13:03:36 EDT Tue 09 Jun 2026
Enter Symbol
or Name
USA
CA



Sherritt International Corp
Symbol S
Shares Issued 295,717,790
Close 2011-10-25 C$ 4.88
Market Cap C$ 1,443,102,815
Recent Sedar+ Documents

Sherritt International earns $45.5-million in Q3

2011-10-26 08:16 ET - News Release

An anonymous director reports

SHERRITT REPORTS THIRD-QUARTER 2011 RESULTS

Sherritt International Corp. has released its third quarter 2011 results.

  • Net earnings for third quarter 2011 were up 102 per cent to $45.5-million (16 cents per share, basic), compared with net earnings of $22.5-million (seven cents per share, basic) for third quarter 2010.
  • Sales volumes for third quarter 2011 (Sherritt's share) totalled 9.4 million pounds of nickel, 1.1 million pounds of cobalt, 9.1 million tonnes of thermal coal, 1.1 million barrels of oil and 159 gigawatt hours of electricity.
  • Cash, cash equivalents and short-term investments were $586.6-million at Sept. 30, 2011, including $18.2-million (50-per-cent basis) held by the Moa joint venture. Cash held by the Ambatovy project is included in investment in an associate and was $12.1-million (40-per-cent basis) as at Sept. 30, 2011.
  • Operating cash flow for third quarter 2011 was $95.8-million, compared with $91.3-million in third quarter 2010.
  • Spending on capital and intangibles relating to existing operations totalled $36.8-million for third quarter 2011 (excluding accruals and capital leases), unchanged compared with third quarter 2010. Spending on capital in the Ambatovy project was $322.7-million (100-per-cent basis) for third quarter 2011, 60 per cent higher than the prior year period.
  • Primary construction of the Ambatovy project is complete with all 56 major process plant modules turned over to commissioning teams. All areas of the project are either in precommissioning, commissioning or start-up. Two of the three power plant units are operating reliably and provide sufficient power for commissioning activities and start-up. The start-up sequencing has begun on the first systems of the pressure acid leach circuits, including the first autoclave and the ammonia storage facility. Commissioning is complete on many ancillary operations and systems including the acid plants, air separation plant and limestone plant. The project is scheduled to produce first metal in first quarter 2012.
  • At Sept. 30, 2011, total available liquidity was approximately $1.0-billion. During third quarter 2011, the borrowing under the $2.1-billion (U.S.) (100-per-cent basis) Ambatovy joint venture senior project financing was completed. Total long-term debt at Sept. 30, 2011, was $1.6-billion, including approximately $800-million related to non-recourse Ambatovy partner loans to Sherritt.

                                                                
                           SUMMARY FINANCIAL DATA 
              (In millions of dollars unless otherwise noted)    
                                                                 Nine months ended
                                                                         Sept. 30,
                                          Q3 2011    Q3 2010       2011       2010

Revenue                                    $466.4     $412.7   $1,441.5   $1,185.4
EBITDA (1)                                  148.5      135.8      470.8      387.7
Earnings from operations and
associate                                    89.7       72.4      311.7      242.8
Net earnings                                 45.5       22.5      169.2      102.1
Basic earnings per share ($ per
share)                                       0.16       0.07       0.58       0.35
Diluted earnings per share ($ per
share)                                       0.15       0.07       0.57       0.35
Net working capital (2)                   1,031.7    1,045.5    1,031.7    1,045.5
Spending on capital and
intangibles (3)                              36.8       36.8       86.3      106.5
Total assets                              6,367.6    6,020.2    6,367.6    6,020.2
Shareholder equity                        3,764.4    3,561.5    3,764.4    3,561.5
Long-term debt to total assets (%)             26         25         26         25

Notes
(1) For additional information see the non-IFRS (international financial 
reporting standards) measure -- EBITDA (earnings before interest, taxes, 
depreciation and amortization) section on the company's
website.                                                       
(2) Net working capital is calculated as total current assets less total   
current liabilities.                                                   
(3) Spending on capital does not include accruals and does not include     
spending on the Ambatovy project.                                      
    
