Mr. Matt Badylak reports
GALIANO GOLD REPORTS Q3 2023 OPERATING AND FINANCIAL RESULTS
Galiano Gold Inc. has released the third quarter (Q3) operating and financial results for the company and the Asanko gold mine (AGM), located in Ghana, West Africa. The AGM is a 50:50 joint venture (JV) with Gold Fields Ltd., which is managed and operated by Galiano. All financial information contained in this news release is unaudited and reported in U.S. dollars.
Asanko gold mine JV key metrics (100-per-cent basis):
-
Safety: one lost-time injury (LTI) and three total recordable injuries (TRI) recorded during the quarter, resulting in 12-month rolling LTI and TRI frequency rates of 0.54 and 1.61 per million employee hours worked, respectively;
-
Production performance: gold production of 35,779 ounces during the third quarter; year-to-date gold production of 102,130 ounces. Full-year gold production is expected to come in at the top end of guidance of between 120,000 and 130,000 ounces;
-
Milling performance: achieved milling throughput of 1.6 million tonnes (t) of ore at a grade of 0.8 gram per tonne (g/t) during the quarter. Metallurgical recovery in Q3 2023 was 87 per cent;
-
Cost performance and cash flow: total cash costs (1) of $1,056 per gold ounce (oz) and all-in sustaining costs (AISC) (1) of $1,445 per oz for the three months ended Sept. 30, 2023. Full-year AISC (1) guidance has been revised from between $1,650 per oz and $1,750 per oz to between $1,500 per oz and $1,600 per oz due to higher gold sales and timing of sustaining capital expenditures. Additionally, the JV generated positive cash flow from operations of $39.7-million and free cash flow (1) of $24.0-million during the quarter;
-
Financial performance: gold revenue of $67.6-million generated from 35,522 gold ounces sold at an average realized price of $1,902 per oz for the quarter. Net income of $21.3-million and adjusted EBITDA (earnings before interest, taxes, depreciation and amortization) (1) of $25.5-million during the quarter;
-
Restart of mining: mining operations at the AGM restarted on Oct. 1, 2023. The AGM's mining contractor has mobilized a fleet of mining equipment and prestripping activities are continuing. The Abore pit remains on track to deliver higher-grade ore to the processing plant, than the current stockpile processing, in Q2 2024;
- Exploration focus: initiated drilling programs at Abore to convert inferred mineral resources to the indicated mineral resource category, at Midras South to advance the deposit toward a maiden mineral reserve estimate, and at Nkran, completed a phase 1 mineral resource upgrade and mineral reserve conversion drilling;
-
Robust liquidity:
$136.9-million in cash and cash equivalents, $4.4-million in gold sales receivables, $2.0-million in gold on hand, and no debt as of Sept. 30, 2023.
Galiano highlights:
-
Stable balance sheet: cash and cash equivalents of $56.1-million as at Sept. 30, 2023, while remaining debt free;
-
Positive earnings: net income of $11.4-million or five cents per common share during the quarter, including the company's share of the JV's net earnings for the quarter.
"The third quarter was another strong financial and operating period for the AGM, which is on track to achieve the upper end of gold production guidance of between 120,000 to 130,000 ounces," stated Matt Badylak, Galiano's president and chief executive officer. "The mine continued to generate significant cash flows through stockpile processing, which has further strengthened the AGM's balance sheet. As planned, mining operations at the AGM have recommenced and Abore is on track to deliver higher-grade ore to the processing plant by the second quarter of 2024.
"At the corporate level, we closed the quarter with $56-million in cash, no debt and remain in an enviable position to pursue accretive opportunities for growth. Health and safety continue to remain a top priority throughout the organization as we constantly strive to reinforce our commitment to zero harm and implementation of best safety practices at the Asanko gold mine."
