Ms. Diane Garrett reports
ROMARCO ANNOUNCES TIMING OF RECORD OF DECISION
Following the posting of
the final environmental impact statement on July 24, 2014, on the U.S.
Army Corps of Engineers website, the Corps has now informed Romarco Minerals Inc. it will issue its record of
decision on the 404 wetlands permit application in November,
2014. The 404 permit is the only federal environmental permit required
for the Haile gold mine.
Diane R. Garrett, president and chief executive officer, commented: "We are pleased that the
Corps has announced its guidance on the timing of the ROD. The
November timing falls within our planned schedule for funding and
preparing for construction activities at the Haile gold mine. Based on
our continued work with South Carolina Department of Health and
Environmental Control, we anticipate that the remaining state
permits also will meet this schedule."
In 2013, the company received four state permits: the national
pollutant discharge elimination system permit, air quality permit, dam
safety permit and stormwater construction permit. The state permits
or authorizations remaining for the Haile project include, among
others, the state mine operating permit and 401 water quality
certification. A list of other required permits is included in the
company's National Instrument 43-101-compliant technical report filed
on SEDAR on March 19, 2012.