Minera Alamos pegs Cerro posttax NPV at $150.5M (U.S.)

2022-10-03 09:40 ET - News Release

Mr. Doug Ramshaw reports

MINERA ALAMOS ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR THE CERRO DE ORO GOLD PROJECT

Minera Alamos Inc. has released the positive results of an independent preliminary economic assessment (PEA) for its Cerro de Oro project in Zacatecas, Mexico. The PEA was prepared in accordance with National Instrument 43-101 -- Standards of Disclosure for Mineral Projects (NI 43-101) by Scott Zelligan, PGeo, Lawrence Segerstrom, MSc, CPG, Peimeng Ling, PEng, Alex Duggan, PEng, and Toren Olsen, PG. A technical report with the details of the PEA will be filed on SEDAR under the company's profile within 45 days of the date of this news release. (Unless stated, all currency references are in United States dollars).

Highlights of PEA

  • Production highlights:
    • Average annual gold production approaching 60,000 ounces (approximately 60,000 ounces to 70,000 ounces in years 1 through 4);
    • 8.2-year mine life based on initial minable total of 59 Mt (million tonnes) of mineralization (0.37 g/t (gram per tonne) gold) heap leached at an average rate of approximately 20,000 tonnes per day (tpd) -- plus 0.4 g/t Au in years 1 through 4;
    • 477,000 ounces of gold produced in loaded carbon/dore;
    • LOM (life of mine) strip ratio of 0.3:1 (waste: mineralization);
  • Robust economics using metals prices of $1,600/ounce Au:
    • LOM all-in sustaining cost (AISC) of $873/ounce -- averaging $763/ounce in years 1 through 4;
    • After-tax NPV (net present value) at 5 per cent of $150.5-million and IRR (internal rate of return) of 111 per cent;
  • Low capital intensity project with rapid payback:
    • Preproduction capital costs of $28.1-million (includes 30 per cent contingency);
    • Payback period of 11 months;
    • Used crushing plant already purchased reduces up front capital requirements;
  • Significant upside:
    • Mineralization appears open in multiple directions as well as to depth;
    • Additional metallurgical testing to examine amenability of gold recovery from deeper sulphide zones of mineralization not accounted for in current resource calculations and mine plans (some early indications that material may prove to be leachable);
  • Updated inferred mineral resource estimate containing 67 million tonnes of 0.37 g/t Au (790,000 ounces of contained gold) based on an upward revision of the base case resource metal price to $1,700/ounce.

"Leaning on our team's collective experience in mine building in Mexico with capital and operating costs informed by the recent construction and ramp up of the Santana gold mine, the Cerro de Oro PEA is a game changer for Minera as we strive to reach our initial target of a plus-100,000-ounce/year gold producer," commented Doug Ramshaw, president. "Given the rampant inflationary pressures across the industry, it is a testament to Minera's smart and nimble business model that a new mine could be developed at Cerro de Oro for the low capital intensity presented in the PEA."

Capital cost estimates

Total preproduction capital costs at the Cerro de Oro project are estimated at $28.1-million. Sustaining capital costs over the LOM are estimated at $14.7-million for a total project capital cost of $42.8-million. The preproduction capital cost estimate includes the construction of a stand-alone gold recovery (to carbon) facility, phase 1 of the heap leach pad construction and all necessary site infrastructure to bring the mine into production.

Preliminary site layouts for the project were completed and included suitable areas for life of mine leach pad areas, required pond volumes and other infrastructure items in addition to the process plant and crushing operations. Cost estimates are primarily based on cost factors/data obtained from the company's recent project construction experience in Mexico including the Santana gold project completed in 2021. To reduce initial capital requirements all open-pit mining operations and associated capital costs are the responsibility of an independent mining contractor. In addition, the company plans to utilize (with some modifications) an existing crushing plant purchased previously and personnel will stay in the local municipality eliminating the requirement for any significant mine site camp facilities.

