Mr. Michel Letellier reports
INNERGEX REPORTS FIRST QUARTER 2013 RESULTS
Innergex Renewable Energy
Inc. has released its
operating and financial results for the first quarter ended March 31,
2013.
"Innergex continues to benefit from well-executed project development
and strategic acquisitions that expand and diversify our operations,
reducing risks and improving cash flows," declares Michel Letellier,
president and chief executive officer of the corporation. "We remain
focused on optimizing operating efficiencies, advancing projects under
construction and under permit phase on time and on budget, and closing
previously announced acquisitions," adds Mr. Letellier.
OPERATING RESULTS
(amounts shown are in thousands of dollars except as noted otherwise)
For the periods ended March 31,
2013 2012
Restated (3)
Power generated (MWh) 386,171 319,341
Long-term average (MWh) 461,529 394,532
Operating revenues $ 35,688 $ 28,069
Adjusted EBITDA (1) 25,403 18,289
Net (loss) earnings (178) 7,805
Net earnings per share (2) 0.01 0.10
(1) Adjusted EBITDA is defined as operating revenues less operating expenses, general and
administrative expenses, and prospective project expenses.
(2) Net earnings (loss) per share are calculated as net earnings (loss) attributable to
owners of the parent, less dividends declared on preferred shares, divided by the
weighted average number of common shares outstanding.
(3) Two thousand results have been restated to reflect the application of international
financial reporting standard 11.
First-quarter results
For the three-month period ended March 31, 2013, electricity production
reached 386.2 gigawatt-hours, or 84 per cent of the long-term average, compared with 81 per cent in
the corresponding quarter last year. Low water flows in British
Columbia and in the United States were partly offset by better-than-anticipated water flows in Quebec and Ontario. Wind conditions were
slightly lower than anticipated at all the wind farms except Carleton.
The Stardale solar farm produced 6 per cent less than its long-term average due
to the unusually large snowfalls followed by the extreme cold weather
in January, which slowed down the removal of snow on the solar panels.
Operating revenues increased by 27 per cent for the quarter, due mainly to the
contribution of the Stardale solar farm (which began commercial
operations in May, 2012), additional capacity of the Gros-Morne wind
farm (which began commercial operations in November, 2012), and the
acquisition of the Brown Lake and Miller Creek hydroelectric facilities
(which closed in October, 2012). Adjusted earnings before interest, taxes, depreciation and amortization increased by 39 per cent,
mainly as a result of higher operating revenues, and relatively stable
operating, general and administrative expenses.
For the first quarter of 2013, the corporation recorded a net loss of
$200,000, compared with net earnings of $7.8-million in the
corresponding quarter last year, due mainly to a much higher unrealized
net gain on derivative financial instruments recorded in the first
quarter of 2012. Excluding the unrealized net gain and the related
deferred provision for income taxes, the loss would have been
$5.0-million, compared with a loss of $17.5-million in 2012.
Cash flows from operating activities
For the first quarter of 2013, cash flows generated by operating
activities totalled $12.2-million, compared with $9.4-million in 2012.
Higher adjusted EBITDA and other net revenues were partly offset by a
negative variation in non-cash operating working capital items.
New international financial reporting standards rules impacting results presentation
The application of IFRS 11 has changed the classification and subsequent
accounting of the corporation's investments in Umbata Falls and Viger
Denonville. These facilities were classified as jointly controlled
entities under the previous standard and were accounted for using the
proportionate consolidation method; under IFRS 11, they are treated as
joint ventures, and the corporation's interests in these facilities are
required to be accounted for using the equity method.
These changes have taken effect as of Jan. 1, 2013. As a result, all
comparative figures for the year ended Dec. 31, 2012, were restated
to reflect the presentation changes arising from application of IFRS
11.
Development projects
Kwoiek Creek hydroelectric facility
The construction of this facility began in the last quarter of 2011.
During the first quarter of 2013, the clearing for the transmission
line was completed, and 90 per cent of the poles were installed. The intake
construction and penstock installation were still under way. Current
activities also include assembly and installation of the turbines and
generators, as well as work on the plant's electrical equipment.
Construction of this 49.9-megawatt facility is progressing as scheduled and
budgeted, and is expected to be completed in the last quarter of 2013.
