIVITY TO GOLD PRICE

                                  Pretax NPV ($M)

Gold price                  0%          5%         10%         IRR
(US$/oz)

1,000                     $117       $ 66         $ 38         30%
1,250                      278         172         112         62%
1,500                      438         278         186         92%

The nature of the Kobada deposit lends itself to high early cash flow. This characteristic allows fast repayment of debt, and the tax regime in Mali allows for a three-year tax-free window for the local operating company. This is significant as the project has a capital payback period of just 18 months, during the time of the government tax incentive.

The priority of the company during the initial years of production will be to identify other shallow resources (within 25 m of surface) on the 215-square-kilometre property which will allow continued mining of low waste-to-ore-ratio pits, further enhancing the cash flow characteristics of the project.

African Gold Group president and CEO Declan Franzmann, FAusIMM, commented:

"The MIK resource estimate has lowered the resource tonnage with a corresponding 20-per-cent improvement in gold grade to 1.05 g/t. This is a significant increase in resource grade and has an important impact on the project's economics.

"The favourable metallurgy characteristics have resulted in a processing route with a cost profile equivalent to heap-leaching techniques, but with more reliable, faster and greater recovery of gold. This favourable metallurgy also means that preproduction capital expenditures are significantly lower than for CIP processing plants of this throughput.

"The free-digging saprolite means mining is relatively cheap and simple. The outcropping mineralization leads to high early cash flow and fast capital payback.

"All these facets underlie an economic mine plan, but there is significant upside potential that can be demonstrated. It is my opinion that additional resources can be added to mine plan. The target depth is less than 25 m below surface and covers a significant portion of AGG's 215-square-kilometre landholding. The pathfinder exploration tool utilizes the artisanal miner's workings, which is pervasive throughout the concession, following up with shallow augur and reverse circulation drilling. Success in this strategy will allow a low strip ratio to be maintained for a greater duration, enhancing the project's financial parameters further. This exploration can be funded from the project cash flow."

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.