                               SUMMARY SALES DATA                                                          
                                (Units as noted)                   
                                                                   Nine months ended
                                                                           Sept. 30,
                                           Q3 2011    Q3 2010      2011         2010
Sales volumes
Nickel (thousands of pounds,
50-per-cent basis)                           9,421      9,800    27,922       27,462
Cobalt (thousands of pounds,
50-per-cent basis)                           1,052      1,067     3,121        2,989
Thermal coal -- prairie operations
(millions of tonnes)                           8.1        8.1      23.5         25.0
Thermal coal -- mountain operations
(millions of tonnes) (1)                       1.0        1.0       3.1          2.1
Oil (boepd, net working interest
production)                                 11,982     10,911    12,250       11,913
Electricity (GWh, 33-1/3-per-cent
basis)                                         159        176       461          519
Average realized prices
Nickel ($ per pound)                         $9.81      $9.87    $10.70        $9.88
Cobalt ($ per pound)                         15.50      18.61     16.42        19.20
Thermal coal -- prairie operations
($/tonne)                                    16.20      14.32     16.19        14.41
Thermal coal -- mountain operations
($/tonne)                                   102.39      88.41     98.03        83.71
Oil ($/boe)                                  69.62      50.51     66.81        51.58
Electricity ($/MWh)                          40.66      42.92     40.49        42.59

Note
(1) Prior to July 1, 2010, the corporation proportionately consolidated its
50-per-cent interest in the entity that owned the Coal Valley and Obed Mountain
mines.                                                                 
 
                             REVIEW OF OPERATIONS -- METALS
                                    (Units as noted)
                                                                     Nine months ended 
                                                                             Sept. 30, 
                                        Q3 2011    Q3 2010        2011            2010
Production
Mixed sulphides (tonnes,
50-per-cent basis)                        4,872      4,734      14,647          14,077
Nickel (tonnes,
50-per-cent basis)                        4,395      4,522      12,689          12,527
Cobalt (tonnes,
50-per-cent basis)                          489        489       1,408           1,361
Fertilizers (tonnes)                     58,083     56,301     173,249         173,205
Sales
Nickel (thousands of pounds,
50-per-cent basis)                        9,421      9,800      27,922          27,462
Cobalt (thousands of pounds,
50-per-cent basis)                        1,052      1,067       3,121           2,989
Fertilizers (tonnes)                     15,055     26,001     103,400         137,758
Reference prices
Nickel (U.S. dollars per pound)          $10.00      $9.62      $11.04           $9.61
Cobalt (U.S. dollars per pound) (1)       16.13      18.10       17.16           19.18
Realized prices
Nickel ($ per pound)                       9.81       9.87       10.70            9.88
Cobalt ($ per pound)                      15.50      18.61       16.42           19.20
Unit operating costs
(U.S. dollars per pound)
Mining, processing and refining
costs                                      6.28       4.86        6.06            5.02
Third party feed costs                     0.11       0.21        0.17            0.30
Cobalt byproduct credits (loss)           (1.76)     (1.95)      (1.87)          (2.02)
Other (loss)                              (0.17)      0.25       (0.11)           0.01
Net direct cash costs of
nickel (2)                                 4.46       3.37        4.25            3.31
Sulphur (U.S. dollars per tonne)         260.82     160.30      234.67          139.95
Sulphuric acid
(U.S. dollars per tonne)                 191.87     133.28      187.92          132.76
Revenue (millions of dollars)
Nickel                                     92.4       96.7       298.8           271.3
Cobalt                                     16.3       19.9        51.2            57.4
Fertilizers, other                         14.2       11.2        62.7            53.3
Total revenue                             122.9      127.8       412.7           382.0
EBITDA (millions of dollars) (3)           44.4       56.4       164.7           157.3
Earnings from operations and
associate (millions of dollars)            35.7       50.0       143.2           133.2
Spending on capital (millions
of dollars)                                 8.0       12.7        23.3            25.9

Notes
(1) Average metal bulletin -- low-grade cobalt published price.             
(2) Net direct cash costs of nickel after cobalt and other byproduct      
credits.                                                               
(3) For additional information see the non-IFRS measure -- EBITDA section 
on the company's website.

