Overview
-
Pre-production capital requirements $261 million
-
Mill throughput of 2 million tonnes of ore per annum- 6,000 tonnes per
day
-
Life of Mine Production: 239,000 tonnes of copper concentrate, 122,000
tonnes of lead concentrate
and 770,000 tonnes of zinc concentrate
-
Total Net Smelter Return Revenue $1,246 million
-
Further metallurgical studies planned
-
Excellent exploration upside with additional drilling plans on adjacent
Camel Back Claims
|
VANCOUVER, June 5, 2013 /CNW/ - El Nino Ventures Inc. ("ELN" and the
"Company") (TSX.V: ELN; OTCQX: ELNOF Frankfurt: E7Q) is pleased to
announce the results of an NI 43-101 Preliminary Economic Assessment ("PEA") for the Murray Brook polymetallic massive sulfide deposit, New Brunswick
(the "Project"). The results of the PEA demonstrate the potential
technical and economic viability of establishing a new mine and mill
complex on the Murray Brook property. The projected cash flows
indicate an after-tax NPV at a 5% discount rate of $96.4 million, an
IRR of 11.4%, and a payback period of 5.4 years (see table 1). An NI
43-101 Technical Report will be filed on SEDAR within 45 days of the
date of this press release.
Harry Barr, ELN's Chairman & CEO commented, "The results of the PEA
clearly indicate that there is an indicative basis for a mining project
at Murray Brook. There is excellent potential to further enhance the projected economics
of the project, through continued refinements in metal recoveries as
well as the potential to augment existing resources by achieving an
exploration success on the adjacent Camel Back claims. With forecasts of increased metal demand and dwindling supply, the
positive PEA results for the Murray Brook project provide ELN
shareholders with the potential to benefit from the predicted upward
trend in zinc prices over the next few years".
Unless otherwise noted, all amounts in this press release are expressed
in Canadian currency. The PEA is prepared for 100% ownership of the
project revenues and expenditures. As noted below, ELN holds a 35%
interest in the project. The PEA includes Inferred mineral resources
that are considered too speculative geologically to have the economic
considerations applied to them that would enable them to be categorized
as mineral reserves, and there is no certainty that the PEA will be
realized.
Table 1- Summary of 2013 Murray Brook PEA Results
|
NPV (5%)
|
$96.4
|
Million
|
|
NPV (7%)
|
$59.7
|
Million
|
|
IRR
|
11.4%
|
|
|
Payback
|
5.4
|
Years
|
|
Total LOM* Capital
|
$334.8
|
Million
|
*Life of Mine
The PEA was prepared by P&E Mining Consultants Inc. and the full results
of the study will be disclosed in a NI 43-101 Technical Report within
45 days of the date of this press release. The PEA was prepared under
the supervision of Eugene Puritch, P. Eng. of P&E Mining Consultants
Inc. Mr. Puritch is an independent QP in accordance with NI 43-101 and
has reviewed and approved the technical information in this release.
The main conclusions from the PEA follow below.
Mining and Mineral Processing
Life of Mine production on a diluted and extracted basis for the Murray
Brook potentially economic portion of the resource estimate is planned
to be as follows:
Table 2 - Murray Brook Potentially Economic Portion of the Resource
Estimate
| Classification | Tonnes | Zn% | Cu% | Pb% | Ag g/t | Au g/t |
| Measured |
12,075,000
|
2.75
|
0.37
|
0.96
|
38.8
|
0.47
|
| Indicated |
6,635,000
|
1.98
|
0.50
|
0.78
|
36.1
|
0.66
|
| Meas. & Ind. |
18,710,000
|
2.48
|
0.42
|
0.90
|
37.9
|
0.53
|
| Inferred |
240,000
|
1.18
|
1.46
|
0.41
|
24.7
|
0.39
|
|
|
| (1) | Potentially economic portion of the mineral resource estimate which are
not mineral reserves do not have demonstrated economic viability. This
estimate of mineral resources may be materially affected by
environmental, permitting, legal, title, taxation, sociopolitical,
marketing, or other relevant issues. |
|
|
| (2)
| The quantity and grade of reported potentially economic Inferred
resources in this estimation are uncertain in nature and there has been
insufficient exploration to define them as an Indicated or Measured
potentially mineable mineral resource and it is uncertain if further
exploration will result in upgrading them to an Indicated or Measured
potentially economic mineral resource category. |
|
|
| (3) | The potentially economic portion of the mineral resource in this press
release was estimated using the Canadian Institute of Mining,
Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and
Reserves, Definitions and Guidelines prepared by the CIM Standing
Committee on Reserve Definitions and adopted by CIM Council. |
The PEA assumes the start of the open pit mining operations at an
average annual process plant production rate of 2,000,000 tonnes per
annum over a mine life of approximately 9.5 years. The envisaged mining
operation is a conventional open pit. Mining operations will reach a
sustained total annual material movement of 11.6 million tonnes using
11.5 m3 diesel hydraulic excavators, 90 tonne haulage trucks, and track mounted
diesel powered drill rigs with up to 100 mm diameter blastholes drilled
on 6 metre high benches.
