Mr. Jeff Quartermaine reports
PERSEUS MINING LIMITED: OPERATIONS AT EDIKAN GOLD MINE RESUMED
Ore-processing operations resumed at Perseus Mining Ltd.'s Edikan gold mine in Ghana on April 16, 2014, at approximately 5 p.m. GMT, seven days after a fire occurred in the cyclone nest of the plant while undergoing routine maintenance.
Perseus's managing director, Jeff Quartermaine, said that, following a thorough investigation into the cause of the fire and the company's response, work commenced on repairing fire damage.
"The effort put in by our on-site team to assess and carry out the repair work was impressive, and the fact that we were able to resume operations, as forecast, within seven days is a real credit to all of those involved," Mr. Quartermaine said.
"We have learned a lot of very valuable lessons, and the cost of repairs has been relatively modest."