Operating cost estimates

The total unit operating cost for the project is estimated at $6.66 (U.S.)/tonne of mineralized material (including general and administrative costs (G&A)). Operating costs were developed based on first principles where possible including estimated staffing levels, reagent consumption and power requirements. Unit costs and allowances for things such as G&A and maintenance supplies are based on data from current Minera Alamos facilities (Santana gold project) and other similar heap leach operations in Mexico. Power requirements for the process operation (excluding crushing) were estimated based on operating equipment motor sizes and plant availability; costs assume diesel generation with a delivered diesel fuel cost of $1.10 (U.S.)/litre (approximately 30 U.S. cents/kWh (kilowatt-hour)). Power for the crushing system is assumed to be taken from the nearby power grid at a price of 13 U.S. cents/kWh. An overall contingency of 20 per cent was applied to the operating cost totals to account for additional cost items such as outside contractors, laboratory consumables and vehicle fuel requirements.

All mine operating activities are assumed to be the responsibility of a third party mining contractor. Contractor rates include drilling, blasting and transportation of the waste/ore. Costs for the company mine services group were prepared separately and included. LOM operating costs are summarized in the "Operating costs (opex)" table. Actual annual costs in the economic models for the project will vary based on the proposed annual mine schedule and utilize the unit costs detailed below.

Mineral resources

As part of the PEA, an updated Cerro de Oro project mineral resource estimate was completed to reflect a higher gold price of $1,700 (U.S.)/ounce, which is more reflective of the three-year trailing average price. This reflects a change in the reasonable prospects for eventual economic extraction due to the current market conditions. Other than the change to the gold price assumption, the remainder of the estimate methodology remain identical to that utilized in the previous NI 43-101 report "Mineral resource estimate for the Cerro de Oro project" by Scott Zelligan, PGeo, dated Nov. 16, 2020, that is currently available on SEDAR. The block model was constrained using an economic pit shell at the updated gold price resulting in the new and current mineral resource estimate, as presented in the "Cerro de Oro project, estimate of mineral resources" table.

The mineral resource estimate has been wholly classified as inferred. The estimate represents the oxidized portion of the Cerro de Oro deposit. Although drill spacing is locally sufficient for indicated classification, there remain necessary revisions and updates to the geological logs; better definition of the limit between the oxides and fresh rock; understanding of mineralization controls; and bulk density measurements. The reported inferred resources are estimated with an average drilling grid of approximately 85 metres by 85 m.

The "Sensitivity of mineral resource to gold price" table shows the open pit constrained mineral resource sensitivity to the gold price. The reader should be cautioned that the figures provided in the "Sensitivity of mineral resource to gold price" table should not be interpreted as a mineral resource statement. The reported quantities and grade estimates at different gold prices are presented for the sole purpose of demonstrating the sensitivity of the resource model to the selection of a reporting gold price. The gold price of $1,700/ounce that was used to report the mineral resources (the base case) for Cerro de Oro is highlighted in bold. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Mining

The Cerro de Oro project is planned as a conventional open pit operation that will utilize 100-tonne haul trucks and front-end loaders. Material will be drilled and blasted, before being loaded and hauled to a waste dump, crusher, or direct to the heap leach pad. Mining activities will be completed by a contractor who will supply all of the required mine equipment and personnel working under the supervision of the company's technical staff.

Using a nested pit shell that is based on a gold price of $1,500/ounce and the economic parameters applied to the resource estimate as a guide, a full open-pit mine plan was completed. Upon completion of the ultimate pit designs, a check was completed that considered both revisions to the company's gold price forecast and its operating cost estimates for the project. A LOM gold price of $1,600/ounce was selected for use in the final mine planning economics. Based on available metallurgical data for the project and an evaluation of the host rock lithologies it was assumed that the majority of mineralization mined will be placed directly on the heap leach as run-of-mine (ROM), with approximately 30 per cent of the mineralization reporting to the crusher for size reduction (equivalent to crushing cut-off grade of approximately 0.4 to 0.45 g/t Au).

The mine production schedule anticipates that mining starts at the beginning of year 1 following the completion of all required earthworks activities such as road, dump and starter leach pad construction. Due to the low LOM strip ratio (0.30:1) and the size of the mineralization, the PEA did not adjust the planned mining physicals to account for mining losses or dilution (magnitude of losses likely similar to dilution). Mine planning efforts going forward will be aimed at cut-off grades and the smoothing of the mining activities later in the mine life that may provide additional economic upside for the project. Over the life of mine of 8.2 years, a total of 59 Mt of mineralization grading 0.37 g/t gold (approximately 700,000 ounces of contained gold) are anticipated to be mined.