Mixed sulphides production for third quarter 2011 was 3 per cent (276 tonnes, 100-per-cent basis) higher than third quarter 2010, reflecting the impact of continuing process improvements. Finished nickel production was 3 per cent (254 tonnes, 100-per-cent basis) lower than the prior year period due to a lower nickel-to-cobalt ratio in the feed as well the impact of maintenance activities at the refinery. Finished cobalt production was unchanged when compared with third quarter 2010.

Third quarter 2011 nickel and cobalt sales volumes were 4 per cent (379 tonnes, 50-per-cent basis) and 1 per cent (15 tonnes, 50-per-cent basis) lower, respectively, than the prior year period due to the timing of shipments. Nickel sales were also impacted by lower production in the period.

The average nickel reference price in third quarter 2011 was 4 per cent (38 U.S. cents per pound) higher than the prior year period due mainly to relatively stronger demand. The average cobalt reference price was 11 per cent ($1.97 (U.S.) per pound) lower than third quarter 2010, due to lower demand.

The net direct cash cost of nickel for third quarter 2011 was 32 per cent ($1.09 (U.S.) per pound) higher than the prior year period due to the impact of higher commodity input prices, including a 63-per-cent increase in the cost of sulphur, a 44-per-cent increase in the cost of sulphuric acid and a lower cobalt byproduct credit resulting from the lower cobalt reference price. These impacts were only partially offset by lower third party feed costs and higher fertilizer byproduct credits.

Spending on capital in third quarter 2011 for the Moa joint venture was 37 per cent ($4.7-million, 50-per-cent basis) lower than the prior year period due to the timing of expenditures.

Ambatovy

Ambatovy project expenditures for third quarter 2011 were $329.2-million (U.S.) (100-per-cent basis) and cumulative capital spending on the project at Sept. 30, 2011, was $5.1-billion (U.S.) (100-per-cent basis). During third quarter 2011, a total of $211.2-million (100-per-cent basis) in financing was provided by the Ambatovy joint venture partners; Sherritt's 40-per-cent share ($84.5-million) was financed directly from cash on hand. In addition, $138.9-million (U.S.) was drawn on the senior project finance facility during third quarter 2011.

Primary construction of the project is complete with all 56 major process plant modules turned over to commissioning teams. All areas of the project are either in precommissioning, commissioning or start-up. As of Sept. 30, 2011, approximately 70 per cent of the construction personnel have been demobilized from the project, including approximately 4,300 people in third quarter 2011. During the staged start-up of the project, demobilization will continue as precommissioning, commissioning, testing, reworking and site cleanup are completed. Full production rates require the operation of two of the three power plant units. As of mid-October, two of the three power plant units were operating reliably and provide sufficient power for commissioning activities and start-up. Commissioning of the third and final coal-fired boiler is under way and it is expected to be operational during the fourth quarter. Supplemental diesel power generation (30 megawatts in total) is being installed to provide additional assurance of reliable power availability for plant operations. When complete, total generation capacity of the plant site will be approximately 163 megawatts and will exceed total power requirements at full production (60 to 75 megawatts). The start-up sequencing has begun on the first systems of the pressure acid leach circuits, including the first autoclave and the ammonia storage facility. Commissioning is also complete on many ancillary operations and systems including the acid plants, air separation plant and limestone plant. During third quarter 2011, the first sulphur shipment was received at the port, transported to the plant site and discharged to the stockpile. The first ammonia vessel is due to arrive at the port during the fourth quarter.

The project is designed to produce 60,000 tonnes (100-per-cent basis) of nickel and 5,600 tonnes (100-per-cent basis) of cobalt annually at capacity. The estimated project capital cost is $5.5-billion (U.S.) (100-per-cent basis), excluding financing charges, working capital and foreign exchange with production of first metal scheduled for first quarter 2012.

