07:56:03 EDT Thu 25 Apr 2024
Enter Symbol
or Name
USA
CA



Orezone Gold Corp
Symbol ORE
Shares Issued 95,683,698
Close 2015-04-27 C$ 0.43
Market Cap C$ 41,143,990
Recent Sedar Documents

Orezone Gold releases Bombore FS showing 24.4% IRR

2015-04-28 07:19 ET - News Release

Mr. Ron Little reports

OREZONE ANNOUNCES POSITIVE FEASIBILITY STUDY FOR BOMBORE

Orezone Gold Corp. has released the highlights of the independent feasibility study for its wholly owned Bombore gold project in Burkina Faso. The study envisions a shallow open-pit mining operation with a processing circuit that combines heap leaching and carbon-in-leach without any grinding to process the soft and mostly free digging oxidized ores. The 11-year mine plan, based on a mineral reserve using a $1,100 (U.S.) gold price, is designed to deliver higher-grade ore in the early years (0.88 gram per tonne over the first eight years of production at a strip ratio of 1:1). Lower-grade stockpiles will be processed in the final three years. The financial model with revenues based on a $1,250 (U.S.) gold price, yields a robust 24.4-per-cent after-tax internal rate of return to the company (based on 90-per-cent ownership, 10 per cent government) with a net present value of $196-million (U.S.) at a 5-per-cent discount rate. Project payback is estimated at 2.7 years with all-in sustaining costs averaging $678 per ounce. Initial capital is estimated at $250.0-million, including contingencies, all working capital and a $10.5-million credit for gold revenues generated during the preproduction period. Capital costs include the mining fleet, a much larger water storage reservoir and higher resettlement costs than envisioned in the March, 2014, preliminary economic assessment. Sustaining capital is estimated at $75.2-million, taking into account the additional three years of mine life and higher resettlement costs than estimated in the PEA. Total reclamation and closure costs are estimated at $22.5-million, including $8.7-million of heap rinsing costs expensed in year 12.

"The results of the study are compelling and the project benefits from size, location, low reagent consumption, rapid leaching kinetics and low all-in operating costs," said Ron Little, chief executive officer of Orezone. "Bombore is one of the largest and most advanced undeveloped gold deposits in the region that lends itself to phased development. The initial 11-year phase requires less capital and has lower operating costs to process the shallow and softer oxidized ores. A second phase, at slightly higher gold prices (greater than $1,400 (U.S.)) could expand the standard CIL circuit with the addition of grinding to process the well-defined sulphide resource (73 million tonnes at 1.1 grams per tonne for 2.6 million ounces)."

The study was completed by Kappes, Cassiday and Associates of Reno (processing and study manager), Golder Associates Inc. of Reno and Montreal (geotechnical), RPA Inc. of Toronto (reserves and mining), and WSP Canada Inc. of Montreal, in conjunction with Socrege and BEGE of Burkina Faso (social and environmental).

Summary of financials

The base case assumptions include mineral reserves using an average gold price of $1,100 per ounce and revenues based on $1,250 per ounce along with current prices for fuel, reagents and labour. Capital is based on quotes received from potential equipment and service providers between the third quarter of 2014 to present.

                               BASE CASE HIGHLIGHTS

Mine plan contained gold at $1,100 Au (ounces)                   1,465,000
Average gold grade (g/t)                               LOM 0.76/years (1-8)
                                                                      0.88
Processing throughput (Mt/yr)                                          5.5
Mine life (years)                                                     10.7
Average annual gold production (ounces)             LOM 116,000/years (1-8)
                                                                   135,000
Gold production (ounces recovered)                               1,275,000
Waste to ore strip ratio (incl. prestrip, water OCR)              1.07:1.0
Gross revenue ($M) using $1,250 Au                                   1,589
Direct cash cost ($/oz)                                                554
Operating cost ($/oz)                                                  603
Initial capital ($M) (incl. $10.5M capital
credit)                                                              250.0
Sustaining capital ($M)                                               75.2
Closure costs ($M) (incl. $8.7M of expensed
costs)                                                                22.5
Attributable to Orezone (1)
NPV after tax (0%) ($M)                                              323.9
NPV after tax (5%) ($M)                                              196.1
IRR after tax                                                        24.4%
Attributed to government (2)
NPV (0%) with taxes ($M)                                             214.8
NPV (5%) with taxes ($M)                                             152.7

