Lupaka to start development at Invicta in February

2018-01-22 08:18 ET - News Release

Mr. Will Ansley reports

LUPAKA GOLD INITIATES DEVELOPMENT OF INVICTA GOLD PROJECT

Lupaka Gold Corp. has provided an update on operational advancements associated with the Invicta gold development project.

Highlights:

  • Mining contractor selected, mobilization has commenced and expected to take two to three weeks;
  • Rehabilitation, preparation and initial development of Invicta to commence in February, 2018, with three crews, new adit and 3430 level to be constructed;
  • Bulk samples to be extracted and sent to toll milling facilities in order to test and optimize metallurgical recoveries and concentrate quality;
  • Road construction resumes after holiday period and is approximately 20 per cent complete;
  • Preliminary economic assessment on track for completion in the first quarter of 2018.

Mining contractor commences rehabilitation, preparation and development work

PLH SAC, the mining contractor selected for the Invicta project, has commenced mobilization activities that will take two to three weeks to complete. By early February, 2018, the company anticipates PLH will have established three crews at site focused on:

  • Rehabilitation of the existing 3400 level including widening access points, reinforcing ground support and the installation of services;
  • Driving a new access drift from surface to develop the first sublevel for mining and a crosscut at the 3430 level. This new access point, when connected by the raise from the 3400 level, will complete the ventilation circuit and provide a secondary egress from underground;
  • Preparing initial development on the 3430 level access to the mineralized zone. Sampling will be performed and cross-referenced with the block model. Bulk samples will be sent to toll mill facilities to test and optimize throughput rates, metallurgical recoveries and concentrate quality.

The rehabilitation, preparation and initial development activities are expected to be completed mid-2018.

Road construction progress update

To avoid disruption with local communities over the holiday period and maintain safety standards, road construction was temporarily suspended from Dec. 22, 2017, until Jan. 5, 2018. Progress now continues on three fronts and project is approximately 20 per cent complete. Efforts to date have been primarily focused at the top section of the road in advance of the rainy season and in constructing bypasses around local communities.

Preliminary economic assessment

Further to the announcement on Nov. 28, 2017, the company has engaged SRK Consulting Canada Inc. as the lead contractor to prepare a preliminary economic assessment (PEA) on Invicta. The PEA remains on track for completion in the first quarter of 2018 and will be used as a basis for additional development by PLH.

Related-party transaction

In December, 2017, the company sold 200,000 of its Goldmining Inc. shareholdings, which were received as consideration for the company's November, 2017, sale of the Crucero project, to Will Ansley, chief executive officer of the company. This transaction was made in order to take advantage of an allowable, one-time block sale under the sale purchase agreement with Goldmining.

The sale of the Goldmining shares is considered to be a related-party transaction as defined under Multilateral Instrument 61-101 because it involves a director and officer of the company, Mr. Ansley. The transaction was exempt from the formal valuation and minority shareholder approval requirements of MI 61-101 in reliance on the exemptions set forth in sections 5.5(a) and 5.7(1)(a) of MI 61-101 as neither the fair market value of the Goldmining shares nor the consideration for the Goldmining shares exceeded 25 per cent of the company's market capitalization (as determined in accordance with MI 61-101). The company did not file a material change report more than 21 days before the expected closing of the sale of the Goldmining shares as the details of the sale and the participation therein by Mr. Ansley were not settled until shortly prior to closing and the company wished to close on an expedited basis for sound business reasons.

About Lupaka Gold Corp.

Lupaka Gold is a Peru-focused gold explorer and developer with geographic diversification and balance through its interest in asset-based resource projects spread across three regions of Peru.