                           REVIEW OF OPERATIONS -- COAL
                                  (Units as noted) 
                                                                      Nine months ended
                                                                              Sept. 30,
                                           Q3 2011     Q3 2010       2011          2010
Production (millions of tonnes)
Prairie operations                             7.7         8.4       22.9          24.4
Mountain operations (1)                        1.0         1.1        3.1           2.1
Sales (millions of tonnes)
Prairie operations                             8.1         8.1       23.5          25.0
Mountain operations (1)                        1.0         1.0        3.1           2.1
Realized prices ($/tonne)
Prairie operations (2)                      $16.20      $14.32     $16.19        $14.41
Mountain operations                         102.39       88.41      98.03         83.71
Unit operating costs ($/tonne)
Prairie operations (3)                       14.32       12.19      14.19         12.47
Mountain operations                          83.94       72.97      81.44         72.76
Revenue (millions of dollars)
Prairie operations
Mining revenue                               136.9       120.7      398.9         371.6
Coal royalties                                 7.6        10.7       29.1          31.7
Potash royalties                               4.8         1.5       14.8           8.0
Mountain operations and other
assets (1)                                    97.9        84.9      304.4         174.4
Total revenue                                247.2       217.8      747.2         585.7
EBITDA (millions of dollars) (4)
Prairie operations                            27.8        29.4       88.0          85.4
Mountain operations and other
assets (1)                                    15.7        12.3       47.2          19.5
Total EBITDA                                  43.5        41.7      135.2         104.9
Earnings from operations
(millions of dollars)                         14.0        12.2       56.1          53.6
Spending on capital
(millions of dollars)
Prairie operations                            21.0        14.3       57.4          43.1
Mountain operations and other
assets (1)                                     5.5         5.3       17.8          12.6
Total spending on capital                     26.5        19.6       75.2          55.7

Notes
(1) Prior to July 1, 2010, the corporation proportionately consolidated its
50-per-cent interest in the entity that owned the Coal Valley and Obed Mountain
mines.                                                                 
(2) Prairie operations realized pricing excludes results of the char and   
activated carbon businesses and royalties.                             
(3) Prairie operations unit operating costs exclude char and activated     
carbon results.                                                        
(4) For additional information see the non-IFRS measure -- EBITDA section 
on the company's website.

Third quarter 2011 production volumes at prairie operations were 8 per cent (700,000 tonnes) lower than the prior year period mainly due to lower demand at a contract mine, where the mine's main customer removed two generating units from service in first quarter 2011. In September, 2011, the customer began commercial operations of a new 495-megawatt (gross) generation unit that is considered one of the most advanced facilities of its kind in the world. The coal supply for this new unit is expected to offset the majority of the impact on coal demand from the closure of the two older generating units. Production volumes at mountain operations were 11 per cent (100,000 tonnes) lower than third quarter 2010, reflecting the impact of dragline repair and increased overburden removal at the Obed Mountain mine. The focus on preparatory activities in the third quarter is expected to permit higher production levels in the last quarter of the year.

Sales volumes at both prairie operations and mountain operations for third quarter 2011 were unchanged relative to third quarter 2010.

Realized pricing in prairie operations (excluding royalties, activated carbon and char) for third quarter 2011 was 13 per cent ($1.88 per tonne) higher than in the prior year period primarily due to higher contract revenue on lower sales volume at a contract mine and the sale of stockpile inventory from Bienfait to Boundary Dam's main customer. Realized pricing in mountain operations in third quarter 2011 was 16 per cent ($13.98 per tonne) higher than the prior year period due to stronger export thermal coal pricing, partially offset by the impact of a stronger Canadian dollar relative to the U.S. dollar.

Unit operating costs at prairie operations were 17 per cent ($2.13 per tonne) higher than third quarter 2010, due to the impact of lower production at a contract mine. Unit operating costs at mountain operations were 15 per cent ($10.97 per tonne) higher than in the prior year period due to lower production volumes at the Obed Mountain mine and higher loading equipment costs at the Coal Valley mine.

Total royalties for third quarter 2011 were 2 per cent ($200,000) higher than third quarter 2010, primarily due to the impact of higher potash market prices and production volumes.