Pit bench heights were selected at five-metre intervals in order to provide good ore/waste selectivity although use of larger bench heights in zones of primarily waste and on final open pit walls should be considered as part of future optimization studies. Overall average pit slopes with the benches/ramps in place range between approximately 30 to 43 degrees in the north pit and 34 to 38 degrees in the south pit.

It is assumed that all drilling/blasting/loading/hauling operations at the project are planned to be completed by an open-pit mining contractor. Mining costs were developed for the project utilizing recent Mexican cost information for similar heap leach operations and as part of the company's recent work at its Santana mine. Contractor availability in northern Mexico is currently high and rates are competitive. An additional cost was applied to the mineralized material to account on average for longer hauls to the heap leach pads over the mine life. Mine planning and supervision activities will be performed by company personnel; these costs are excluded from contractor rates.

Processing

The process flow sheet for the Cerro de Oro project is similar to that utilized by the company at its recently constructed Santana gold heap leach project. Metallurgical test work completed to date on samples from the Cerro de Oro deposit indicate that the gold mineralization is well disseminated throughout the host rock and that the oxide mineralization responds positively to cyanidation. Residual gold contents following leaching in multiple series of bottle roll tests (conventional and coarse particle) appear to trend toward a typical range of ultimate values near 0.1 g/t Au. Leach kinetics were generally rapid in nature with low to moderate reagent consumption (lime and cyanide). A limited number of column tests have been completed resulting in leach extractions consistent with those observed from bottle roll studies. Additional studies have been recommended to better define leaching parameters and any variability that may exist between the different mineralized zones and lithologies.

The process design for the Cerro de Oro gold project includes crushing of high-grade material to less than three-fourths of an inch to seven-eights of an inch (30to 35 per cent of total with remaining low grade sent to leach pad as run-of-mine), a heap leaching pad, solution ponds and carbon column recovery of gold from pregnant leach solutions. The current design excludes carbon desorption and gold refining facilities as gold-loaded carbon will be shipped off-site for final dore production. The overall plant design was based on a nominal rate of seven million tonnes per year of mineralized material stacked to the leach pad at an average grade of 0.4 g/t Au. Sufficient excess capacity is included in the design to allow for expected annual variations in mine production around these nominal values. Base case leach solution flow rate to the carbon column recovery area was set at 800 cubic metres per hour, with allowances to expand to 1,200 cubic metres per hour to accommodate increases in annual production rates and/or an expansion in the overall project resources.

The overall Cerro de Oro gold recovery facilities consist of the following unit operations and support facilities:

  • Low-grade run-of-mine material leach pad loading via direct truck dump;
  • Two-stage crushing (jaw and cone) and screening operations for higher grade mine material with conveyor/stacker transport to leach pad;
  • Lined heap leach pad area sufficient to handle current life-of-mine resource (40 to 50 per cent constructed initially as phase 1 with subsequent expansions);
  • Lined leach solution ponds adjacent to the leach pad -- barren, pregnant and emergency overflow solution capacity;
  • Four trains of four-stage carbon in columns with area to expand to six trains;
  • All required process pumping and loaded and barren carbon handling;
  • Reagent preparation and storage facilities;
  • Metallurgical laboratory (necessary production samples only);
  • Utilities including water supply system (surface wells) and diesel power generation.

Infrastructure

Access

The Cerro de Oro project is accessible by road from the city of Saltillo in neighbouring Coahuila state, a driving distance of approximately 165 kilometres, about a two-hour drive. The exit to Melchor Ocampo is off Federal Highway 54, approximately five km northeast of the town of Concepcion del Oro. The site access road is approximately 2.5 km east of Melchor Ocampo and itself is a three-kilometre gravel road that provides access to the project site. All roads to the town are paved and in good condition.

Based on preliminary engineering a total of approximately 11 km of new access roads are required for initial site development and early mine production. Roads will consist of gravel surface suitable for the operation of mining trucks and general purpose vehicles. An allowance has also been included for some upgrading of existing roads including the widening of sections that pass through/near the project mining operations in order to better accommodate two-way truck traffic

Power

Details of the complete modifications to the existing crushing system previously purchased by the company have not yet been completed but the arrangement will include a truck dump hopper/feeder, two stage crushing and screening, as well as required transfer conveyors and area sufficient for short term material stockpiles. It is planned that grasshopper-style conveyors will be utilized to transfer crushed rock to a mobile stacker located at the leach pad for final stacking/placement. In total, an allowance has been included for a connected load of approximately 1.5 MW (megawatts) to power all the major crusher and transfer equipment unit operations. An existing two-megawatt backup diesel generator was acquired as part of the overall used crushing circuit equipment and will be installed as a backup.