(1) Represents Orezone's Burkina Faso subsidiary cash flows net of 
royalties and local taxes.
(2) The government of Burkina Faso benefits from its 10-per-cent free 
carried interest, royalties (4-per-cent NSR), corporate tax (18.3 per cent)
and withholding taxes.
Exchange rates: U.S. dollars to CFA francs: 550; euros to U.S. dollars: 
$1.19; euros to CFA francs: 655.957.
Fuel price delivered to site (U.S. dollars per litre): diesel $1.20; HFO 
77 cents.

The mineral resource and mineral reserve

The mineral reserve estimate prepared by RPA, is based on the 2013 mineral resource estimate prepared by SRK Consulting (Canada) Inc., which includes 139.9 million tonnes of measured and indicated resources grading 1.01 grams per tonne for 4.6 million ounces plus 18.4 million tonnes inferred resources grading 1.22 grams per tonne for 700,000 ounces. The study minable reserve is limited to only the measured and indicated near-surface saprolite (oxide) and transitional (semi-oxidized) resources to an average depth of 45 metres.

The mineral resource estimate consists of three separate block models:

  • The North model, which consists of the KT, Maga, CFU, OCR and P8P9 zones;
  • The South model, which consists of the P11, Siga E and Siga W zones;
  • The Southeast model, which is to the south and southeast of the South model and consists of the P16 and P17 zones.

 MINERAL RESOURCE ESTIMATE -- SRK CONSULTING (CANADA) INC., APRIL 26, 2013

                       Measured mineral  Indicated mineral Inferred mineral
                           resource          resource          resource
                 Cut-              Cont-             Cont-             Cont-
                  off   Ton-       ained  Ton-       ained  Ton-       ained
                 gold   nage Grade  gold  nage Grade  gold  nage Grade  gold
Category          g/t     Mt   g/t   koz    Mt   g/t   koz    Mt   g/t   koz

North
Laterite/oxide   0.45  13.57  0.95   417 14.20  0.82   375  2.04  0.88    57
Transitional     0.45   9.22  0.93   275  5.84  0.92   173  0.79  1.00    25
Fresh            0.50  22.04  1.00   711 11.98  1.29   497  4.42  1.63   232
                       -----  ---- ----- -----  ---- -----  ----  ----   ---
Subtotal               44.83  0.97 1,402 32.02  1.02 1,046  7.25  1.35   315
South
Laterite/oxide   0.45   8.11  0.94   246  4.53  0.86   125  1.66  0.89    48
Transitional     0.45   7.49  0.89   214  2.97  0.96    92  1.35  0.96    41
Fresh            0.50  20.58  1.02   674 15.26  1.19   584  5.46  1.26   222
                       -----  ---- ----- -----  ---- -----  ----  ----   ---
Subtotal               36.17  0.98 1,134 22.76  1.10   801  8.46  1.14   311
Southeast
Laterite/oxide   0.45   0.24  1.33    10  0.37  1.05    12  0.30  0.97     9
Transitional     0.45   0.25  1.53    12  0.34  0.97    11  0.24  0.97     7
Fresh            0.50   1.53  1.44    71  1.32  1.43    61  2.18  1.15    81
                       -----  ---- ----- -----  ---- -----  ----  ----   ---
Subtotal                2.03  1.44    94  2.02  1.28    83  2.71  1.12    97
Combined
Laterite/oxide   0.45  21.92  0.95   673 19.10  0.84   513  4.00  0.89   115
Transitional     0.45  16.96  0.92   501  9.14  0.94   275  2.37  0.97    74
                       -----  ---- ----- -----  ---- -----  ----  ----   ---
Lat/ox/tr total  0.45  38.88  0.94 1,174 28.24  0.87   789  6.37  0.92   189
Fresh            0.50  44.14  1.03 1,456 28.55  1.24 1,142 12.05  1.38   534
                       -----  ---- ----- -----  ---- -----  ----  ----   ---
Total all
material               83.03  0.99 2,630 56.79  1.06 1,930 18.42  1.22   723
                       -----  ---- ----- 
Total M+I all
material              139.82  1.01 4,560
                      ------  ---- ----- 
Total M+I
oxidized               67.12  0.91 1,963