Northwest Stave River hydroelectric facility
The construction of this facility began in the last quarter of 2011. As
planned, construction activities were halted for the winter period and
resumed at the end of March, 2013. The fish habitat compensation channel
and civil engineering work at the powerhouse have been completed, and
the powerhouse superstructure is nearly complete. Current activities
include penstock installation, as well as intake and switchyard
construction. Construction of this 17.5-megawatt facility is progressing as
scheduled and budgeted, and is expected to be completed in the last
quarter of 2013.
Viger-Denonville wind farm
Construction activities began in the first quarter of 2013, and
currently include wood clearing, road construction and concrete
pouring of the substation foundation. In April, 2013, the
Riviere-du-Loup regional county municipality and Innergex executed a
term sheet for the construction and long-term non-recourse project
financing of the wind farm. The partners expect the financing to close
during the summer of 2013. Construction of this 24.6-megawatt facility is
progressing as scheduled and budgeted, and is expected to be completed
in the last quarter of 2013.
Boulder Creek, North Creek and Upper Lillooet hydroelectric facilities
In January, 2013, an important milestone was reached when these projects
received their environmental assessment certificate from the province
of British Columbia. Following receipt of the proposals from civil
works contractors, and the corporation's decision to increase the
installed capacity of the Upper Lillooet project and of the Boulder
Creek project, a request for new pricing was made to some civil works
contractors. The decision regarding the selection of turbine generator
suppliers is pending. A limited notice to proceed was issued to the
transmission line contractor to move forward with the detailed design
and survey layout of the transmission line. Current activities include
continuing consultation with stakeholders and applications for obtaining
the relevant permits.
Discussions are continuing with BC Hydro to obtain its consent to amend the
power purchasing agreements to increase the installed capacity of the Boulder Creek and Upper
Lillooet projects, and to cancel the current version of the North Creek
project. Construction of the 25.3-megawatt Boulder Creek facility is expected
to start in 2013, and the project is expected to reach commercial
operation in 2015. Construction of the 81.4-megawatt Upper Lillooet facility
is expected to start in 2013, and the project is expected to reach
commercial operation in 2016.
Tretheway Creek hydroelectric facility
The corporation is evaluating the proposals from civil works
contractors, turbine and generator suppliers, and transmission line
contractors. Current activities also include hydrometric monitoring,
environmental studies, consultation with the various stakeholders and
applications for obtaining the relevant permits. Discussions are
continuing with BC Hydro to obtain the authorization to increase the
installed capacity. The corporation is moving ahead with some aspects
of the design and geotechnical studies. Construction of this 23.2-megawatt
facility is expected to start in 2013, and the project is expected to
reach commercial operation in 2015.
Big Silver Creek hydroelectric facility
Proposals from civil works contractors, turbine and generator suppliers,
and transmission line contractors have been received, and the
corporation is currently evaluating these proposals. Current activities
also include hydrometric monitoring, consultation with the various
stakeholders and applications for obtaining the relevant permits.
Construction of this 40.6-megawatt facility is expected to start in 2013, and
the project is expected to reach commercial operation in 2016.
Dividends declared
Dividends to preferred shareholders
On May 14, 2013, the corporation declared a dividend of 31.25 cents per
Series A preferred share payable on July 15, 2013, to Series A
preferred shareholders of record at the close of business on June 28,
2013.
On May 14, 2013, the corporation declared a dividend of 35.9375 cents per
Series C preferred share payable on July 15, 2013, to Series C
preferred shareholders of record at the close of business on June 28,
2013.
Dividends to common shareholders
On May 14, 2013, the corporation declared a dividend of 14.50 cents per
common share payable on July 15, 2013, to common shareholders of record
at the close of business on June 28, 2013.
Conference call reminder
The corporation will hold a conference call tomorrow, Wednesday, May 15,
2013, at 10 a.m. EDT. The first-quarter results will be presented by
Michel Letellier, president and chief executive officer of Innergex,
and by Jean Trudel, chief investment officer and senior vice-president, communications. Investors and financial analysts are
invited to access the conference call by dialling 647-427-7450 or 1-888-231-8191. Media and the public may also access this conference call on a
listen-only mode. A replay of the conference call will be available
later the same day on the corporation's website.
We seek Safe Harbor.
© 2026 Canjex Publishing Ltd. All rights reserved.