The nearest federal electricity (CFE) connection to the planned crushing area is a local line approximately 0.5 km to the east. The main line supplying the town of Melchor Ocampo runs along the primary access road to the town approximately two km to the south. The company is currently discussing the project requirements with the CFE to confirm sufficient capacity exists within the local network and to confirm acceptable locations for connection to the power grid.

It is assumed, for the foreseeable future, that all power required for the Cerro de Oro gold leaching and recovery plant operations will be generated at site by diesel generators. The total maximum operating plant power load is estimated at 780,000 watts (actual draw will vary over LOM and as leach pad evolves), which will be supplied by a single diesel generator unit (one MW). A backup generator (300,000 to 400,000 watts) will also be installed to manage basic requirements during maintenance periods or periods of reduced solution pumping. Generators are to be located within close proximity to the processing plant area, so transmission line requirements will be negligible. Wherever possible, smaller power consumers not associated with the processing plant (that is, test wells and local offices) will be self-contained with local diesel hydraulic/electric generation.

At current fuel prices in Mexico diesel generation is equivalent to an electric power cost in the range of 30 cents/kWh, which has been used for budgeting purposes in the PEA. Should the project resources continue to grow further studies would be warranted to investigate the economics of extending grid power to the process plan area.

Water management

The sources of process water available for the Cerro de Oro project consist of groundwater wells. In mid 2022, a hydrogeological consulting group was retained by the company to perform reviews of the Cerro de Oro area and to better understand the regional water flows around Melchor Ocampo. A series of reconnaissance visits were completed to review available regional geology maps for the area and to make local field investigations (including electromagnetic geophysical surveys -- TEM). Seven high-priority targets have been selected by the company for test drilling down to a maximum depth of 300 metres. The majority of the target areas are located north of the planned leach pad/processing plant facilities and at a distance of less than five km.

Other infrastructure

Preliminary estimates were completed to calculate the total amount of material to be excavated during the overall site preparations. Of this total, approximately 40 per cent will be moved short distances and utilized as compacted fill. The remainder will be moved to one of the site waste storage dumps.

Other general infrastructure to be constructed at the project includes offices, powder magazines, lab and warehouse facilities. No capital allowance has been made for the truck shop area as these facilities are typically provided by the mine contractor as part of the contract for mining operations. Simple buildings are planned with a combination of trailers/container units and locally constructed concrete block structures. Only very basic lab services are planned for the site focusing exclusively on production samples (mine blast holes and process solutions). Other samples/test work/analysis to be completed for the project will be completed at third party facilities located in Zacatecas or Durango.

General administration

The PEA model is based on the assumption that Minera Alamos will provide overall site management, technical support and surface and processing plant personnel. Mining and crushing activities will be completed by contractors and all personnel other than high level supervision and planning are included in the contractor costs.

It is anticipated that wherever possible basic operations labour will be sourced locally from the Melchor Ocampo area or other small nearby villages. Management and more skilled personnel that are not locally available can be sourced from the Concepcion de Oro general area, which is a local centre for a number of mining operations. Minera Alamos will provide basic transportation services (by road) for operations personnel.

Minera Alamos plans to maintain a local operations office in Melchor Ocampo and will have some accommodation facilities in the town that can be utilized by visiting management personnel and outside consultants.

Permitting status

No permits have been granted for the development of the Cerro de Oro project. The company intends to advance efforts related to the application for these documents prior to a decision being made to develop the project. The primary applications under consideration include:

  • Environmental impact statement (manifestacion de impacto ambiental, or MIA);
  • Technical justification study (estudio tecnico justificativo, or ETJ), which includes the change of land use (cambio de uso de suelo, or CUS).

When appropriate, the company will submit these applications to the appropriate government agencies, including the Secretariat of Environment and Natural Resources (SEMARNAT).

A prerequisite for these submissions is the completion of a surface agreement(s) that covers the development areas of interest. Agreements were finalized by the company in 2022 and work is currently under way to prepare the MIA/ETJ application documents. In total, the company is in possession of two surface rights rental agreements covering a period of 25 years -- 656 hectares from the Melchor Ocampo municipality and an adjacent 160 hectares from the local Ejido.