Spending on capital in prairie operations in third quarter 2011 was 47 per cent ($6.7-million) higher than third quarter 2010, due to a scheduled tub replacement at the Paintearth mine and the timing of mining equipment lease additions at the Boundary Dam mine. Capital spending in mountain operations for third quarter 2011 was largely consistent with spending in the prior year period.

 
                      REVIEW OF OPERATIONS -- OIL AND GAS 
                                 (Units as noted)
                                                                  Nine months ended
                                                                          Sept. 30,
                                           Q3 2011    Q3 2010       2011       2010
Production (boepd) (1)
Gross working interest -- Cuba (2),
(3)                                         20,756     20,622     20,843     21,288
Net working interest (4)
Cuba -- cost recovery                        3,501      4,655      3,809      3,991
Cuba -- profit oil                           7,764      5,559      7,665      7,078
Cuba -- total                               11,265     10,214     11,474     11,069
Spain                                          354        336        422        481
Pakistan                                       363        361        354        363
Total net working interest                  11,982     10,911     12,250     11,913
Reference prices (U.S. dollars
per bbl)
U.S. Gulf Coast fuel oil No. 6              $98.55     $66.69     $94.45     $68.56
Brent crude                                 114.47      77.49     112.73      77.47
Realized prices
Cuba ($/bbl)                                 70.36      51.06      67.06      51.77
Spain ($/bbl)                               111.21      79.07     109.81      79.78
Pakistan ($/boe)                              8.15       8.31       8.01       8.34
Weighted average ($/boe)                     69.62      50.51      66.81      51.58
Unit operating costs
Cuba ($/bbl)                                 12.65      10.34      11.59      10.53
Spain ($/bbl)                                84.22      47.84      46.75      32.75
Pakistan ($/boe)                              2.49       1.90       2.98       2.05
Weighted average ($/boe)                     14.45      11.22      12.55      11.17
Revenue (millions of dollars)                 78.5       53.2      230.5      176.3
EBITDA (millions of dollars) (5)              60.8       38.5      181.2      131.0
Earnings from operations
(millions of dollars)                         43.4       14.4      132.2       71.4
Spending on capital (millions
of dollars)                                   16.6       11.6       50.3       41.4

Notes
(1) Oil production is stated in barrels per day (bpd). Natural gas       
production is stated in barrels of oil equivalent per day (boepd),   
which is converted at 6,000 cubic feet per barrel.                     
(2) In Cuba, the oil and gas segment delivers all of its gross working 
interest oil production to Union Cubapetroleo (Cupet) at the time of production.    
Gross working interest oil production excludes production from wells   
for which commerciality has not been established in accordance with    
production-sharing contracts.                                          
(3) Gross working interest oil production is allocated between oil and gas 
and Cupet in accordance with production-sharing contracts. The         
corporation's share, referred to as net working interest oil          
production, includes: (i) cost-recovery oil (based upon the           
recoverable capital and operating costs incurred by oil and gas under  
each production-sharing contract) and (ii) a percentage of profit oil 
(gross working interest production remaining after cost-recovery oil is
allocated to oil and gas). Cost-recovery pools for each production-sharing 
contract include cumulative recoverable costs, subject to      
certification by Cupet, less cumulative proceeds from cost-recovery oil
allocated to oil and gas. Cost-recovery revenue equals capital and     
operating costs eligible for recovery under the production-sharing     
contracts.                                                             
(4) Net working interest production (equivalent to net sales volume)       
represents the corporation's share of gross working interest           
production.                                                            
(5) For additional information see the non-IFRS measure -- EBITDA section 
on the company's website.

Third quarter 2011 gross working interest production for the period was relatively unchanged from the prior year period. Net working interest production in Cuba was 10 per cent (1,051 bpd) higher for the same comparable periods due mainly to a 25-per-cent (1,154 bpd) decrease in cost-recovery volumes resulting from the impact of higher realized oil prices, partially offset by an increase in cost-recovery expenditures. Third quarter 2011 production in both Spain and Pakistan was largely unchanged from the prior year period.

Average realized prices in third quarter 2011 were significantly higher than third quarter 2010 in Cuba (38 per cent or $19.30 per bbl) and Spain (41 per cent or $32.14 per bbl), as the impact of stronger reference pricing more than offset the impact of a stronger Canadian dollar relative to the U.S. dollar.

