2016-01-25 06:58 ET - News Release

Mr. Joseph Conway reports

PRIMERO INCREASES PRODUCTION BY 15% AND LOWERS AISC BY 20% IN 2015; EXPECTS ADDITIONAL COST REDUCTIONS IN 2016

Primero Mining Corp. has released its preliminary fourth quarter and full year 2015 operating results, and its 2016 guidance (all amounts are in U.S. dollars). The company's fourth quarter and full year 2015 financial results will be released on Feb. 18, 2016.

Highlights:

  • Record production achieved in 2015: Fourth quarter production of 68,155 gold-equivalent ounces resulted in record annual 2015 production of 259,474 gold-equivalent ounces, 15 per cent higher than in 2014 and within the company's 2015 production guidance range. Annual gold-equivalent production is expected to increase by up to 8 per cent in 2016 to between 260,000 and 280,000 ounces.
  • Low cash costs and all-in sustaining costs: Two thousand fifteen consolidated total cash costs are expected to be $637 per gold-equivalent ounce with preliminary all-in sustaining costs of $972 per gold ounce, below the company's 2015 guidance range of $640 to $680 per gold-equivalent ounce for total cash costs and $1,030 to $1,060 per gold ounce on an all-in-sustaining-cost basis. Preliminary all-in sustaining costs at the San Dimas mine were notably low at $680 per gold ounce, benefiting from high mill throughput rates well above the 2,500-tonne-per-day nameplate capacity and increased byproduct silver production versus 2014 due to the inclusion of the Jessica vein.
  • Further cost reductions expected in 2016: Primero expects a 10-per-cent all-in sustaining cost reduction will be achieved in 2016 compared with 2015 through a combination of increased cost controls and improved economies of scale with higher throughput rates. The company's 2016 guidance includes all-in sustaining costs of $850 to $900 per gold ounce, providing competitive positioning amongst gold industry peers.
  • Focused 2016 capital expenditures: Capital spending in 2016 will focus on core expenditures related to mining operations at San Dimas and Black Fox, and will total $82.4-million, including capitalized exploration. Aside from the remaining capital required to complete the 3,000-tonne-per-day mill expansion at San Dimas, all capital allocated for expansionary projects has been suspended until metal prices improve.

"We completed 2015 with production momentum, low costs and financial strength from our two mines in stable Americas-only jurisdictions," said Joseph F. Conway, chief executive officer. "Although 2015 was a volatile year in the markets we remained focused on delivering our operating plan. We advanced the San Dimas expansion while cutting its estimated capital costs significantly and delivered excellent exploration results across our asset portfolio. We are also well prepared to execute on the planned succession of Ernest Mast to the position of president and chief executive officer, and myself to executive vice-chairman later this month."

"Our top priorities in the year ahead are meeting or exceeding operational targets, preserving a strong balance sheet amid a challenging metals price environment and continuing to focus on delivering free cash flow," said Ernest Mast, president and chief operating officer. "We are particularly focused on completing the expansion of our platform San Dimas asset to 3,000 tonnes per day and continuing to identify productivity opportunities while also ensuring we create a transformational shift in attitude at the mine towards a safety culture committed to a workplace free of accidents. We also will be vigilant in our assessment of the ongoing progress at the Black Fox mine and will act to ensure it is a profitable asset for the company."

Low-cost gold production in Canada and Mexico

Primero produced 68,155 gold-equivalent ounces during the fourth quarter of 2015 (41,371 ounces of gold and 2.32 million ounces of silver from San Dimas, and 17,785 ounces of gold from Black Fox), resulting in record annual production for the company of 259,474 gold-equivalent ounces in 2015 (151,355 ounces of gold and 8.3 million ounces of silver from San Dimas, and 69,705 ounces of gold from Black Fox), 15 per cent higher than in 2014 and within the company's 2015 production guidance range.

The company was successful at maintaining cost control in the fourth quarter, with preliminary consolidated total cash costs of $613 per gold-equivalent ounce and preliminary all-in sustaining costs (AISC) of $1,021 per ounce. For the full year 2015, preliminary consolidated total cash costs were $637 per gold-equivalent ounce below the guidance range of between $640 to $680 per gold-equivalent ounce and preliminary AISCs of $972 per ounce also below the company's 2015 cost guidance range of $1,030 to $1,060 per ounce.

San Dimas exceeded expectations producing 50,370 gold-equivalent ounces during the fourth quarter at preliminary cash costs of $535 per gold-equivalent ounce and preliminary AISCs of $753 per ounce. This resulted in Primero achieving another consecutive record for annual production of 190,139 gold-equivalent ounces at preliminary cash costs of $558 per gold-equivalent ounce and preliminary AISCs of $680 per ounce, well below the 2015 guidance range of $740 to $770 per ounce. Production in 2015 at San Dimas was notably higher than 2014 as a result of higher throughput related to the continuing expansion of the mill to 3,000 tonnes per day and increased availability of the high-grade Jessica vein. Average throughput in 2015 increased by 10 per cent averaging a record 2,721 tpd (based on 365-day availability).