The mined material will be processed at a new 6,000 tonnes per day
flotation plant located on the Project site. Three concentrates will be produced: 1) copper-silver; 2) lead-silver;
and 3) zinc-silver. It is anticipated that the concentrates could be
processed at the nearby Belledune Smelter or other suitable facilities.
Site Infrastructure
The Project will benefit from infrastructure, services and skilled
labour available in the Bathurst Mining Camp. The Murray Brook Project
site is located 60 km west of the city of Bathurst and is accessible
year-round from paved Provincial Highway 180 and a 6.5 km gravel access
road. Project site infrastructure is anticipated to include:
-
Plant site and haul roads;
-
Administration buildings and assay lab;
-
Mine maintenance garage, warehouse and fuel storage facilities;
-
Fresh water supply and sewage treatment; and
-
Lined tailings storage area
The proposed Murray Brook Project mill and mine site is ideally located
on the access road to the open pit area. The proposed processing plant site is located on a ridge overlooking a
valley about 100 metres below. Several lateral ridges form natural
containment dykes for at least two sides of a tailings management
facility. Power to the site will be supplied by a 12 km long
transmission line connecting to the Caribou Mine site and provincial
grid.
The labour force for the construction and operation of this project is
anticipated to be drawn from the Bathurst area. The labour pool in this
area is highly skilled and experienced in construction projects and
mining operations.
Financial Assumptions and Results
Total operating costs during the Life of Mine is illustrated in Table 3:
Table 3-Projection of total operating costs during the Life of Mine,
Murray Brook Project
|
Mining Cost
|
$/t material
| $2.30 |
|
Processing Cost
|
$/t ore
| $14.25 |
|
G&A
|
M$/year
| $2.50 |
Capital costs are categorized as Initial Project Capital and Sustaining
Capital. Initial Project Capital consists primarily of mining
equipment, process plant and ancillary plant construction, initial
tailing storage, facility construction, an allowance for water
treatment, and local infrastructure. Sustaining capital consists of
further additions to mining equipment during production and
environmental and closure costs.
Table 4-Initial Project and Sustaining Capital of Murray Brook Project
|
Total ($'000) |
| Initial Project Capital |
|
Mine Pre-Stripping
| $8,707 |
|
Mining Capital Cost
| $33,706 |
|
Process Plant
| $104,184 |
|
Infrastructure
| $35,000 |
|
Indirects
| $44,000 |
|
Contingency
| $35,257 |
| Total Initial Project Capital | $260,854 |
| Sustaining Capital |
|
Mine
| $10,137 |
|
Process Plant
| $2,100 |
|
Environmental & Reclamation
| $60,800 |
|
Contingency (sustaining)
| $927 |
| Total Sustaining Capex | $73,964 |
| Total Capital | $334,818 |
Metal prices used in the PEA are based on the April 30, 2013 three year
trailing prices which are listed in Table 5 below.
Table 5-Metal prices used in this study
| Metal | Prices (US$) | Unit |
|
Copper
|
3.70
|
lb
|
|
Lead
|
1.00
|
lb
|
|
Zinc
|
0.94
|
lb
|
|
Gold
|
1,540
|
oz
|
|
Silver
|
30.09
|
oz
|
Exchange Rate: $US:$CAD = 1
Project and Exploration Upside
Further technical studies on the Murray Brook Project will focus on
additional metallurgical studies designed to evaluate potential
techniques of improving metal recoveries. The first step is a small
pilot plant project proposal to test three to five tonnes of drill core
material.
The largest impact on the potential value of the Murray Brook Project is
likely to be achieved by increasing the mineral resource base available
for mining, thereby increasing the mine life and (or) annual mill
throughput. Excellent potential exists for additional discoveries along
and adjacent to the favourable geological horizon which extends from
the former Restigouche Mine to the west of the Murray Brook deposit
deposit to Trevali's Caribou deposit 11 km to the east. An exploration
success on this stretch of productive stratigraphy could significantly
increase the scale of the Murray Brook Project prior to development. A
2,000 metre exploration program is proposed to drill test five priority
geophysical and geochemical anomalies this summer.
Qualified Persons Statement
The PEA was prepared under the supervision of Eugene Puritch, P. Eng. of
P&E Mining Consultants Inc. Mr. Puritch is an independent QP in
accordance with NI 43-101 and has reviewed and approved the technical
information in this
release.The information in this release was reviewed
by Dr. William Stone, Executive Vice President of
Exploration of ELN and a Qualified Person as defined by NI43‐101.
About El Niño Ventures Inc. Bathurst Projects
El Niño Ventures Inc. has two active projects in the Bathurst Mining
Camp;
1. Murray Brook Project
Murray Brook property is located 60 km west of Bathurst and a portion of
the property is underlain by the Murray Brook polymetallic massive
sulfide deposit. The property is supported by excellent nearby
infrastructure, including paved roads, grid electricity and communities
to provide goods, services and skilled labour (Figure 1).
