Mr. Barry Hildred reports
AQUILA RESOURCES ANNOUNCES FILING OF TECHNICAL REPORT; FINAL TECHNICAL REPORT INCLUDES UPDATED ECONOMICS; $282.2M PRE-TAX NPV AND 38.8% PRE-TAX IRR
Aquila Resources Inc. has
filed a technical report in respect of the
company's preliminary economic assessment on the Back Forty project.
PEA highlights
In preparation of the final National Instrument 43-101-compliant technical report, the
company has provided updated economics for Back Forty.
KEY ECONOMIC HIGHLIGHTS
Pretax After tax
Net present value
at 6 per cent $282.2-million $210.8-million
Internal rate
of return 38.8% 32.0%
Payback period 1.4 years 1.8 years
The PEA includes inferred resources that are considered too speculative
geologically to have the economic considerations applied to them that
would enable them to be categorized as mineral reserves. There is no
certainty that the PEA results will be realized.
There are no updates to the capital or operating expenditures from the
figures stated in the July 23, 2014, press release.
Sensitivity analysis
Taking into consideration the updated economics, a new sensitivity
analysis was performed to test the economic viability of Back Forty
against possible fluctuations in commodity prices. A table illustrating
project sensitivity is attached.
SENSITIVITY ANALYSIS
Base case Base case Base case
-15% +15%
Gold (per ounce) $1,099 $1,293 $1,487
Silver (per
ounce) $17.39 $20.46 $23.53
Zinc (per pound) $0.82 $0.96 $1.10
Copper (per
pound) $2.70 $3.18 $3.66
Lead (per pound) $0.82 $0.96 $1.10
Pretax
NPV at 6 per
cent (in
millions) $122.3 $282.2 $440.6
IRR 23.7% 38.8% 52.0%
Payback period 2.8 years 1.4 years 0.9 year
After-tax
NPV at 6 per
cent (in
millions) $95.2 $210.8 $324.8
IRR 20.2% 32.0% 42.0%
Payback period 3.1 years 1.8 years 1.2 years
Project potential
An alternative mine plan, which considers a low-capex, high-grade initial-phase operation, was evaluated in the PEA and provides some flexibility
in the development of the project. This option would focus on mining
near-surface, high-grade zones by way of three small open pits in order
to maximize capital return in the early years of production. This
approach has the potential to provide attractive economic returns,
mitigate certain start-up risks and allow for significant optionality
in the long-term development of the project. Following the five-year
initial-phase operation, Aquila could commence a second-phase operation,
which would consider an expanded pit and/or inclusion of the
underground resource.
This opportunity would be fully evaluated during the feasibility stage
of project development and could be pursued depending on future
macroeconomic conditions.
KEY ECONOMIC HIGHLIGHTS OF INITIAL-PHASE OPERATION
Pretax After tax
NPV at 6 per cent $129.4-million $103.3-million
IRR 38.6% 35.2%
Payback period 2.1 years 2.2 years
Qualified persons
The technical report was prepared under the supervision of Tetra Tech
Inc., specifically Rex Bryan, SME; Wenchang Ni, PEng; Daniel Sweeney,
PEng; Arun Vathavooran, PhD, CEng, MIMMM, SME; Dharshan
Kesavanathan, PEng; Mike McLaughlin, PEng; Sabry Abdel Hafez,
PEng; and Andrew Carter, EurIng, CEng, MIMMM, MSAIMM, SME. All
of the aforementioned individuals are qualified persons as defined in
National Instrument 43-101.
The environmental components of the technical report were prepared under
the supervision of Andrea K. Martin, PE, from Foth Infrastructure &
Environment LLC. Ms. Martin is considered a qualified person as
defined under NI 43-101.
The scientific and technical information in this news release was
reviewed and approved by Thomas O. Quigley, vice-president of
exploration and senior technical adviser for the Back Forty project. By
virtue of his education, experience and professional association, Mr.
Quigley is considered a qualified person as defined under NI 43-101.
Information regarding data verification is provided in Aquila's annual
information form dated March 31, 2014.
We seek Safe Harbor.
© 2024 Canjex Publishing Ltd. All rights reserved.