Mr. James Campbell reports
ROCKWELL PROVIDES PRODUCTION UPDATE FOR FIRST QUARTER OF FISCAL 2012 ENDING MAY 31, 2012
Rockwell Diamonds Inc.'s volumes of gravel processed in the first quarter increased 56 per cent year on
year, with a 74-per-cent improvement in carat production from the three
operational mines over the same period to 6,116 carats. Overall volumes
processed continued to track closer to the company's internal targets
while budgeted carat recoveries were exceeded as the bulk X-ray proof
of concept plant introduced earlier in the year contributed 1,118
carats in the last six weeks of the quarter.
First quarter operational update
The volume and carat production for the company's operational mines for
the quarter ended May 31, 2012, is in the attached table.
Volumes of gravel processed (m3) Carats produced
Q1 2012 Q1 2013 % change Q1 2012 Q1 2013 % change
Saxendrift 325,076 453,204 39% 1,693 2,126 26%
Saxendrift bulk X-ray - - - - 1,118 100%
Tirisano - 123,048 100% - 1,222 100%
Klipdam 194,192 232,216 20% 1,832 2,768 51%
Total 519,268 808,468 56% 3,525 6,116 105%
Saxendrift complex
Saxendrift achieved a 39-per-cent year-on-year increase in volumes processed to 453,204 cubic metres for the first quarter, in line with its targets, while carats produced
increased 26 per cent to 2,126 carats.
The bulk X-ray plant was commissioned in April, 2012, below budget and on
schedule. A total of 1,118 carats were extracted from recovery tailings
during the first six weeks of operation of this proof of concept
project with the largest stone recovered weighing 74 carats. The next
phase of testing is progressing with the processing of additional
recovery tailings.
The in field screen, commissioned in November, 2011, increased plant
throughput during the first quarter. In addition, it went some way to
mitigate the impact of increased sand content of the orebodies being
mined.
Improving production from Rockwell's properties that are located
adjacent to the Saxendrift mine is now the company's focus. This
includes the additional resources acquired as part of the Jasper project purchase, which became unconditional at the end of May, 2012. Plans are
also in progress to evaluate the potential of extending mining
operations to other parts of the Saxendrift mine property with the
objective of extending the life of this operational footprint.
The prefeasibility study for Wouterspan, scheduled for completion by the end of 2012, has commenced and is
scheduled for completion by year-end.
Tirisano
Ramp up in production continues, with plant throughput volumes
increasing by 30 per cent to 123,048 cubic metres in the first quarter, from 94,643 cubic metres in the fourth quarter of fiscal 2012.
Carat production more than doubled in the three months to May 31, 2012,
yielding 1,222 carats compared with 557 carats in the previous
three-month period. This was as a result of grade increases to 0.99
carat per 100 cubic metres, from 0.59 carat per 100 cubic metres in the quarter ended Feb. 29, 2012.
Construction of the wet front end facility which has the capability to
process gravels with high clay content was completed on schedule at the
end of May, 2012, and is expected to provide additional flexibility in
the mine plan that was previously lacking.
Maintenance and rationalization of the earthmoving fleet have been a key
focus this past quarter.
Klipdam
A year-on-year increase of 20 per cent in plant throughput to 232,216 cubic metres was due to the conversion to continuous operations, installing a new
barrel screen and the removal of five conveyor belts in the front end
of the production plant.
Carat production increased 51 per cent with improved grades as a result of the
focus on processing the Rooikoppie gravels. The value per carat was in
line with the previous quarter due to current world markets.
The appointment of a mine manager and mining manager has significantly
improved the overall operation of the mine.
Commenting on Rockwell's progress in relation to its focus on diamond
value management, James Campbell, chief executive officer, stated that: "In 2011, our
executive management and board put in place two simultaneous strategies
for enhancing shareholder value, namely to execute on our plans to
optimize production at each of our operational mines and to rebuild the
mine life profile of the company's assets. The results to date are
showing the first positive impacts of these strategies."
We seek Safe Harbor.
© 2024 Canjex Publishing Ltd. All rights reserved.