Ms. Pamela Solly reports
THOMPSON CREEK ANNOUNCES COMPLETION OF THE ENDAKO MILL EXPANSION PROJECT AND PRELIMINARY FIRST QUARTER 2012 PRODUCTION AND CASH COST RESULTS
Thompson Creek Metals Company Inc. has completed the mill expansion
project at the Endako mine. As previously announced, commissioning of
the company's new SAG/ball mill and rougher flotation circuit was
completed in early January, followed by a successful ramp-up to
commercial production beginning Feb. 1, 2012. The remaining
construction work on the regrind circuit and the pebble crusher was
completed in late March. The mill is meeting its design capacity
throughput of approximately 55,000 tons per day. Concentrate and
recovery grades continue to improve and are expected to meet design
capacity in the second quarter of 2012. The existing 45-year-old mill
at the site has been shut down and will be left on care and
maintenance.
For the first quarter of 2012, the company expects to realize an
operating loss primarily due to the start-up and commissioning of the
new mill at the Endako mine. First quarter 2012 results are expected
to include the company's 75-per-cent share of an aggregate lower-of-cost or
market product inventory writedown at the Endako mine of approximately
$12-million and approximately $3-million of the company's share of Endako
commissioning and start-up costs that will be expensed through
operating expenses (previously included in the company's share of total
estimated capital expenditures of approximately $500-million),
together with significantly lower production, higher unit costs, higher
unit depreciation, and lower sales volumes and average realized prices
compared with the first quarter of 2011. Significant stripping costs at
the Thompson Creek mine, associated with the continuing mine pit
pushbacks, have been incurred and are expected to continue in the first
half of 2012, which also contributed to the expected operating loss for
the first quarter.
For the first quarter of 2012, the company produced approximately 4.4
million pounds of molybdenum at an average cash cost of approximately
$13 per pound produced (excluding commissioning and start-up costs
at the Endako mine) and sold approximately 4.9 million pounds of
molybdenum from its mines, for an average realized molybdenum sales
price per pound for the quarter of approximately $14.75. For the first
quarter of 2012, the Thompson Creek mine produced approximately 3.4
million pounds of molybdenum at a cash cost of approximately $10.35 per
pound produced, and the company's share of production from the Endako
mine was approximately one million pounds of molybdenum for the first
quarter at a cash cost of approximately $22 per pound produced.
"We are extremely pleased to have completed the construction of the new
mill at the Endako mine and to have achieved design capacity throughput
so quickly in the start-up process," said Kevin Loughrey, chairman and
chief executive officer of Thompson Creek. "Our dedicated employees,
contractors and suppliers performed a remarkable job, commissioning the
new mill and achieving design capacity throughput in approximately 20
days under extreme and difficult winter conditions, with temperatures
at times reaching minus 40 C," added Mr. Loughrey.
"The higher costs and lower production that we experienced during the
commissioning and start-up phase are typical with projects like this,
and, although production was lower and costs were higher from the Endako
mine in the first quarter of 2012, through continued optimization, we
expect to make up for the lower production throughout the remainder of
2012 and to meet our previously announced 2012 production guidance from
the Endako mine of approximately 14 [million] to 15 million pounds of molybdenum
on a 100-per-cent basis, or 10 [million] to 11 million pounds for the company's 75-per-cent
share," said Mr. Loughrey. "We anticipate meeting our total 2012
production guidance of approximately 26 [million] to 28 million pounds of
molybdenum; however, due to inflationary pressures on diesel fuel,
consumables and energy, we are currently tracking to the higher range
of the company's current 2012 average cash cost guidance of
approximately $7.75 to $9 per pound produced. If the current
inflationary pressures continue, our costs will continue to increase
and potentially rise above the current guidance," added Mr. Loughrey.
We seek Safe Harbor.
© 2026 Canjex Publishing Ltd. All rights reserved.