Highlights continued:
-
The AGM produced 35,779 ounces of gold during Q3 2023, as the processing plant achieved milling throughput of 1.6 million tonnes (t) of ore at a grade of 0.8 g/t with metallurgical recovery averaging 87 per cent. The composition of the feed blend processed during Q3 2023 had a higher percentage of oxide ore resulting in the strong recoveries achieved;
- Sold 35,522 ounces of gold in Q3 2023 at an average realized gold price of $1,902 per oz for total revenue of $67.8-million (including $200,000 of byproduct silver revenue), a decrease of $9.1-million from Q3 2022. The decrease in revenue quarter on quarter was due to a 22-per-cent reduction in sales volumes relative to Q3 2022, partly offset by a 13-per-cent increase in realized gold prices;
-
Income from mine operations for Q3 2023 totalled $23.7-million, compared with income from mine operations of $25.7-million in Q3 2022. The decrease in income from mine operations was due to a $9.1-million reduction in revenue described above, partly offset by $6.2-million decrease in cost of sales that resulted from fewer ounces sold as well as processing ore that had no carrying value for accounting purposes;
-
Reported adjusted EBITDA (1) of $25.5-million in Q3 2023, compared with $22.3-million in Q3 2022. The increase in adjusted EBITDA (1) was largely driven by Q3 2022 including $4.3-million of mining contractor costs;
- Total cash costs (1) in Q3 2023 amounted to $1,056 per oz, compared with $1,001 per oz in Q3 2022. Although gold sales volumes decreased by 22 per cent in Q3 2023, total cash costs per ounce (1) in Q3 2023 were only 5 per cent higher than Q3 2022 as a result of processing ore that had no carrying value for accounting purposes;
- AISC (1) for Q3 2023 was $1,445 per oz, compared with $1,178 per oz in the comparative period. AISC (1) was higher in the current quarter predominately due to the increase in total cash costs per ounce (1) mentioned above and higher sustaining capital expenditures ($276-per-ounce increase) to support the restart of mining in Q4 2023, construction of water treatment facilities and raising the height of the tailings storage facility;
-
The AGM generated $39.7-million of cash flow from operating activities and free cash flow (1) of $24.0-million during Q3 2023. This compares with $26.1-million of cash flow from operating activities and free cash flow (1) of $16.3-million during Q3 2022. The increase in free cash flow1 was primarily due to lower working capital tie-up, partly offset by higher capital spend to support a restart of mining operations.
Highlights continued:
-
The company reported net income of $11.4-million in Q3 2023, compared with net income of $1.3-million in Q3 2022. Net income was higher in Q3 2023 due to the company recording its share of the JV's net earnings which amounted to $9.6-million. During Q3 2022, the company did not recognize its share of the JV's net earnings as the estimated recoverable amount of the company's investment in the JV was nil as at Sept. 30, 2022.
- Adjusted EBITDA (1) for Q3 2023 amounted to $10.3-million, compared with a loss of $2.1-million in Q3 2022. The increase in adjusted EBITDA (1) was due to the increase in net income during Q3 2023 as described above.
-
Cash used in operating activities in Q3 2023 was $100,000, compared with cash provided by operating activities of $1.5-million in Q3 2022. The increase in cash used in operating activities from Q3 2022 to Q3 2023 was driven by working capital movements, specifically related to the company's service fee receivable from the JV.
-
As of Sept. 30, 2023, the company had cash and cash equivalents of $56.1-million, while remaining debt free.
This news release should be read in conjunction with Galiano's management's discussion and analysis (MD&A) and the unaudited condensed consolidated interim financial statements for the three and nine months ended Sept. 30, 2023, and Sept. 30, 2022, which are available on the company's website and on SEDAR+.
(1) Non-IFRS (international financial reporting standards) performance measures.
Qualified person
Richard Miller, PEng, vice-president, technical services, with Galiano, is a qualified person as defined by Canadian National Instrument 43-101, Standards of Disclosure for Mineral Projects, and has approved the scientific and technical information contained in this news release.
About Galiano Gold Inc.
Galiano is focused on creating a sustainable business capable of value creation for all stakeholders through production, exploration and disciplined deployment of its financial resources. The company operates and manages the Asanko gold mine, which is located in Ghana, West Africa, and jointly owned with Gold Fields. Galiano is committed to the highest standards for environmental management, social responsibility, and the health and safety of its employees and neighbouring communities.
We seek Safe Harbor.
© 2026 Canjex Publishing Ltd. All rights reserved.