Mr. Mark Learmonth reports
BLANKET PRODUCTION UPDATE AND 2012 OUTLOOK
Caledonia Mining Corp. has provided information on its gold production from the Blanket mine in Zimbabwe during fourth quarter
2011 which ended Dec. 31, 2011.
- 10,533 ounces of gold produced during fourth quarter 2011, representing an 8.1-per-cent increase on
third quarter 2011 (9,743 ounces), and a 69-per-cent increase on fourth quarter 2010 (6,227 ounces);
- Total 2011 gold production was 35,826 ounces, a 102-per-cent increase over the annual
gold production in 2010 of 17,707 ounces;
- Targeted 2012 annual gold production of 40,000 ounces.
Blanket production
The company is pleased to announce a successful year at the Blanket mine
which produced 35,826 ounces of gold, an increase of 102 per cent over the previous
year.
In accordance with the company's aim to continuously improve operations at
Blanket, the following infrastructure, process and equipment investment
programs were undertaken during the final quarter of 2011:
- Considerable work on the refurbishment of the level 14, 18 and 22 underground haulages continued throughout the fourth quarter and this is expected to be
completed by the end of first quarter 2012. This program is essential to support
and sustain the company's increased underground production.
-
The installation of an automatic cyanide measuring and dosing system on
the CIL circuit was commissioned. This installation is providing both
better control over, and a detectable reduction in, cyanide usage per
tonne of ore milled.
-
Certain rectification and maintenance work on the 825-metre-deep No. 4 shaft
was commenced during November, 2011. This work is expected to be
completed by the end of February, 2012, and once completed will allow
Blanket to increase the speed of the No. 4 shaft winder, thereby
increasing hoisting capacity. As noted in the third quarter management's discussion and analysis (MD&A), this work may
have an adverse effect on gold production in the first quarter of 2012.
-
A belt scale was installed on the No. 1 conveyor belt so that all ore
tonnages delivered from various ore sources such as the level 14
mid-shaft loading station, Lima, and in due course the satellite
properties such as GG and Mascot, can be individually and accurately
measured. The reprogrammed computerized recording system is expected to
be commissioned during early February and the system is then expected
to facilitate further metallurgical optimization.
Outlook
Following a year in which Caledonia has increased production at Blanket
by 102 per cent to 35,826 ounces (2010 gold production was 17,707 ounces), the company is now
confident that it will be able to achieve its targeted gold production
of 40,000 ounces for the current financial year. Discussions with the
government of Zimbabwe regarding the indigenization of the Blanket mine
have continued.