Third quarter 2011 unit operating costs in Cuba were 22 per cent ($2.31 per bbl) higher than the prior year period as the impact of a stronger Canadian dollar relative to the U.S. dollar was more than offset by higher input prices. Unit operating costs in Spain were 76 per cent ($36.38 per bbl) higher than the prior year period primarily due to well workover costs incurred in third quarter 2011.

Spending on capital in third quarter 2011 was 43 per cent ($5.0-million) higher than in the prior year period due to increased drilling activity in the Puerto Escondido and Yumuri fields. In third quarter 2011, drilling on two development wells commenced and two development wells were completed. This compares with one development well commenced and two development wells completed in third quarter 2010.

                              REVIEW OF OPERATIONS -- POWER 
                                     (Units as noted)  
                                                                        Nine months ended
                                                                                Sept. 30,
                                             Q3 2011      Q3 2010        2011        2010
Electricity sold (GWh,
33-1/3-per-cent basis)                           159          176         461         519
Realized price ($/MWh)                        $40.66       $42.92      $40.49      $42.59
Unit cash operating cost ($/MWh)               20.13        15.34       21.26       13.87
Net capacity factor (%)                           68           76          66          72
Revenue (millions of dollars)                   14.0         11.0        41.4        34.7
EBITDA (millions of dollars) (1)                 6.4          7.5        17.7        22.3
Earnings from operations (millions
of dollars)                                      3.7          4.8         9.8        13.9
Spending on capital (millions
of dollars)                                      2.5          3.5         4.7         5.3
Spending on service concession
arrangements (millions of dollars) (2)           4.3          0.6        13.4         3.5

Notes
(1) For additional information see the non-IFRS measure -- EBITDA section 
on the company's website.                                                       
(2) Costs incurred to maintain or enhance the Boca de Jaruco and Puerto    
Escondido operating assets are expensed on the consolidated statements 
of comprehensive income. As a result, maintenance and construction     
activities at Boca de Jaruco, including the 150-megawatt Boca de Jaruco      
combined cycle project, are expensed as incurred. The corporation      
records an intangible asset and a corresponding construction revenue   
amount to reflect the right to charge the Cuban government for the     
future supply of electricity. The net result is a nil impact to net    
earnings.

Electricity production for third quarter 2011 was 10 per cent (17 gigawatt hours, 33-1/3-per-cent basis) lower than third quarter 2010, due to continued gas supply shortages and scheduled maintenance. The gas turbine at Varadero that failed in second quarter 2011 is expected to be returned to service in fourth quarter 2011. Efforts to address the gas supply shortage continue, but to date, no efforts have provided viable solutions to the issue.

Third quarter 2011 unit cash operating costs were 31 per cent ($4.79 per megawatt hour) higher than third quarter 2010, due to higher repair and scheduled maintenance costs.

Spending on capital, including capitalized interest, and spending on service concession arrangements in third quarter 2011 were 66 per cent ($2.7-million, 33-1/3-per-cent basis) higher than in the prior year period primarily due to increased activity on the 150-megawatt Boca de Jaruco combined cycle project.

Cash, debt and financing

Cash, cash equivalents and short-term investments were $586.6-million at Sept. 30, 2011. Of the cash balance, $18.2-million (50-per-cent basis) was held by the Moa joint venture and is for the exclusive use of the joint venture. Cash held by the Ambatovy project is included in investment in an associate and was $12.1-million (40-per-cent basis) as at Sept. 30, 2011.

Total long-term debt at Sept. 30, 2011, was $1.6-billion, including approximately $800-million related to non-recourse Ambatovy partner loans to Sherritt.

At Sept. 30, 2011, the amount of credit available under various facilities was $500-million. During third quarter 2011, the borrowing under the $2.1-billion (U.S.) (100-per-cent basis) Ambatovy joint venture senior project financing was completed.

Outlook

Projections for Sherritt's production volumes, royalties and spending on capital for the year 2011 are shown in the associated table.