(i) Mineral resources are not mineral reserves and do not have a
demonstrated economic viability. All figures have been rounded to reflect 
the relative accuracy of the estimates. The gold price of $1,400 (U.S.) and 
the cut-off grades from the previous resource estimation (2012) have been 
retained for comparison purposes. Reported within conceptual open-pit shells 
optimized considering a carbon in leach CIL process option.

For the mineral reserve estimate, RPA developed reserve block models, for each of the three resource block models, by applying modifying factors for conversion of mineral resources to mineral reserves. Those factors included among others, weathering profiles, operating costs, metallurgical recoveries, mining dilution and extraction, and pit slopes.

               MINERAL RESERVE ESTIMATE -- RPA, MARCH 20, 2015

                       Proven             Probable       Proven and probable
                 Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
Category             Mt   g/t    koz     Mt   g/t    koz     Mt   g/t    koz

North             25.32  0.77    627  15.11  0.69    333  40.43  0.74    960
South             12.96  0.81    339   6.15  0.92    173  19.13  0.80    491
Southeast          0.18  1.17      7   0.18  1.18      7   0.36  1.18     14
                  -----  ----    ---  -----  ----    ---  -----  ----  -----
Total             38.48  0.79    973  21.44  0.71    493  59.92  0.76  1,465

CIM definitions were followed for mineral reserves. Mineral reserves are estimated using a variable gold cut-off grade based on ore type and location; estimated cut-off grades range from 0.30 gram per tonne to 0.45 gram per tonne gold. Mineral reserves are estimated using an average long-term gold price of $1,100 (U.S.) per ounce. A minimum mining width of five metres was used. Bulk density is estimated in the mineral resource model by block; the average density of ore is 1.8 tonnes per cubic metre. Numbers may not add due to rounding. Mineral reserves are included in the mineral resource.

Estimated annual gold production

The study assumes during years 1 through 8 an average annual mining rate of 13.9 million tonnes, including 5.5 million tonnes of ore. The ore is composed almost equally of plus-or-minus-212-micron material and is processed via the heap leach pad (plus-212-micron) and CIL (minus-212-micron) circuits. Some gold is recovered during the preproduction period as a result of mining and processing the ore contained within the water storage facility (OCR). During years 9 to 11 ore is only processed from the lower-grade stockpiles.

                                AVERAGE PRODUCTION

Year         -1    1    2    3    4    5    6    7    8    9   10   11 Total

Gold (Koz) 11.1  186  168  146  135  135  112  115   89   65   65   48 1,275
Grade
(g/t)      0.45 1.21 1.09 0.95 0.88 0.87 0.73 0.75 0.58 0.42 0.42 0.42  0.76

          SUMMARY OF OPERATING COSTS (EXCLUDING PREPRODUCTION PERIOD)

                               Total costs     Average cost     Average cost
Category                                $M    $/t processed             $/oz

Mining                                 299             5.06              234
Processing                             293             4.97              230
General services                       111             1.88               87
Transport and refining                 3.2             0.05              2.5
Cash cost                              706            11.96              554
Royalties                               63             1.07               50
                                     -----           ------             ----
Total cash cost                        770            13.03              603

Initial project capital cost estimates

Initial capital costs are based on quotes of equipment and services from potential providers.

                    INITIAL PROJECT CAPITAL COST ESTIMATES
                       (in millions of U.S. dollars)

Project capital area                                                    
Infrastructure                                                        $  7.5
Power plant                                                              7.8
Mining and support equipment                                            24.8
Process plant (incl. water system)                                      98.7
Indirects (i)                                                           14.1
Resettlement                                                            10.3
EPCM, commissioning and owner's cost (ii)                               29.3
Preproduction (i) (w/OCR and preproduction gold credit(iii))            30.5
Working capital                                                         10.2
Contingencies                                                           16.7
                                                                      ------
Total initial capital costs                                           $250.0

(i) Including contingency
(ii) Excluding VAT
(iii) Gold credit is for gold produced during the preproduction period of
commissioning equipment and amounts to approximately 8,400 ounces.