Black Fox produced 17,785 ounces of gold during the fourth quarter at preliminary cash costs of $834 per ounce and preliminary AISCs of $1,104 per ounce. Underground throughput increased significantly quarter over quarter to an average of 620 tonnes per day. For full year 2015, the mine produced 69,705 ounces at preliminary cash costs of $850 per ounce. Preliminary AISCs were $1,163 per ounce, in line with the 2015 cost guidance range and a significant decrease compared with 2014. The cost reduction was achieved largely through the achievement of process optimizations following Primero's recapitalization efforts in 2014 and early 2015. Average mill throughput increased by 4 per cent in 2015 averaging a record 2,400 tpd (based on 365-day availability).

Primero's 2016 focus is on maintaining a low-cost structure and disciplined capital allocation

Primero expects an increase in 2016 production of up to 8 per cent relative to 2015, partly due to the completion of the San Dimas mill expansion to 3,000 tpd expected in third quarter 2016. The completion of the tailings filter has been delayed due to flooding in southern India which has impacted the timing of equipment delivery. Primero is guiding to between 260,000 and 280,000 gold-equivalent ounces in 2016, which includes gold production of 215,000 to 235,000 ounces and 8.5 million to 9.5 million ounces of silver. However, the company expects first quarter 2016 production to be lower than the quarterly average due to the implementation of improved safety procedures at San Dimas.

The company expects to lower its overall spending profile in 2016 by focusing on prudent sustaining capital allocation. Sustaining capital projects have been prioritized given their respective relevance to maintaining production levels, and 2016 exploration targets have been identified and prioritized based on potential to influence near-term production. As a result, AISCs are expected to decrease by an additional 10 per cent compared with 2015 to between $850 and $900 per gold ounce and total cash costs are expected to be in the range of $570 to $620 per gold-equivalent ounce, well below industry averages.

Primero's 2016 production guidance is summarized in the table.

 
                                PRODUCTION GUIDANCE

                                      San Dimas       Black Fox   Estimated 2016
Attributable gold-equivalent
production (gold-equivalent
ounces)                                 190,000-  70,000-80,000  260,000-280,000
                                        200,000
Gold production (ounces)                145,000-
                                        155,000   70,000-80,000  215,000-235,000
Silver production (million ounces)      8.5-9.5             N/a          8.5-9.5
Total cash costs (per
gold-equivalent ounce)                $525-$575       $680-$730        $570-$620
All-in sustaining costs (per gold
ounce)                                $660-$710       $940-$990        $850-$900

Material assumptions used to forecast total cash costs for 2016 include: an average gold price of $1,050 per ounce; an average silver price of $5.16 per ounce (calculated using the silver purchase agreement contract price of $4.26 per ounce and assuming excess silver beyond contract requirements is sold at an average silver price of $14 per ounce); and foreign exchange rates of $1.35 and 16 Mexican pesos to the U.S. dollar.

Capital expenditures for 2016 reduced but not restrictive

Primero has narrowed its 2016 focus to core capital expenditures related to advancing the existing underground mining operations at San Dimas and Black Fox, and as a result the company expects capital expenditures in 2016 of $82.4-million, which includes capitalized exploration costs of $18.4-million.

                              CAPITAL EXPENDITURES 
 
                                                              Estimated 2016 

San Dimas underground development                              $24.5-million
San Dimas sustaining capital                                   $10.8-million
San Dimas projects                                             $12.0-million
San Dimas subtotal                                             $47.4-million 
Black Fox underground development                               $9.3-million
Black Fox sustaining capital                                    $4.2-million
Black Fox projects                                              $1.2-million
Black Fox subtotal                                             $14.7-million 
Cerro del Gallo development                                     $1.9-million
Total                                                          $64.0-million

Capital projects at San Dimas are principally related to the completion of the 3,000 tpd mill expansion, which is expected to increase the mine's annual production capacity to approximately 215,000 gold-equivalent ounces beginning in Q3 2016. The company is also focused on accessing the recently added mining concessions located adjacent to the original San Dimas concession that are not covered by the silver purchase agreement with Silver Wheaton Caymans Ltd. and as a result capital allocated for underground development is higher than in previous years.

Capital expenditures at Black Fox are principally related to the development of drifts and necessary infrastructure to ramp up mining rates from the Deep Central zone.

As a result of the current gold price and based on the results of the recently completed internal scoping study, the company has elected not to immediately proceed with the development of the Grey Fox project. The project does not generate a sufficient internal rate of return to justify the required capital expenditure in the current gold price environment. Expenditures at Grey Fox have therefore been minimized in 2016, and the company's principal exploration focus at the Black Fox complex will be the continued definition and delineation of the Froome deposit, and other Froome-style targets located near to existing infrastructure.

Exploration focused on adding near-term production ounces

Primero continues to invest in exploration at both of its mining operations, and has identified and prioritized 2016 exploration targets based on potential to influence near-term production in areas near existing infrastructure. In 2016, the company is planning total capitalized exploration expenditures of $18.4-million.