                              PROJECTIONS
                            (Units as noted)
                                                                   2011
Production volumes
Mixed sulphides (tonnes)                                         38,850
Nickel (tonnes, 100-per-cent basis)                              34,350
Cobalt (tonnes, 100-per-cent basis)                               3,750
Coal -- prairie operations (millions of tonnes)                      32
Coal -- mountain operations (millions of tonnes)                    4.4
Oil -- Cuba (gross working interest, bpd)                        20,700
Oil -- all operations (net working interest, boepd)              12,250
Electricity (GWh, 33-1/3-per-cent basis)                            620
Royalties (millions of dollars)
Coal                                                                 39
Potash                                                               17
Spending on capital (millions of dollars)
Metals -- Moa joint venture (50-per-cent basis)                     $45
Coal -- prairie operations                                           94
Coal -- mountain operations                                          44
Oil and gas -- Cuba (1)                                              62
Oil and gas -- other (1)                                              8
Power (33-1/3-per-cent basis) (2)                                    36
Total spending on capital (excluding Ambatovy)                      289
Metals -- Ambatovy (millions of U.S. dollars,
100-per-cent basis)                                               1,000

Notes
(1) Exploration and evaluation spending incurred prior to the 
technical feasibility and commercial viability of extracting the 
resources is recorded as an intangible asset.  
(2) Includes projected spending related to the 150-megawatt Boca 
de Jaruco combined cycle project that is expensed as incurred and 
is included in cost of sales on the consolidated statement of 
comprehensive income.   

In metals

  • Moa joint venture guidance for full-year 2011 production of mixed sulphides increased 1 per cent (550 tonnes, 100-per-cent basis), reflecting the strong operating performance in the first nine months. Finished nickel and cobalt production guidance for full-year 2011 is marginally higher than previous estimates due to the performance in the first nine months of the year. Guidance for spending on capital in the Moa joint venture is 10 per cent ($5-million, 50-per-cent basis) lower than previously provided, reflecting the deferral of spending to 2012. The Moa joint venture partners continue to review options for the completion of the phase 2 expansion and construction of a sulphuric acid plant at Moa. Guidance for spending on capital does not include any expansion-related expenditure, other than capitalized interest.
  • Ambatovy joint venture full-year 2011 capital spending remains at $1.0-billion (U.S.).
  • Sulawesi project projected spending for 2011 is expected to be $9-million, due to permitting delays. Spending is being directed toward the next phase of the resource drilling program and advancing environmental and social baseline studies as well as project prefeasibility work.

In coal

  • Prairie operations guidance for full-year 2011 production is 3 per cent (one million tonnes) lower than previous guidance due to the impact of adverse weather conditions in first half 2011 as well as the impact of lower demand at a contract mine, which main customer removed two generating units from service in first quarter 2011. Spending on capital in prairie operations is 6 per cent ($6-million) lower than previous full-year 2011 guidance, largely due to projects in the first nine months of 2011 costing less than originally projected, as well as the timing of expenditures.
  • Mountain operations production guidance remains unchanged. Spending on capital in mountain operations is projected to be 4 per cent ($2-million) lower than previous full-year 2011 guidance largely due to projects in the first nine months of 2011 costing less than originally projected.

In oil and gas

  • Guidance relating to full-year 2011 gross working interest oil production in Cuba increased 1 per cent (200 bpd), reflecting better than expected performance from producing wells. Total net working interest production for 2011 remains largely unchanged. Guidance on spending on capital for 2011 in Cuba remains largely unchanged from previous estimates. In total, eight development wells are planned for 2011.

In power

  • Guidance for 2011 full-year production is 5 per cent (32 gigawatt hours, 33-1/3-per-cent basis) higher than previous estimates, reflecting higher than expected gas supply in third quarter 2011, and higher gas supply in fourth quarter 2011 than previously anticipated. However, gas supply is expected to continue to be insufficient for the facilities to operate at full capacity. Full-year 2011 guidance for spending on capital, which is primarily related to the 150-megawatt Boca de Jaruco combined cycle project, remains largely unchanged from previous estimates.

We seek Safe Harbor.

© 2026 Canjex Publishing Ltd. All rights reserved.