                SUSTAINING CAPITAL AND CLOSURE COST ESTIMATES
                       (in millions of U.S. dollars)

Project sustaining and closure capital area                               
Mining and G&A                                                        $ 23.1
Plant and nested tails                                                  36.1
Resettlement                                                             9.9
Contingencies                                                            6.1
                                                                      ------
Total sustaining capital costs                                          75.2
Reclamation and closure(i)                                              13.8
                                                                      ------
Total sustaining and closure capital                                  $ 89.0

(i) Total closure cost estimated at $22.5-million; $8.7-million of expensed 
costs for heap rinsing not included in closure capital as gold production is 
associated with the process.

Sustaining capital costs were estimated on the basis of quotes on equipment from potential providers. Taxes and freight are included along with the individual items. The closure and reclamation plan includes work to be conducted from the closure of the mine at the end of operating activities, as well as progressive rehabilitation work during the life of the mine. The goal is to return the site to a satisfactory state as quickly as possible in terms of reducing the risks for health and safety, controlling erosion, and developing a profile compatible with the future uses of the site.

Total LOM reclamation and closure costs are estimated to be $22.5-million including $8.7-million in expensed operating costs for heap rinsing in year 12. The additional $13.8-million in capital and $8.7-million in expenses are included in the LOM AISC estimate of $678 per ounce. An estimated equipment salvage value of $9.6-million has been included as a credit.

Project sensitivities

The project is sensitive to gold price.

                           PROJECT SENSITIVITIES
 
                                                          Base
                                                          case
Gold price (per oz)                       $1,000 $1,100 $1,250 $1,400 $1,500

To Orezone
NPV (0%) after tax ($M)                    121.2  198.5  323.9  437.1  519.8
NPV (5%) after tax ($M)                     49.1  105.1  196.1  278.2  338.1
IRR after tax                              10.4%  16.1%  24.4%  31.3%  36.2%
To gov't of Burkina Faso (incl. taxes,
dividends and royalties)
NPV (0%) after tax ($M)                     99.1  149.1  214.8  292.6  337.3
NPV (5%) after tax ($M)                     69.8  105.7  152.7  208.5  240.6

The project is also sensitive to operating costs, in particular fuel (diesel and HFO) which accounts for approximately 25 per cent of expenses. Diesel pricing is set by the government of Burkina Faso. The study uses the conservative delivered to site fuel prices of $1.20 per litre for diesel and 77 cents per litre for HFO. Although diesel prices are lower than those used in the 2014 PEA, they are not as low as the current price in Burkina Faso or the free market price. The project economics and other mining operations in the country would benefit if the government were to change their policy to allow free market pricing and direct supply.

Mine plan and pit optimization studies

The company has worked with RPA to develop a mine plan and production schedule (based on the April, 2013, resource model). Scheduling has been optimized for project returns by processing the higher-grade ore in the early years and stockpiling the lower grade ore for processing after mining is complete in year 8. Initial process grade for years 1 through 3 averages 1.08 grams per tonne, with the years 1 through 8 averaging 0.88 gram per tonne. A fleet of 32-tonne haul trucks, such as Volvo or Scania rear-dump units, will be used to provide increased versatility, as the mine plan consists of a large number of shallow pits of varying tonnage.

Total ore processed, including the lower-grade stockpiles, will be 59.9 million tonnes of oxide and semi-oxidized ore grading an average of 0.76 gram per tonne. The life of mine strip ratio is approximately one tonne of waste per tonne of ore.

