Mr. Harry Barr reports
POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR MURRAY BROOK ZN-CU-PB-AG DEPOSIT, BATHURST MINING CAMP, NEW BRUNSWICK
El Nino Ventures Inc. has provided the results of a National Instrument 43-101 preliminary economic assessment (PEA) for the Murray Brook polymetallic massive sulphide deposit, New Brunswick. The results of the PEA demonstrate the potential
technical and economic viability of establishing a new mine and mill
complex on the Murray Brook property. The projected cash flows
indicate an after-tax NPV (net present value) at a 5-per-cent discount rate of $96.4-million, an
IRR (internal rate of return) of 11.4 per cent, and a payback period of 5.4 years (see attached table). An NI
43-101 technical report will be filed on SEDAR within 45 days of the
date of this press release.
Harry Barr, ELN's chairman and chief executive officer commented: "The results of the PEA
clearly indicate that there is an indicative basis for a mining project
at Murray Brook. There is excellent potential to further enhance the projected economics
of the project, through continued refinements in metal recoveries as
well as the potential to augment existing resources by achieving an
exploration success on the adjacent Camel Back claims. With forecasts of increased metal demand and dwindling supply, the
positive PEA results for the Murray Brook project provide ELN
shareholders with the potential to benefit from the predicted upward
trend in zinc prices over the next few years."
Unless otherwise noted, all amounts in this press release are expressed
in Canadian currency. The PEA is prepared for 100-per-cent ownership of the
project revenues and expenditures. As noted below, ELN holds a 35-per-cent
interest in the project. The PEA includes inferred mineral resources
that are considered too speculative geologically to have the economic
considerations applied to them that would enable them to be categorized
as mineral reserves, and there is no certainty that the PEA will be
realized.
SUMMARY OF 2013 MURRAY BROOK PEA RESULTS
NPV (5%) $96.4-million
NPV (7%) $59.7-million
IRR 11.4%
Payback 5.4 years
Total LOM* capital $334.8-million
*Life of mine
The PEA was prepared by P&E Mining Consultants Inc. and the full results
of the study will be disclosed in an NI 43-101 technical report within
45 days of the date of this press release. The PEA was prepared under
the supervision of Eugene Puritch, PEng, of P&E Mining Consultants
Inc. Mr. Puritch is an independent qualified person in accordance with NI 43-101 and
has reviewed and approved the technical information in this release.
The main conclusions from the PEA follow below.
Mining and mineral processing
The life of mine production on a diluted and extracted basis for the Murray
Brook potentially economic portion of the resource estimate is planned
to be as displayed in the table.
MURRAY BROOK POTENTIALLY ECONOMIC PORTION OF THE RESOURCE ESTIMATE
Classification Tonnes Zn % Cu % Pb % Ag g/t Au g/t
Measured 12,075,000 2.75 0.37 0.96 38.8 0.47
Indicated 6,635,000 1.98 0.50 0.78 36.1 0.66
Meas. and ind. 18,710,000 2.48 0.42 0.90 37.9 0.53
Inferred 240,000 1.18 1.46 0.41 24.7 0.39
(1) Potentially economic portion of the mineral resource estimate
which is not a mineral reserve does not have demonstrated
economic viability. This estimate of mineral resources may be
materially affected by environmental, permitting, legal,
title, taxation, socio-political, marketing, or other relevant
issues.
(2) The quantity and grade of reported potentially economic
inferred resources in this estimation are uncertain in nature
and there has been insufficient exploration to define them as
an indicated or measured potentially minable mineral resource,
and it is uncertain if further exploration will result in
upgrading them to an indicated or measured potentially economic
mineral resource category.
(3) The potentially economic portion of the mineral resource in
this press release was estimated using the Canadian Institute
of Mining, Metallurgy and Petroleum (CIM), CIM Standards on
Mineral Resources and Reserves, Definitions and Guidelines
prepared by the CIM Standing Committee on Reserve Definitions
and adopted by CIM council.
The PEA assumes the start of the open pit mining operations at an
average annual process plant production rate of two million tonnes per
annum over a mine life of approximately 9.5 years. The envisaged mining
operation is a conventional open pit. Mining operations will reach a
sustained total annual material movement of 11.6 million tonnes using
11.5-cubic-metre diesel hydraulic excavators, 90-tonne haulage trucks and track-mounted
diesel powered drill rigs with up to 100-millimetre diameter blastholes drilled
on six-metre high benches.
The mined material will be processed at a new 6,000 tonnes per day
flotation plant located on the project site. Three concentrates will be produced: 1) copper-silver; 2) lead-silver;
and 3) zinc-silver. It is anticipated that the concentrates could be
processed at the nearby Belledune smelter or other suitable facilities.
Site infrastructure
The project will benefit from infrastructure, services and skilled
labour available in the Bathurst mining camp. The Murray Brook project
site is located 60 kilometres west of the city of Bathurst and is accessible
year-round from paved Provincial Highway 180 and a 6.5 km gravel access
road. Project site infrastructure is anticipated to include:
-
Plant site and haul roads;
-
Administration buildings and assay lab;
-
Mine maintenance garage, warehouse and fuel storage facilities;
-
Fresh water supply and sewage treatment; and
-
Lined tailings storage area.
The proposed Murray Brook project mill and mine site is ideally located
on the access road to the open pit area. The proposed processing plant site is located on a ridge overlooking a
valley about 100 metres below. Several lateral ridges form natural
containment dikes for at least two sides of a tailings management
facility. Power to the site will be supplied by a 12 km long
transmission line connecting to the Caribou mine site and provincial
grid.
