ENTERPRISE AND ENBRIDGE ANNOUNCE COMPLETION OF SEAWAY PIPELINE REVERSAL
Enterprise Products Partners LP and Enbridge Inc.
have completed modifications to the Seaway crude
oil pipeline which allow it to transport crude oil from Cushing, Okla.,
to the U.S. Gulf Coast. The pipeline is in the
process of being commissioned, and the first flows of crude oil into the
line are expected to begin this weekend. The reversal of the 500-mile,
30-inch-diameter pipeline, which had been in northbound service since
1995, provides North American producers with the infrastructure needed
to access more than four million barrels per day of Gulf Coast
refinery demand.
The reversal will initially provide 150,000 barrels per day of capacity, which is
expected to increase to more than 400,000 barrels per day in the first quarter of
2013 with additional modifications and increased pumping capabilities.