09:33:39 EDT Sat 20 Apr 2024
Enter Symbol
or Name
USA
CA



Maya Gold & Silver Inc
Symbol MYA
Shares Issued 116,823,758
Close 2014-07-21 C$ 0.46
Market Cap C$ 53,738,929
Recent Sedar Documents

Maya Gold commissions Zgounder mill, processing 200 tpd

2014-07-22 12:35 ET - News Release

Mr. Guy Goulet reports

MAYA GOLD & SILVER: OPERATIONS STARTED AT ZGOUNDER SILVER MINE

Maya Gold & Silver Inc. has started milling operations at its flagship Zgounder silver mine in Morocco.

Ore grading an average of 245 grams per tonne silver are now being processed. The ore being run through the mill is being sourced from the 35,000 tonnes of mineralized rock that were transferred to storage areas adjoining the plant from the existing 66,000 tonnes of "ancient stockpiles." The size of this stockpile can sustain over six months of production at the initial rate of approximately 200 tonnes per day. Silver recovery is expected to be in the range of 92 per cent. The company is not basing its production decision on a feasibility study of mineral reserves demonstrating economic and technical viability.

"The mill start-up at Zgounder is a significant key milestone in the successful development of Maya as an operating resource company, and we recognize and thank our president, Noureddine Mokaddem, and the local and Moroccan government offices which have just provided the company with a very precious tool in a difficult period of the mining industry: a stable and upwardly potential cash flow stream," stated Guy Goulet, chief executive officer.

Cautionary statements

The decision to restart production at Zgounder and the company's plans for a mining operation as disclosed herein were based on economic models prepared by the company in conjunction with management's knowledge of the property, and the existing preliminary estimates of the measured, indicated and inferred mineral resources on the property. The production decision and plans were not based on a feasibility study of mineral reserves demonstrating economic and technical viability. Accordingly, there is increased uncertainty, and economic and technical risks of failure associated with the production decision and plans, in particular the risk that mineral grades will be lower than expected, the risk that construction or continuing mining operations are more difficult or more expensive than expected, the risk that the company will not be able to transport or sell the mineralized rock it produces to local custom toll mills on the terms it expects, or at all; production and economic variables may vary considerably, due to the absence of a detailed economic and technical analysis according to and in accordance with National Instrument 43-101. Inferred mineral resource estimates are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves.

Milestones achieved at Zgounder mine project (2013-14):

  • The complete rehabilitation of mine site and mill;
  • Completion of an environmental impact study;
  • Creation of Zgounder Millennium Silver Mining (85 per cent Maya/15 per cent ONHYM);
  • Filing of an initial NI 43-101-compliant silver resources estimate for Zgounder silver mine (February, 2014);
  • Obtaining of cyanide importing and operating permits (March, 2014);
  • Filing of an NI 43-101 preliminary economic assessment on SEDAR (March, 2014);
  • Filing of an NI 43-101 prefeasibility study on SEDAR (May, 2014);
  • Reception of cyanide (June, 2014);
  • Operations team strengthened at mine site. Key management employees all being in place.

Commissioning phase

The commissioning phase for the processing facility is expected to continue for approximately four months, and ore throughput will increase to 250 tonnes per day. Mill feed during the commissioning period will initially be sourced from the existing ancient stockpile. Underground development and operations will commence, and are expected to generate further stockpiles of ore for processing following the commissioning period.

A new tailings pond with a capacity of one million tonnes was built, and 25,000 square metres of geo-membrane have been stretched out and certified as compliant by local authorities. The local authorities visited the mine site on Friday, July 18, and favourably commented on the geo-membrane covering the new tailings dam which is designed to hold the first few years of mine production.

Underground development

Additional underground production equipment is expected to arrive on site during the second week of August, 2014, which will immediately accelerate ore extraction from several already developed stopes.

Highlights of recent preliminary economic assessment study:

  • A mining life of 10 years with the current resources;
  • First-year silver production of 647,000 ounces, followed by a regular production of 1,027,000 ounces per year;
  • Very high mill feed grade estimated at 360 grams per tonne silver;
  • Total operating costs of $113.5 (U.S.) per tonne (averaged over the expected mine life);
  • Additional capital expenditure requirements of only $3.8-million (U.S.), including the concentrator expansion;
  • Internal rate of return of 174 per cent;
  • Net present value of $65.9-million (U.S.) (discounted at 6.5 per cent) at a silver price of $22 (U.S.) per ounce;
  • The Zgounder PEA was prepared as a strictly underground mine related solely to the initial mineral resources reported on Feb. 19, 2014, as noted above.

Cautionary statements

The PEA is preliminary in nature and includes the use of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Thus, there is no certainty that the results stated in the PEA will be realized. Actual results may vary, perhaps materially. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Goldminds Geoservices, which authored the PEA, recognized in addition to the measured, indicated and inferred resources that there are areas within recognized structures and depth extensions which will require additional drilling. These recognized structure and depth extensions can offer additional mineral potential of between 1.5 million to two million tonnes grading 300 to 400 grams per tonne silver.

The potential quantity and grade are conceptual in nature, there has been insufficient exploration to define a mineral resource, and it is uncertain if further exploration will result in discovery of a mineral resource.

Qualified persons

The technical content of this news release has been reviewed by Francois Goulet from Goulex Inc., an independent qualified person under NI 43-101 standards.

We seek Safe Harbor.

© 2024 Canjex Publishing Ltd. All rights reserved.