Following the completion of the ETJ/MIA process a number of other registrations and local/state permits are required in advance of various site development stages and the start of commercial production. These include:

  • Water use -- Comision de Agua (National Water Commission or CONAGUA). The company initiated the hydrogeological studies required for this permit in 2022;
  • Explosives use -- covers projected explosives requirements and design of explosives storage facilities;
  • Exploration permits -- as required when surface disturbances are created for site drilling purposes;
  • Construction permits -- obtained from the local municipality.

Sensitivity analysis

A sensitivity analysis was conducted on the base case (after-tax) NPV for the project using the following variables -- metal price/recovery, initial capex (capital expenditure) and total opex. The "Analysis (5-per-cent discount/after-tax)" table summarizes the sensitivity analysis results. As illustrated, the project NPV is most sensitive to changes in metal price/recovery and less sensitive to initial capex and opex.

Project opportunities

The PEA identifies several project opportunities to further enhance project economics. These include:

  • The known zones of gold mineralization appear to remain open both laterally and at depth;
  • Additional metallurgical test work should allow for a more complete understanding of the gold recovery versus crush size relationships for different areas of the deposit and potential improvements in overall gold extraction via optimization of the processing parameters;
  • Based on preliminary test work there appears to be potential to leach sulphide mineralization at depth. Further metallurgical work should continue to evaluate the amenability of leaching this material, followed by additional drilling to better delineate the extents of these zones if warranted;
  • Additional mine planning optimization studies to evaluate opportunities to expand annual production rates and better optimize production phasing;
  • Haul road optimization to attempt to reduce distances to the planned leach pads.

Project recommendations

The PEA identifies several recommendations to advance the development of the project. These include:

  • Topographic work to provide additional accurate positions and directional details for historical drill holes;
  • Infill drilling program (phase 1) for resource modelling purposes and to collect samples for additional metallurgical test work as well as in situ rock density studies;
  • Preparation of plans for an additional phase of exploration drilling aimed at defining disseminated sulphide extensions of known oxide mineralization;
  • Geotechnical site investigations to obtain a better understanding of existing ground conditions for open pit slope, waste dump and leach pad design purposes;
  • Further pit design optimization to examine access road development alternatives, open pit phasing to maximize mined mineralization release and further smoothing of the production profile later in the mine life;
  • Additional metallurgical optimization studies (coarse bottle roll and columns) to examine crush size/gold recovery relationships and variability for primary lithological zones within the project mineralization;
  • Sulphide mineralization leach studies;
  • Complete environmental baseline studies for preparation of MIA/ETJ application;
  • Hydrogeological survey of the project area to prioritize locations for process water access.

Qualified person statements

The 2022 PEA was conducted by the following qualified person contributing to their respective sections. All qualified person (QP) are as defined under Canadian National Instrument 43-101. All of the QPs are independent of the company, pursuant to National Instrument 43-101. The listed qualified person have reviewed the data contained in this news release and verified that it is accurately disclosed: Scott Zelligan, PGeo, independent resource geologist; Lawrence Segerstrom MSc (geology), CPG; Peimeng, Ling, PEng; Alex Duggan, PEng; Toren Olson, PG.

Darren Koningen, PEng, a qualified person as defined under Canadian National Instrument 43-101, is responsible for the other technical information (information not directly related to the PEA) in this news release.

About Minera Alamos Inc.

Minera Alamos is a gold production and development Company undergoing the operational start-up of its first gold mine that produced its first gold in October, 2021. The company has a portfolio of high-quality Mexican assets, including the 100-per-cent-owned Santana open-pit, heap-leach mine in Sonora that is currently going through its operational ramp up. The 100-per-cent-owned Cerro de Oro oxide gold project in northern Zacatecas that has considerable past drilling and metallurgical work completed with plans to enter the permitting process. The La Fortuna open pit gold project in Durango (100-per-cent-owned) has an robust and positive preliminary economic assessment (PEA) completed and the main federal permits in hand. Minera Alamos is built around its operating team that together brought three mines into successful production in Mexico over the past 13 years.

The company's strategy is to develop very low capex assets while expanding the projects' resources and continuing to pursue complementary strategic acquisitions.