                    CAPITALIZED EXPLORATION EXPENDITURES  
         
                                                              Estimated 2016 

San Dimas diamond drilling                                      $4.7-million
San Dimas drifting                                              $4.8-million
San Dimas regional diamond drilling                                 $400,000
San Dimas subtotal                                              $9.1-million 
Black Fox diamond drilling                                      $4.4-million
Regional exploration                                            $4.5-million
Black Fox complex subtotal                                      $8.9-million 
Cerro del Gallo geology mapping                                     $400,000
Total                                                          $18.4-million* 
                                                                            
* Excludes $4.0-million of expensed exploration expenditures at the Ventanas 
project.

Similar to previous years, the 2016 exploration program at San Dimas will target high-grade mineralization located close to existing infrastructure. However, this year's program will rely more heavily on drifting as an exploration tool in order to reach highly prospective areas located north of the Jessica vein, northwest toward the Perez vein, and south toward the Verdosa and Camichin veins, and the recently added Lechuguilla concession. The goal of the 2016 exploration program includes the full replacement of expected 2016 mining depletion and investing in the company's future by advancing toward accessing ore outside of the silver purchase agreement. To this end, the company expects to spend $4.0-million in expensed exploration at Ventanas for new target identification and approximately 24,000 metres of diamond drilling.

The company intends to build on its successful 2015 exploration program at Black Fox which included the delineation of Deep Central zone mineralization down to approximately 800 metres below surface and the discovery of the highly prospective Froome zone to be included in the year-end 2015 resource update. Exploration in 2016 will continue to be focused on exploring Black Fox west of the Deep Central zone and at depth. The adjacent Froome zone is also a key focus with a delineation program planned, given the promising preliminary results obtained, its location approximately one kilometre west of the Black Fox mine and potential to access the zone via underground drifting. Surface activities will seek to explore other Froome-style deposits on existing concessions.

San Dimas improvements demonstrate effectiveness of capital allocations

Following the initial recapitalization of the San Dimas mine in the years immediately following the acquisition in 2010, San Dimas has consistently increased annual production, while consistently decreased capital and exploration spending. Production has approximately doubled from 102,224 gold-equivalent ounces in 2011 to approximately 195,000 ounces expected in 2016, with annual capital spending including exploration declining year over year from $66.4-million in 2013 to $56.5-million expected in 2016.

Production in 2016 is expected to increase modestly over 2015, benefiting from higher mill throughput rates following the completion of the 3,000 tpd mill expansion expected to be complete in third quarter 2016. Gold head grades in 2016 are expected to be in line with grades achieved in 2015, with some improvement expected through the year as the mine works to decrease dilution as a critical part of achieving improved process efficiencies. Silver byproduct production and by extension associated byproduct credits will be elevated in 2016 as a greater proportion of mine production is sourced from the high-grade Jessica vein.

Primero continues to advance initiatives at San Dimas aimed at increasing long-term operational efficiencies and profit margin. These include achievement of commercial haulage rates through the Sinaloa Graben-Central block haulage loop in first quarter 2016 and implementation of improved mining techniques with an emphasis on safety. San Dimas is also focused on increasing longhole mining to a 40-per-cent contribution using high production two-by-12-hour shifts and developing areas outside the original San Dimas concessions.

Ensuring the viability of the Black Fox mine

Primero remains committed to the Black Fox complex and aims to achieve profits from the mine in 2016 at current gold prices. This commitment includes continued investment in the mine to develop areas in the Deep Central zone. The contribution of ore from the Deep Central zone increases throughout 2016 and a mining rate of approximately 850 tpd is expected in fourth quarter 2016. Exploration is focused west of the Deep Central zone, at depth and locally within the concession at significantly reduced levels relative to 2014 and 2015. The goal of the 2016 exploration program at Black Fox is to replace 100 per cent of expected mining depletion.

The company believes that at a gold price of $1,050 per ounce the mine is operating at a cash-flow-neutral state and should the gold price remain below the $1,050 level for an extended period, the company will assess all options regarding the future of the site. Additionally, the company has decided not to advance the Grey Fox project and will wait for a more positive gold price environment before investing the capital required for its development. The company's focus will move to delineating the Froome deposit as a medium-term alternative to complement Black Fox ore in order to fill the mill beyond the end of 2017. The current Black Fox stockpile is projected to be depleted during Q3 2017.

Conference call details

Primero plans to release its fourth quarter and full year 2015 financial results before the market opens on Thursday, Feb. 18, 2016. A conference call will also be held on the same day at 10 a.m. ET to discuss these results.

Participants may join the call by dialling North America toll-free 1-888-789-9572 or 416-695-7806 for calls outside Canada and the United States, and entering the participant passcode 5647764.

A live and archived webcast of the conference call will also be available at the company's website under the news and events section.

A recorded playback of the third quarter 2015 results call will be available until May 19, 2016, by dialling 1-800-408-3053 or 905-694-9451 and entering the call-back passcode 5647764.

We seek Safe Harbor.