The labour force for the construction and operation of this project is
anticipated to be drawn from the Bathurst area. The labour pool in this
area is highly skilled and experienced in construction projects and
mining operations.
Financial assumptions and results
Total operating costs during the life of mine is illustrated in the attached table.
PROJECTION OF TOTAL OPERATING COSTS
DURING THE LIFE OF MINE,
MURRAY BROOK PROJECT
Mining cost $/t material $2.30
Processing cost $/t ore $14.25
G&A M$/year $2.50
Capital costs are categorized as initial project capital and sustaining
capital. Initial project capital consists primarily of mining
equipment, process plant and ancillary plant construction, initial
tailing storage, facility construction, an allowance for water
treatment and local infrastructure. Sustaining capital consists of
further additions to mining equipment during production and
environmental and closure costs.
INITIAL PROJECT AND SUSTAINING CAPITAL
OF MURRAY BROOK PROJECT TOTAL
(thousands of dollars)
Initial project capital
Mine prestripping $8,707
Mining capital cost $33,706
Process plant $104,184
Infrastructure $35,000
Indirects $44,000
Contingency $35,257
Total initial project capital $260,854
Sustaining capital
Mine $10,137
Process plant $2,100
Environmental and reclamation $60,800
Contingency (sustaining) $927
Total sustaining capex $73,964
Total capital $334,818
Metal prices used in the PEA are based on the April 30, 2013, three-year
trailing prices which are listed in the attached table.
METAL PRICES USED IN THIS STUDY
Metal prices (US$) Unit
Copper 3.70 lb
Lead 1.00 lb
Zinc 0.94 lb
Gold 1,540 oz
Silver 30.09 oz
Exchange rate: $1 (U.S.)
is equal to $1 (Canadian)
Project and exploration upside
Further technical studies on the Murray Brook project will focus on
additional metallurgical studies designed to evaluate potential
techniques of improving metal recoveries. The first step is a small
pilot plant project proposal to test three to five tonnes of drill core
material.
The largest impact on the potential value of the Murray Brook project is
likely to be achieved by increasing the mineral resource base available
for mining, thereby increasing the mine life and (or) annual mill
throughput. Excellent potential exists for additional discoveries along
and adjacent to the favourable geological horizon which extends from
the former Restigouche mine to the west of the Murray Brook deposit
deposit to Trevali's Caribou deposit 11 km to the east. An exploration
success on this stretch of productive stratigraphy could significantly
increase the scale of the Murray Brook project prior to development. A
2,000-metre exploration program is proposed to drill test five priority
geophysical and geochemical anomalies this summer.
Qualified persons statement
The PEA was prepared under the supervision of Eugene Puritch, PEng, of
P&E Mining Consultants Inc. Mr. Puritch is an independent QP in
accordance with NI 43-101 and has reviewed and approved the technical
information in this
release. The information in this release was reviewed
by Dr. William Stone, executive vice-president of
exploration of ELN and a qualified person as defined by NI43-101.
About El Nino Ventures Inc. Bathurst projects
El Nino Ventures Inc. has two active projects in the Bathurst mining
camp.
Murray Brook project
The Murray Brook property is located 60 km west of Bathurst and a portion of
the property is underlain by the Murray Brook polymetallic massive
sulphide deposit. The property is supported by excellent nearby
infrastructure, including paved roads, grid electricity and communities
to provide goods, services and skilled labour.
ELN and Votorantim Metals Canada Inc. (VMC, which is the operator of the
joint venture project) currently own 70 per cent of the project, of which 35 per cent
is held by each of the two parties. Under a purchase agreement signed
by VMC on Aug. 28, 2012, with Murray Brook Minerals and Murray Brook
Resources Inc., VMC acquired the right to
purchase the additional 30 per cent of the Murray Brook project from the
owners. The purchase agreement between VMC and the owners provides for
a series of staged payments totalling $6-million over a five-year period
and provides for a 0.25-per-cent net smelter returns royalty payable to the owners after one year of
commercial production.
VMC provided ELN the option to purchase an additional 15 per cent in the
project as required by an underlying amending agreement dated Sept. 30, 2010, between Xstrata Zinc (now Glencore Xstrata PLC), VMC and ELN
(see reference to the triparty agreement immediately below). ELN did
not elect to exercise the option and consequently at this time the
joint venture remains at VMC 65 per cent: ELN 35 per cent.
To date, more than 28,000 metres of drilling have been completed with
encouraging results. In February, 2012, NI 43-101 resource estimation
was announced (see news release). The technical report is filed on SEDAR and also available on ELN's website. The new preliminary economic assessment report, PEA, will be filed on
SEDAR within 45 days of the date of this press release.
Bathurst mining camp project (triparty agreement)
This project consists of an initial 4,712 claims in the triparty agreement with
Xstrata Zinc (now Glencore Xstrata) and VM Canada, whereby VM Canada
may incur exploration expenditures of $10-million over a period of five years to earn a 50-per-cent interest. VM Canada may further increase its
interest to 70 per cent by spending an additional $10-million over two years.
Drilling and further exploration activities have been planned for 2013.
Votorantim Metals Canada Inc. statement
Technical details in this news release were provided by VMC, the professional geologists of which conduct operations consistent with mineral
industry best practices. VMC accepts no responsibility for this news
release or any inferences made from the technical details provided
herein.
We seek Safe Harbor.
© 2026 Canjex Publishing Ltd. All rights reserved.