Figure 1- Murray Brook and Camel Back Location map in the Bathurst
Mining Camp
(http://www.elninoventures.com/s/NewsReleases.asp?ReportID=586536)
ELN and Votorantim Metals Canada Inc. "VMC" (who is the operator of the
joint venture project) currently own 70% of the project, of which 35%
is held by each of the two parties. Under a purchase agreement signed
by VMC on August 28, 2012 with Murray Brook Minerals and Murray Brook
Resources Inc. (collectively the "Owners"), VMC acquired the right to
purchase the additional 30% of the Murray Brook Project from the
Owners. The purchase agreement between VMC and the Owners provides for
a series of staged payments totaling $6 million over a five year period
and provides for a 0.25% NSR payable to the Owners after one year of
commercial production.
VMC provided ELN the option to purchase an additional 15% in the
project as required by an underlying Amending Agreement dated September
30, 2010 between Xstrata Zinc (now Glencore Xstrata PLC), VMC and ELN
(see reference to the Tri-Party Agreement immediately below). ELN did
not elect to exercise the option and consequently at this time the
Joint Venture remains at VMC 65%: ELN 35%.
To date, more than 28,000 metres of drilling has been completed with
encouraging results. In February 2012, NI 43-101 resource estimation
was announced (see news release. The Technical Report is filed on SEDAR.com and also available on ELN's website. The new Preliminary Economic Assessment Report, PEA, will be filed on
SEDAR within 45 days of the date of this press release.
2. Bathurst Mining Camp Project ( Tri-Party Agreement) :
Consists of an initial 4,712 claims in the Tri‐Party Agreement with
Xstrata Zinc (now Glencore Xstrata) and VM Canada, whereby VM Canada
may incur exploration expenditures of $10 million over a period of 5
years to earn a 50% interest. VM Canada may further increase its
interest to 70% by spending an additional $10 million over two years.
Drilling and further exploration activities have been planned for 2013.
Votorantim Metals Canada Inc. Statement
Technical details in this news release were provided by VMC whose
professional geologists conduct operations consistent with mineral
industry best practices. VMC accepts no responsibility for this news
release or any inferences made from the technical details provided
herein.
About Votorantim Metals Canada Inc.
VMC is a subsidiary of Votorantim Metais is a company that is part of
the Votorantim Group that was founded in Brazil in 1918. The Votorantim
Group operates in twenty countries and has over 40,000 employees.
Votorantim Metais is the largest electrolytic nickel producer in Latin
America and one of the world's leaders in the production of zinc,
aluminum and nickel. Votorantim Canada Metals Inc. in conjunction
with Glencore Xstrata PLC and El Nino Ventures is operator of the
Bathurst Option and Joint Venture which is actively exploring for base
metal deposits within the Bathurst Mining Camp.
About El Nino Ventures Inc.
El Niño Ventures Inc. is an international exploration company, focused
on exploring for zinc, silver, copper, gold and lead in New Brunswick,
Canada and copper in the Democratic Republic of Congo ("DRC").
On Behalf of the Board of Directors
(signed)
Harry Barr
Chairman & CEO
El Niño Ventures Inc.
Neither the TSX Venture Exchange nor its Regulation Services Provider
(as that term is defined in the policies of the TSX Venture Exchange)
accepts responsibility for the adequacy or accuracy of this release.
Cautionary Note Regarding Forward Looking Statements. Note: This
release contains forward-looking statements that involve risks and
uncertainties. These statements may differ materially from actual
future events or results and are based on current expectations or
beliefs. For this purpose, statements of historical fact may be deemed
to be forward-looking statements. In addition, forward-looking
statements include statements in which the Company uses words such as
"continue", "efforts", "expect", "believe", "anticipate", "confident",
"intend", "strategy", "plan", "will", "estimate", "project", "goal",
"target", "prospects", "optimistic" or similar expressions. These
statements by their nature involve risks and uncertainties, and actual
results may differ materially depending on a variety of important
factors, including, among others, the Company's ability and
continuation of efforts to timely and completely make available
adequate current public information, additional or different regulatory
and legal requirements and restrictions that may be imposed, and other
factors as may be discussed in the documents filed by the Company on
SEDAR (www.sedar.com), including the most recent reports that identify important risk
factors that could cause actual results to differ from those contained
in the forward-looking statements. The Company does not undertake any
obligation to review or confirm analysts' expectations or estimates or
to release publicly any revisions to any forward-looking statements to
reflect events or circumstances after the date hereof or to reflect the
occurrence of unanticipated events. Investors should not place undue
reliance on forward-looking statements.
SOURCE: El Nino Ventures Inc.

<p> Tel: +1 604 685 1870 Fax: +1 604 685 8045<br/> Email: <a href="mailto:info@elninoventures.com">info@elninoventures.com</a> or visit <a href="http://www.elninoventures.com">www.elninoventures.com </a><br/> 650-555 West 12th Avenue, City Square, West Tower, Vancouver, B.C., Canada, V5Z 3X7 </p>