Metallurgical test results

KCA has completed all of the metallurgical testing associated with the Bombore project study and have reviewed the historical data. Results indicate that the overall recovery for the combined heap leach and CIL processing circuit is expected to be 87 per cent. The circuit separates the fine ore (minus 212 microns) from the coarse ore in a cyanide solution via a rotary scrubber, screen and classifiers. The slurried fine ore (49 per cent of the total) is pumped to a CIL circuit for gold recovery without any grinding. The CIL tails are sent to a lined tailings facility that utilizes the heap leach as part of the containment system in order to reduce the footprint and liner costs. The tails facility is designed to be zero discharge. The coarse (plus 0.212 millimetre) fraction is conveyed to a standard heap leach pad, where it is leached with a cyanide solution. With the majority of the fines removed from the coarser heap leach ore, there is no requirement for cement agglomeration or interlift liners for a stacking height of up to 60 metres. The pregnant liquor from the heap leach is sent to the CIL circuit for gold recovery. Gold is recovered in a standard carbon desorption plant, finishing with electrowinning and smelting to produce gold dore bars.

Maximum power requirement will be 7.2 kilowatt-hours per tonne of ore.

                               REAGENT CONSUMPTION

Reagent                                                          Consumption

Cyanide                                        0.4 kg/t heap; 0.165 kg/t CIL
Lime                                                               1.24 kg/t
Caustic                                                            25.9 t/yr
Carbon                                                               52 t/yr

Development timetable

Estimated time to construct the Bombore operation (preproduction) is 21 months, including time to excavate the off-channel reservoir to be used for project water storage, and time to commission the process plant equipment.

Water for the operation will be collected by gravity feed into the OCR from about 10 per cent of the annual rainy season runoff from the Nobsin River drainage basin. The OCR usable volume design capacity is three million cubic metres, and significantly larger than those designs presented in the 2014 PEA (900,000 cubic metres). Annual water consumption for the project is calculated to be, on average, between 2.6 million and 2.9 million cubic metres per year and considers recycle of tailings solution. The increase in annual water consumption as compared to the 2014 PEA is due to the change in the process from 100 per cent heap leach to a combined heap leach/CIL process.

Environmental studies and social responsibility

The environmental baseline studies for the Bombore project began in 2011 and were completed at the end of 2014. Local consultants have conducted archeological studies and a comprehensive range of environmental and social impact studies. Their work is supported by WSP, which was retained by Orezone early in 2014 to support and audit the Bombore ESIA study and resettlement action plan.

Over the past five years the company has recognized and accepted its social responsibility by actively supporting local communities by sponsoring over 50 initiatives which included improvements and additions to local schools, clinics, water wells and supply inventories. Orezone has on staff technically qualified employees, sociologists and managers experienced with mining and resettlement projects in Burkina Faso. With the help of the company's employees, consultants and community leaders the company is currently developing plans to pursue these community projects in the coming weeks, months and years.

The company continues to hold formal and informal information meetings with the community leaders to update them regularly on the status of the Bombore study. In order to ensure safe operations, the project will require the relocation of over 500 local households (approximately 3,700 residents) from several communities and two artisanal mining sites over the initial five years of construction and operation. The program for this relocation has been the object of joint discussions involving the communities affected, their representatives, the company and its local consultants Socrege. A detailed analysis based on these discussions has led to a substantial increase in relocation and resettlement cost as compared with the 2014 PEA. The main areas where estimated costs increased were building replacement, artisanal miner compensation, infrastructure crop and tree compensation and livelihood compensation. Preproduction costs for the resettlement program are now estimated at $10.3-million, with life of mine costs estimated at $20.2-million.

Full details of the feasibility study in the form of a National Instrument 43-101 technical report will be filed on SEDAR within the next 45 days. The company is also in the process of updating the 2013 mineral resource estimate with the inclusion of an additional 50,000 metres of drilling. The update will be completed by the third quarter of 2015 and if warranted, an update to the mineral reserve and mine plan will be completed prior to any production decision.

Carl Defilippi of Kappes, Cassiday & Associates, Glen Ehasoo of RPA, Todd Minard of Golder Associates, Craig Wood of WSP, Glen Cole of SRK Consulting (Canada), and Tim Miller, chief operating officer, Pascal Marquis, senior vice-president, and Ron Little, chief executive officer, of Orezone, are qualified persons under National Instrument 43-101 and have reviewed the information in this release.

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.